Your SlideShare is downloading. ×
02 pmp project life cycle exam
Upcoming SlideShare
Loading in...5
×

Thanks for flagging this SlideShare!

Oops! An error has occurred.

×
Saving this for later? Get the SlideShare app to save on your phone or tablet. Read anywhere, anytime – even offline.
Text the download link to your phone
Standard text messaging rates apply

02 pmp project life cycle exam

552
views

Published on

PMP Exqam Preparation by: Jamil Faraj

PMP Exqam Preparation by: Jamil Faraj

Published in: Technology, Business

0 Comments
1 Like
Statistics
Notes
  • Be the first to comment

No Downloads
Views
Total Views
552
On Slideshare
0
From Embeds
0
Number of Embeds
0
Actions
Shares
0
Downloads
0
Comments
0
Likes
1
Embeds 0
No embeds

Report content
Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
No notes for slide

Transcript

  • 1. 54   Chapter 2exam questions1. Which of the following is NOT a Project Constraint?QualityA. ScaleB. TimeC. CostD. 2. A project manager is running a data center installation project. He finds that his stakeholder isangry because he’s run over his budget because the staff turned out to be more expensive thanplanned. The stakeholder’s unhappy that when the project is over, the servers won’t have as muchdrive space as he needs. Which of the following constraints was not affected by this problem?QualityA. ResourceB. TimeC. D. Cost3. Which of the following is NOT an example of operational work?Building a purchase order system for accounts payableA. Submitting weekly purchase orders through a purchase order systemB. Deploying weekly anti-virus software updatesC. Yearly staff performance evaluationsD. 4. You’re managing a project to build a new accounting system. One of the accountants in anotherdepartment really likes the current system and is refusing to be trained on the new one. What isthe BEST way to handle this situation?Refuse to work with him because he’s being difficultA. Appeal to the accountant’s manager and ask to have him required to take trainingB. Get a special dispensation so that the accountant doesn’t have to go to the trainingC. Work with him to understand his concerns and do what you can to help alleviate them withoutD. compromising your project5. Which of the following is used for identifying people who are impacted by the project?Resource ListA. Stakeholder RegisterB. Enterprise Environmental FactorsC. Project PlanD. Exam QuestionsDownload at Boykma.Com
  • 2. you are here 4   55organizations, constraints, and projects6. Your manager asks you where to find a list of projects that should be managed together. What isthe BEST place to find this information?Project PlanA. Project CharterB. Portfolio CharterC. Program CharterD. 7. You want to know specifically which business goal a group of projects and programs are going toaccomplish. Which is the best place to look for this information?Project PlanA. Project CharterB. Portfolio CharterC. Program CharterD. 8. A project coordinator is having trouble securing programmers for her project. Every time she asksher boss to give a resource to the project he says that they are too busy to help out with her project.Which type of organization is she working in?FunctionalA. Weak MatrixB. Strong MatrixC. ProjectizedD. 9. A project manager is having trouble securing programmers for her project. Every time she asksthe programming manager for resources for her project, he says they’re all assigned to other work.So she is constantly having to go over his head to overrule him. Which type of organization is sheworking for?FunctionalA. Weak MatrixB. Strong MatrixC. ProjectizedD. Exam QuestionsDownload at Boykma.Com
  • 3. 56   Chapter 2exam answersExam QuestionsAnswers1. Answer: BScale is not a project constraint. The constraints are Scope, Time, Cost, Quality, Resource, and Risk.2. Answer: CThere is no mention of the project being late or missing its deadlines in the example. The project was overbudget, which affects the project’s cost. The project won’t meet the stakeholder’s requirements, which is aquality problem. And the staff was more expensive than planned, which is a resource problem.3. Answer: ABuilding a purchase order system for accounts payable is a project. It’s a temporary effort that has a uniqueresult.4.Answer: DWhen a stakeholder is negatively impacted by your project, you need to manage his expectations and helphim to buy into your project.5. Answer: BThe stakeholder register is where you identify all of the people who are impacted by your project.6. Answer: DA program is a group of projects that should be managed together because of interdependencies. Aprogram charter fits the description in this question.7. Answer: CA portfolio charter will give the business goal that a group of projects and programs will accomplish as partof a portfolio.Download at Boykma.Com
  • 4. you are here 4   57organizations, constraints, and projects8. Answer: ASince the project manager has to ask permission from the functional manager and can’t overrule him, she’sworking in a functional organization.9. Answer: CThe Project Manager in this scenario can overrule the functional manager, so she’s working in a Strong Matrixorganization. If it were a projectized organization, she wouldn’t have to get permission from the functionalmanager at all because she’d be the person with authority to assign resources to projects.Exam QuestionsAnswersDownload at Boykma.Com

×