Dudley Ingram - Martinus Rail - Delivering a quality product that lasts longer

441 views
291 views

Published on

Dudley Ingram delivered the presentation at 2014 RISSB National Rail Turnouts Workshop.

The RISSB National Rail Turnouts Workshop gives all those involved an in-depth forum for discussion and the sharing of expertise. A key element of this workshop is participation and knowledge sharing from audience as well as the workshop leaders. It is a chance for you to bring your experience and to take away new approaches for best practice.

For more information about the event, please visit: http://www.informa.com.au/railturnoutsworkshop14

Published in: Engineering, Business, Technology
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
441
On SlideShare
0
From Embeds
0
Number of Embeds
1
Actions
Shares
0
Downloads
13
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Dudley Ingram - Martinus Rail - Delivering a quality product that lasts longer

  1. 1. Delivering a quality product that lasts longer Turnout supply and installation Dudley Ingram 23 May 2014 Brisbane
  2. 2. Turnout design and needs of the customer • Look at needs of the project • Design what is required, not necessarily the newest • Work with the customer • Continued feedback and consultation • Drainage, DRAINAGE + DRAINAGE
  3. 3. Example: Onesteel – Whyalla – Iron Ore Line Project • Complete solution: Design – Supply – Install – Maintain • 56t axle loads
  4. 4. Project management and supply PE continuously working with client • Any modification • Production program • Delivery First article inspections • Steelworks • Concrete Project targets move. Consistent contact ensures requirements are met.
  5. 5. What makes a successful turnout installation • Planning • Pre-build • Plant for project • Staffing • Review your plan
  6. 6. Planning • From award of contract • Possession details • Other works in area • Detailed program • Site planning session • Final decision on installation method Don’t be afraid to attempt new things
  7. 7. Pre-build • Level pre-build area • Dummy rail • Correct plant • Accuracy • Measurements • Documentation
  8. 8. Plant for project • Excavation Plant Installation method • Frannas • Cranes • PEM LEMs
  9. 9. Frannas
  10. 10. Cranes
  11. 11. PEM LEMs
  12. 12. My first installation
  13. 13. Staffing • Shift numbers • Specialist • Survey • Welders • Geotech staff
  14. 14. Review your plan Details change • Possession times • Works around site • Work trains • Conditions PLAN B
  15. 15. Lasting longer
  16. 16. Lasting longer • Recommended maintenance • Follow-up grinding • Drainage DRAINAGE DRAINAGE
  17. 17. Thank you, any questions

×