Matt Lynton, Sydney Trains - Underground telecommunications systems and infrastructure

953 views

Published on

Matt Lynton, Project Delivery Manager, Sydney Trains delivered the presentation at ARA’s Telecommunications & Train Control Conference 2014.

The ARA’s Telecommunications & Train Control Conference 2014 brought together passenger and freight rail operators, transport agencies, track owners, regulators and technology suppliers to assess telecommunications solutions and explored the capabilities of a shared future.

For more information about the event, please visit: http://bit.ly/traincontrol14

Published in: Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
953
On SlideShare
0
From Embeds
0
Number of Embeds
10
Actions
Shares
0
Downloads
31
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Matt Lynton, Sydney Trains - Underground telecommunications systems and infrastructure

  1. 1. 1 Commercial in ConfidenceCommercial in Confidence Mobile Carrier Infrastructure Sydney Rail Tunnels – A Project Review 11th - 12th August 2014
  2. 2. 2 Commercial in Confidence Sydney Trains – a Customer Focus Customer Experience Reliability On Time Running
  3. 3. 3 Commercial in Confidence The Objective Provision of mobility infrastructure to enhance the customers journey in and around the CBD rail tunnels.
  4. 4. 4 Commercial in Confidence The Strategy • Commercial Agreements for delivery • 3 different stages • Design and install a solution to provide the objective. ShoreTunnels CityCircle ESR&IllaRelief
  5. 5. 5 Commercial in Confidence Design Solution • c.1920’s Rail Tunnels • c.1970’s Rail Tunnels
  6. 6. 6 Commercial in Confidence Design Solution • Coverage within Tunnels
  7. 7. 7 Commercial in Confidence Design Solution • Distributed Antenna System (DAS)
  8. 8. 8 Commercial in Confidence Design Approval & Risk Management • System Design • Civil & Track Design • Stakeholder Approval
  9. 9. 9 Commercial in Confidence Implementation & Late Scope • Track Access • Power • Testing Window • North Sydney & Chatswood Rail Box (enclosure) • Signal Risk • Carrier Connection
  10. 10. 10 Commercial in Confidence Commissioning • Testing Process • Nth Sydney Signalling • Transport Ministers Office
  11. 11. 11 Commercial in Confidence Program Awareness • Stage 1 in service • Schedule and Completion dates
  12. 12. 12 Commercial in Confidence Stage 2 • City Circle • Similar design concept
  13. 13. 13 Commercial in Confidence Challenges and Risks • Tunnel Profiling – Older data • Design Approval • Track Access • Continual correspondence with multiple stakeholders
  14. 14. 14 Commercial in Confidence System Performance & Expectations • Stage 1 performance • Technical optimisation • Older technology in Stations
  15. 15. 15 Commercial in Confidence Stage 3 • Eastern Suburbs Railway & Illawarra relief • Similar Design Concept • Station Coverage in scope
  16. 16. 16 Commercial in Confidence Challenges and Risks • Tunnel length • Cost • Track Access - Innovation • Late change of solution
  17. 17. 17 Commercial in Confidence Lessons Learnt • Structured Design Approval process • Strong Milestones • Manage Expectations • Risk & Opportunities
  18. 18. 18 Commercial in Confidence

×