An update on the Golden Ears Bridge construction given to Township of Langley Council at its June 23, 2008 meeting.

An update on the Golden Ears Bridge construction given to Township of Langley Council at its June 23, 2008 meeting.

Published in Technology
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Be the first to comment
No Downloads

Views

Total Views
1,292
On SlideShare
0
From Embeds
0
Number of Embeds
0

Actions

Shares
Downloads
25
Comments
0
Likes
1

Embeds 0

No embeds

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
    No notes for slide

Transcript

  • 1. Project Update Township of Langley June 23, 2008
  • 2. Presentation Outline
    • Main Bridge
    • Langley components
    • Noise mitigation
    • Public information
  • 3. Project Plan
  • 4. Main Bridge status
    • On track for opening summer 2009
    • First span closed from Fraser River pier M2 to south approach (Langley)
    • Second span (M2 to M3) to be closed about August 1
    • M2 tower is completed to full height
    • Deck panel installation and concrete pouring to continue through 2008.
  • 5. Main Bridge from Langley Shore June 18 2007
  • 6. Main Bridge Linked to South Approach At Langley Dyke , June 18 2007
  • 7. Main Bridge Deck Looking South June 18 2007
  • 8. M2 and M3 from Barnston Island June 18 2007
  • 9. Langley Components
  • 10. Westcon Section Westcon Overpass Substantially Complete Telegraph Trail Realignment Under Construction
  • 11. Southern Bridge Approach and Ramps Southern Bridge Approach Deck Pouring 201 Street On-Ramp Deck Pouring 199 Street Ramp Deck Panels
  • 12. South Approach from Main Bridge with Colossus Theatre June 18 2008
  • 13. Northwest Langley Streets 200 St Improvements/ Re-Laning July-August 2008 96 Avenue area Top Lift Paving Underway 201 St. North Upgrade Open to Traffic by end of July 96 Avenue area Top Lift Paving Underway 96 Avenue area Top Lift Paving Underway
  • 14. 201 Street North of CN Tracks June 18 2008
  • 15. 96 Avenue – New Median Island June 18 2007
  • 16. Paving, 200 Street June 18 2007
  • 17. Noise mitigation
    • TransLink & GCCJV are committed to construction of noise barriers near:
      • 200 Street - Forest Green Estates (Langley)
      • 201 Street at Telep Avenue (Maple Ridge)
      • Wildwood Crescent (Pitt Meadows)
    • TransLink has accepted GCCJV noise study concluding that, asied from above areas, no further noise mitigation is required under project agreement.
  • 18. Noise mitigation – 200 Street, Langley
  • 19. Interpretive Panel, Main Bridge Pathway
  • 20. Public Information
    • Average 60 calls/e-mails per month to public information line; about a third are related to construction issues
    • Mailings to residences and businesses with contact information
    • Traffic bulletins to news media, local governments and police; advisories in community papers