Flow of Presentation
 Substation Introduction
 Classification of substations
 Transformer substation
 Pole mounted substation
 Underground substation
 Power factor correction substation
 Frequency changer substation
 SUB-STATION EQUIPMENTS & ITS FUNCTIONS
1
Introduction
Sub-stations:- The assembly of
apparatus used to change some
characteristic (voltage ,a.c to d.c,
frequency, power factor, etc)of electrical
supply is called a Sub-stations.
3
A Substation should be-
Located at a proper site and at the center of gravity
of load.
Easily operated and maintained.
Involve minimum capital cost.
For safety, consideration must be given to the
maintenance of regulation clearances, facilities for
carrying out repairs and maintenance, abnormal
occurrences such as possibility of explosion or fire
etc .
For reliability, consideration must be given for good
design and construction, the provision of suitable
protective gear etc.
4
Classification of sub-
stations
According to service requirement
Transformer sub-stations.
Switching sub-stations.
Power factor correction sub-stations.
Frequency changer sub-stations.
converting sub-stations.
Industrial sub-stations
According to construction
Indoor sub-stations.
Outdoor sub-stations.
Underground sub-stations.
Pole-mounted sub-station.
5
Transformer sub-stations
They are concern with the
changing of voltage level
The majority of sub-stations in
power system are or transformer
type
Types
1. Step up sub-stations
2. Primary grid sub-stations
3. Secondary sub-stations
4. Distribution sub-stations
6
7
Gs
11 kv
Step up sub-
stations
11/220kv
Primary grid
Substations
220/66kv
Secondary sub-
stations
66/11kv
Secondary sub-
stations
66/11kv
Distribution
sub-stations
11/0.4kv
Distribution
sub-
stations
11/0.4kv
Distribution
sub-
stations
11/0.4kv
High voltage
11kv consumer
High voltage
11kv consumer
Typical electrical supply system
Step Up Substation
Step up substations are associated with generating stations. Generation
of power is limited to low voltage levels due to limitations of the rotating
alternators. These generating voltages must be stepped up for
economical transmission of power over long distance. So there must be a
step up substation associated with generating station.
Primary Step Down Substation:
The primary step down sub stations are created nearer to load center
along the primary transmission lines. Here primary transmission voltages
are stepped down to different suitable voltages for secondary
transmission purpose.
Secondary Step Down Substation
Along the secondary transmission lines, at load center, the secondary
transmission voltages are further stepped down for primary distribution
purpose. The stepping down of secondary transmission voltages to
primary distribution levels are done at secondary step down substation.
Distribution Substation
Distribution substation are situated where the primary distribution
voltages are stepped down to supply voltages for feeding the actual
consumers through a distribution network. 8
Pole-mounted sub-station
Pole mounted substation are mainly
distribution substation constructed
on two pole, four pole and
sometime six or more poles
structures.
In these type of substation fuse
protected distribution transformer
are mounted on poles along with
electrical isolator switches.
The 11 kV line is connected to the
transformer through gang isolator
and fuses.
The lightning arresters are installed
on the H.T. side to protect the sub-
station from lightning strokes. The
transformer steps down the voltage
to 400V, 3-phase, 4-wire supply
. The oil circuit breaker (O.C.B.)
installed on the L.T. side
automatically isolates the
transformer from
9
Underground Substation
Underground sub-ststion
The substation are
situated at underground
is called underground
substation.
In congested places
where place for
constructing distribution
substation is difficult to
find out, one can go for
underground sub –
station scheme.
10
The following points must be kept in view while laying
out underground sub-station
1. Size of station should be as minimum as possible.
2. There should be reasonable access for both
equipment and personnel.
3. There should be good ventilation.
4. There should be provision for remote indication of
excessive rise in temperature so that H.V.
5. The transformers, switches and fuses should be air
cooled to avoid bringing oil into the premises.
6. There should be provision for emergency lighting and
protection against fire.
11
Power factor correction sub-
stations. Those sub-stations which
improve the power factor of
the system are called power
factor correction sub-stations.
Such sub-stations are
generally located at the
receiving end of transmission
lines. These sub-stations
generally use synchronous
condensers as the power
factor improvement
equipment.
12
Power factor correction sub-stations
Frequency changer substation
. Those sub-stations
which change the
supply frequency are
known as frequency
changer sub-
stations. Such a
frequency change
may be required for
industrial utilisation.
13
SUB-STATION EQUIPMENTS & ITS
FUNCTIONS
Lightening Arrester
Lightening arrestors are the instrument that are used in
the incoming feeders so that to prevent the high voltage
entering the main station. This high voltage is very
dangerous to the instruments used in the substation.
Even the instruments are very costly, so to prevent any
damage lightening arrestors are used. The lightening
arrestors do not let the lightening to fall on the station.
Bus-bars.
When a number of lines operating at the same voltage
have to be directly connected electrically, bus-bars are
used as the common electrical component. Bus-bars are
copper or aluminium bars (generally of rectangular x-
section) and operate at constant voltage. The incoming
and outgoing lines in a sub-station are connected to the
bus-bars. 14
Isolator
The use of this isolator is to protect the transformer
and the other instrument in the line. The isolator
isolates the extra voltage to the ground and thus any
extra voltage cannot enter the line. Thus an isolator is
used after the bus also for protection.
Circuit Breaker
The circuit breakers are used to break the circuit if
any fault occurs in any of the instrument. These circuit
breaker breaks for a fault which can damage other
instrument in the station. For any unwanted fault over
the station we need to break the line current. This is
only done automatically by the circuit breaker. There
are mainly two types of circuit breakers used for any
substations. They are
a. SF6 circuit breakers
b. Spring circuit breakers.
15
Potential Transformer
There are two potential transformers used in the bus
connected both side of the bus. The potential
transformer uses a bus isolator to protect itself. The
main use of this transformer is to measure the voltage
through the bus. This is done so as to get the detail
information of the voltage passing through the bus to
the instrument.
Voltage transformer.
It is essentially a step down transformer and steps
down the voltage to a known ratio. The primary of this
transformer consists of a large number of turns of fine
wire connected across the line. The secondary winding
consists of a few turns and provides for measuring
instruments and relays a voltage which is a known
fraction of the line voltage.
16
Current transformer (C.T.).
A current transformer in essentially a step-up
transformer which steps down the current to a known
ratio. The primary of this transformer consists of one or
more turns of thick wire connected in series with the
line. The secondary consists of a large number of turns
of fine wire and provides for the measuring instruments
and relays a current which is a constant fraction of the
current in the line.
. Miscellaneous equipment.
In addition to above, there may be following
equipment in a sub-station :
( i) fuses
( ii) carrier-current equipment
( iii) sub-station auxiliary supplies
17
THE
END
18

More Related Content

What's hot

220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54Subhash Mahla
 
Sub station training ppt
Sub station training pptSub station training ppt
Sub station training pptsitesh95074
 
Electrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakirElectrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakirSheikh Shakir
 
PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substationIshank Ranjan
 
substation internship report
substation internship report substation internship report
substation internship report Arun Thapa
 
Design of substation (with Transformer Design)
Design of substation (with Transformer Design) Design of substation (with Transformer Design)
Design of substation (with Transformer Design) SayanSarkar55
 
presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.Hemendra Kumar Rajput
 
220KV Substation Training Report
220KV Substation Training Report220KV Substation Training Report
220KV Substation Training ReportSWAPNILKUMARGUPTA
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1Md Irshad Ahmad
 
Understanding transformer vector group
Understanding transformer vector groupUnderstanding transformer vector group
Understanding transformer vector groupShyamkant Vasekar
 
Presentation on 132/33 KVSubstation Training
Presentation on 132/33 KVSubstation Training Presentation on 132/33 KVSubstation Training
Presentation on 132/33 KVSubstation Training Sakshi Rastogi
 
PPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATIONPPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATIONRavi Phadtare
 
132 kv g.s.s chambal jaipur
132 kv g.s.s chambal jaipur132 kv g.s.s chambal jaipur
132 kv g.s.s chambal jaipurmonga786
 
Power system protection topic 1
Power system protection topic 1Power system protection topic 1
Power system protection topic 1Siswoyo Edo
 
132KV SUBSTATION UPPTCL
132KV SUBSTATION UPPTCL132KV SUBSTATION UPPTCL
132KV SUBSTATION UPPTCLAman Rajput
 

What's hot (20)

220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
 
Sub station training ppt
Sub station training pptSub station training ppt
Sub station training ppt
 
Electrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakirElectrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakir
 
SWITCHGEAR
SWITCHGEARSWITCHGEAR
SWITCHGEAR
 
PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substation
 
substation internship report
substation internship report substation internship report
substation internship report
 
Substation
Substation Substation
Substation
 
Design of substation (with Transformer Design)
Design of substation (with Transformer Design) Design of substation (with Transformer Design)
Design of substation (with Transformer Design)
 
presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.
 
220KV Substation Training Report
220KV Substation Training Report220KV Substation Training Report
220KV Substation Training Report
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1
 
Substation
SubstationSubstation
Substation
 
Understanding transformer vector group
Understanding transformer vector groupUnderstanding transformer vector group
Understanding transformer vector group
 
Presentation on 132/33 KVSubstation Training
Presentation on 132/33 KVSubstation Training Presentation on 132/33 KVSubstation Training
Presentation on 132/33 KVSubstation Training
 
Switch yard & Protection
Switch yard & ProtectionSwitch yard & Protection
Switch yard & Protection
 
PPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATIONPPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATION
 
132 kv g.s.s chambal jaipur
132 kv g.s.s chambal jaipur132 kv g.s.s chambal jaipur
132 kv g.s.s chambal jaipur
 
Power system protection topic 1
Power system protection topic 1Power system protection topic 1
Power system protection topic 1
 
132KV SUBSTATION UPPTCL
132KV SUBSTATION UPPTCL132KV SUBSTATION UPPTCL
132KV SUBSTATION UPPTCL
 
Earthing system
Earthing system   Earthing system
Earthing system
 

Viewers also liked

Estimation of a_pole_mounted_substation
Estimation of a_pole_mounted_substationEstimation of a_pole_mounted_substation
Estimation of a_pole_mounted_substationSupardi Amaludin
 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV Girish Gupta
 
33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)Prateek Agarwal
 
Typical layout of a Sub-Station
Typical layout of a Sub-StationTypical layout of a Sub-Station
Typical layout of a Sub-StationTowfiqur Rahman
 
Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.Avirup Ghosh
 
Report on Industrial Visit
Report on Industrial VisitReport on Industrial Visit
Report on Industrial VisitBhavik Vadiya
 
B tech ee ii_ eee_ u-4_ transformer & electrical wiring_dipen patel
B tech ee  ii_ eee_ u-4_ transformer & electrical wiring_dipen patelB tech ee  ii_ eee_ u-4_ transformer & electrical wiring_dipen patel
B tech ee ii_ eee_ u-4_ transformer & electrical wiring_dipen patelRai University
 
132 gss ppt
132 gss ppt132 gss ppt
132 gss ppthunk143
 
Ppt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipurPpt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipurkishankky
 

Viewers also liked (20)

ppt
pptppt
ppt
 
Estimation of a_pole_mounted_substation
Estimation of a_pole_mounted_substationEstimation of a_pole_mounted_substation
Estimation of a_pole_mounted_substation
 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV
 
33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)
 
Substation
SubstationSubstation
Substation
 
Power factor improvement
Power factor improvementPower factor improvement
Power factor improvement
 
Substation overview
Substation overviewSubstation overview
Substation overview
 
Typical layout of a Sub-Station
Typical layout of a Sub-StationTypical layout of a Sub-Station
Typical layout of a Sub-Station
 
Jd deisgn electrcial
Jd deisgn electrcialJd deisgn electrcial
Jd deisgn electrcial
 
GTC
GTCGTC
GTC
 
Siri Nota Prosedur PPU (preview)
Siri Nota Prosedur PPU (preview)Siri Nota Prosedur PPU (preview)
Siri Nota Prosedur PPU (preview)
 
Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.
 
Wiring system
Wiring systemWiring system
Wiring system
 
Report on Industrial Visit
Report on Industrial VisitReport on Industrial Visit
Report on Industrial Visit
 
B tech ee ii_ eee_ u-4_ transformer & electrical wiring_dipen patel
B tech ee  ii_ eee_ u-4_ transformer & electrical wiring_dipen patelB tech ee  ii_ eee_ u-4_ transformer & electrical wiring_dipen patel
B tech ee ii_ eee_ u-4_ transformer & electrical wiring_dipen patel
 
GIS-NESCL-6
GIS-NESCL-6GIS-NESCL-6
GIS-NESCL-6
 
132 gss ppt
132 gss ppt132 gss ppt
132 gss ppt
 
Wiring systems
Wiring systemsWiring systems
Wiring systems
 
Ppt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipurPpt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipur
 
Electrical wiring
Electrical wiringElectrical wiring
Electrical wiring
 

Similar to Substations

Substation equipment and its function 2
Substation equipment and its function 2Substation equipment and its function 2
Substation equipment and its function 2Zulfiqar Mangrio
 
66%20Industrial%20Visit%20Report.docx
66%20Industrial%20Visit%20Report.docx66%20Industrial%20Visit%20Report.docx
66%20Industrial%20Visit%20Report.docxdnyaneshwarvidhate2
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at JassureShuvam Pathania
 
Substation equipments & its functions
Substation equipments & its functionsSubstation equipments & its functions
Substation equipments & its functionsMonzer Abdallah Eisa
 
LEC - 2 (SUBSTATIONS).pdf
LEC - 2 (SUBSTATIONS).pdfLEC - 2 (SUBSTATIONS).pdf
LEC - 2 (SUBSTATIONS).pdfHASNAINNAZIR1
 
Report On Industrial Tour At Khulshi Grid Sub-Station
Report On Industrial Tour At Khulshi Grid Sub-StationReport On Industrial Tour At Khulshi Grid Sub-Station
Report On Industrial Tour At Khulshi Grid Sub-StationEkram Bin Mamun
 
Load Distribution
Load DistributionLoad Distribution
Load DistributionArpit Gupta
 
Power Corporation ppt
Power Corporation pptPower Corporation ppt
Power Corporation pptKamal Tiwari
 
Uttar pradesh power corporation limited
Uttar pradesh power corporation limitedUttar pradesh power corporation limited
Uttar pradesh power corporation limitedVSRAGHU
 
Presentation 2014
Presentation 2014Presentation 2014
Presentation 2014pinki199319
 
Report on Industrial Visit at Pahartali Textile and Hosiery Mills of M.M. Isp...
Report on Industrial Visit at Pahartali Textile and Hosiery Mills of M.M. Isp...Report on Industrial Visit at Pahartali Textile and Hosiery Mills of M.M. Isp...
Report on Industrial Visit at Pahartali Textile and Hosiery Mills of M.M. Isp...Ekram Bin Mamun
 
ELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFjang041
 
Seminar Report on 220 KV Grid Sub Station on Bundi
Seminar Report on 220 KV  Grid Sub Station on Bundi Seminar Report on 220 KV  Grid Sub Station on Bundi
Seminar Report on 220 KV Grid Sub Station on Bundi SahilQureshi14
 
Indusrtrial training ppt (1).pptx
Indusrtrial training ppt (1).pptxIndusrtrial training ppt (1).pptx
Indusrtrial training ppt (1).pptxSNEHAKANWAR1
 
Vocational Training Report ( Sealdah Power House)
Vocational Training Report ( Sealdah Power House)Vocational Training Report ( Sealdah Power House)
Vocational Training Report ( Sealdah Power House)shovandey07
 

Similar to Substations (20)

Substations
Substations Substations
Substations
 
Substation equipment and its function 2
Substation equipment and its function 2Substation equipment and its function 2
Substation equipment and its function 2
 
132kV GSS ppt
132kV GSS ppt132kV GSS ppt
132kV GSS ppt
 
66%20Industrial%20Visit%20Report.docx
66%20Industrial%20Visit%20Report.docx66%20Industrial%20Visit%20Report.docx
66%20Industrial%20Visit%20Report.docx
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at Jassure
 
Substation equipments & its functions
Substation equipments & its functionsSubstation equipments & its functions
Substation equipments & its functions
 
LEC - 2 (SUBSTATIONS).pdf
LEC - 2 (SUBSTATIONS).pdfLEC - 2 (SUBSTATIONS).pdf
LEC - 2 (SUBSTATIONS).pdf
 
Report On Industrial Tour At Khulshi Grid Sub-Station
Report On Industrial Tour At Khulshi Grid Sub-StationReport On Industrial Tour At Khulshi Grid Sub-Station
Report On Industrial Tour At Khulshi Grid Sub-Station
 
Load Distribution
Load DistributionLoad Distribution
Load Distribution
 
Chic export company_catalogue
Chic export company_catalogueChic export company_catalogue
Chic export company_catalogue
 
Power Corporation ppt
Power Corporation pptPower Corporation ppt
Power Corporation ppt
 
Uttar pradesh power corporation limited
Uttar pradesh power corporation limitedUttar pradesh power corporation limited
Uttar pradesh power corporation limited
 
Presentation 2014
Presentation 2014Presentation 2014
Presentation 2014
 
Report on Industrial Visit at Pahartali Textile and Hosiery Mills of M.M. Isp...
Report on Industrial Visit at Pahartali Textile and Hosiery Mills of M.M. Isp...Report on Industrial Visit at Pahartali Textile and Hosiery Mills of M.M. Isp...
Report on Industrial Visit at Pahartali Textile and Hosiery Mills of M.M. Isp...
 
ELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEF
 
Current Transformer.pptx
Current Transformer.pptxCurrent Transformer.pptx
Current Transformer.pptx
 
Seminar Report on 220 KV Grid Sub Station on Bundi
Seminar Report on 220 KV  Grid Sub Station on Bundi Seminar Report on 220 KV  Grid Sub Station on Bundi
Seminar Report on 220 KV Grid Sub Station on Bundi
 
Indusrtrial training ppt (1).pptx
Indusrtrial training ppt (1).pptxIndusrtrial training ppt (1).pptx
Indusrtrial training ppt (1).pptx
 
Vocational Training Report ( Sealdah Power House)
Vocational Training Report ( Sealdah Power House)Vocational Training Report ( Sealdah Power House)
Vocational Training Report ( Sealdah Power House)
 
Shashikdoc
ShashikdocShashikdoc
Shashikdoc
 

More from itfakash

KASHUP Wheels - A hybrid segway Report
KASHUP Wheels - A hybrid segway ReportKASHUP Wheels - A hybrid segway Report
KASHUP Wheels - A hybrid segway Reportitfakash
 
Segway self balancing scooter
Segway self balancing scooterSegway self balancing scooter
Segway self balancing scooteritfakash
 
A report on ultrasonic distance measurement
A report on ultrasonic distance measurementA report on ultrasonic distance measurement
A report on ultrasonic distance measurementitfakash
 
A report on Rf controlled car
A report on Rf controlled car A report on Rf controlled car
A report on Rf controlled car itfakash
 
A report on Antibiotics
A report on AntibioticsA report on Antibiotics
A report on Antibioticsitfakash
 

More from itfakash (6)

SEGWAY
SEGWAY SEGWAY
SEGWAY
 
KASHUP Wheels - A hybrid segway Report
KASHUP Wheels - A hybrid segway ReportKASHUP Wheels - A hybrid segway Report
KASHUP Wheels - A hybrid segway Report
 
Segway self balancing scooter
Segway self balancing scooterSegway self balancing scooter
Segway self balancing scooter
 
A report on ultrasonic distance measurement
A report on ultrasonic distance measurementA report on ultrasonic distance measurement
A report on ultrasonic distance measurement
 
A report on Rf controlled car
A report on Rf controlled car A report on Rf controlled car
A report on Rf controlled car
 
A report on Antibiotics
A report on AntibioticsA report on Antibiotics
A report on Antibiotics
 

Recently uploaded

Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptJasonTagapanGulla
 

Recently uploaded (20)

Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.ppt
 

Substations

  • 1. A PRESENTATION ON Sub-Stations GTU, Ahmedabad Venus International College Of Technology Prepared by V EEE Patel Akash R En.120810108014 Patel Uttam En.120810108006 Patel Yash En.120810108011 Patel Sujal En.120810108004
  • 2. Flow of Presentation  Substation Introduction  Classification of substations  Transformer substation  Pole mounted substation  Underground substation  Power factor correction substation  Frequency changer substation  SUB-STATION EQUIPMENTS & ITS FUNCTIONS 1
  • 3. Introduction Sub-stations:- The assembly of apparatus used to change some characteristic (voltage ,a.c to d.c, frequency, power factor, etc)of electrical supply is called a Sub-stations. 3
  • 4. A Substation should be- Located at a proper site and at the center of gravity of load. Easily operated and maintained. Involve minimum capital cost. For safety, consideration must be given to the maintenance of regulation clearances, facilities for carrying out repairs and maintenance, abnormal occurrences such as possibility of explosion or fire etc . For reliability, consideration must be given for good design and construction, the provision of suitable protective gear etc. 4
  • 5. Classification of sub- stations According to service requirement Transformer sub-stations. Switching sub-stations. Power factor correction sub-stations. Frequency changer sub-stations. converting sub-stations. Industrial sub-stations According to construction Indoor sub-stations. Outdoor sub-stations. Underground sub-stations. Pole-mounted sub-station. 5
  • 6. Transformer sub-stations They are concern with the changing of voltage level The majority of sub-stations in power system are or transformer type Types 1. Step up sub-stations 2. Primary grid sub-stations 3. Secondary sub-stations 4. Distribution sub-stations 6
  • 7. 7 Gs 11 kv Step up sub- stations 11/220kv Primary grid Substations 220/66kv Secondary sub- stations 66/11kv Secondary sub- stations 66/11kv Distribution sub-stations 11/0.4kv Distribution sub- stations 11/0.4kv Distribution sub- stations 11/0.4kv High voltage 11kv consumer High voltage 11kv consumer Typical electrical supply system
  • 8. Step Up Substation Step up substations are associated with generating stations. Generation of power is limited to low voltage levels due to limitations of the rotating alternators. These generating voltages must be stepped up for economical transmission of power over long distance. So there must be a step up substation associated with generating station. Primary Step Down Substation: The primary step down sub stations are created nearer to load center along the primary transmission lines. Here primary transmission voltages are stepped down to different suitable voltages for secondary transmission purpose. Secondary Step Down Substation Along the secondary transmission lines, at load center, the secondary transmission voltages are further stepped down for primary distribution purpose. The stepping down of secondary transmission voltages to primary distribution levels are done at secondary step down substation. Distribution Substation Distribution substation are situated where the primary distribution voltages are stepped down to supply voltages for feeding the actual consumers through a distribution network. 8
  • 9. Pole-mounted sub-station Pole mounted substation are mainly distribution substation constructed on two pole, four pole and sometime six or more poles structures. In these type of substation fuse protected distribution transformer are mounted on poles along with electrical isolator switches. The 11 kV line is connected to the transformer through gang isolator and fuses. The lightning arresters are installed on the H.T. side to protect the sub- station from lightning strokes. The transformer steps down the voltage to 400V, 3-phase, 4-wire supply . The oil circuit breaker (O.C.B.) installed on the L.T. side automatically isolates the transformer from 9
  • 10. Underground Substation Underground sub-ststion The substation are situated at underground is called underground substation. In congested places where place for constructing distribution substation is difficult to find out, one can go for underground sub – station scheme. 10
  • 11. The following points must be kept in view while laying out underground sub-station 1. Size of station should be as minimum as possible. 2. There should be reasonable access for both equipment and personnel. 3. There should be good ventilation. 4. There should be provision for remote indication of excessive rise in temperature so that H.V. 5. The transformers, switches and fuses should be air cooled to avoid bringing oil into the premises. 6. There should be provision for emergency lighting and protection against fire. 11
  • 12. Power factor correction sub- stations. Those sub-stations which improve the power factor of the system are called power factor correction sub-stations. Such sub-stations are generally located at the receiving end of transmission lines. These sub-stations generally use synchronous condensers as the power factor improvement equipment. 12 Power factor correction sub-stations
  • 13. Frequency changer substation . Those sub-stations which change the supply frequency are known as frequency changer sub- stations. Such a frequency change may be required for industrial utilisation. 13
  • 14. SUB-STATION EQUIPMENTS & ITS FUNCTIONS Lightening Arrester Lightening arrestors are the instrument that are used in the incoming feeders so that to prevent the high voltage entering the main station. This high voltage is very dangerous to the instruments used in the substation. Even the instruments are very costly, so to prevent any damage lightening arrestors are used. The lightening arrestors do not let the lightening to fall on the station. Bus-bars. When a number of lines operating at the same voltage have to be directly connected electrically, bus-bars are used as the common electrical component. Bus-bars are copper or aluminium bars (generally of rectangular x- section) and operate at constant voltage. The incoming and outgoing lines in a sub-station are connected to the bus-bars. 14
  • 15. Isolator The use of this isolator is to protect the transformer and the other instrument in the line. The isolator isolates the extra voltage to the ground and thus any extra voltage cannot enter the line. Thus an isolator is used after the bus also for protection. Circuit Breaker The circuit breakers are used to break the circuit if any fault occurs in any of the instrument. These circuit breaker breaks for a fault which can damage other instrument in the station. For any unwanted fault over the station we need to break the line current. This is only done automatically by the circuit breaker. There are mainly two types of circuit breakers used for any substations. They are a. SF6 circuit breakers b. Spring circuit breakers. 15
  • 16. Potential Transformer There are two potential transformers used in the bus connected both side of the bus. The potential transformer uses a bus isolator to protect itself. The main use of this transformer is to measure the voltage through the bus. This is done so as to get the detail information of the voltage passing through the bus to the instrument. Voltage transformer. It is essentially a step down transformer and steps down the voltage to a known ratio. The primary of this transformer consists of a large number of turns of fine wire connected across the line. The secondary winding consists of a few turns and provides for measuring instruments and relays a voltage which is a known fraction of the line voltage. 16
  • 17. Current transformer (C.T.). A current transformer in essentially a step-up transformer which steps down the current to a known ratio. The primary of this transformer consists of one or more turns of thick wire connected in series with the line. The secondary consists of a large number of turns of fine wire and provides for the measuring instruments and relays a current which is a constant fraction of the current in the line. . Miscellaneous equipment. In addition to above, there may be following equipment in a sub-station : ( i) fuses ( ii) carrier-current equipment ( iii) sub-station auxiliary supplies 17