Fehmarnbelt Fixed Link Tunnel
Alun Thomas
Ramboll

RAMBØLL
ARUP
TEC

Fehmarnbelt Fixed Link – Tunnel Design Services
CONTENT
1. The Project in general
2. The Tunnel
• 
• 
• 
• 

Tunnel Layout
Safety Concept
IMT Design
Construction

4.  Env...
LOCATION

Store Baelt
Link

Øresund Link

Femern Baelt
Link

RAMBØLL
ARUP
TEC

Fehmarnbelt Fixed Link – Tunnel Design Serv...
FEHMARNBELT FIXED LINK
Treaty between Denmark
and Sweden 1991
Trans European Network
priority
Treaty between Denmark
and G...
OVERALL PROGRAMME
February 2011: Minister of Transport selects IMT as preferred solution
for the German Plan Approval proc...
ADDITIONAL LANDWORKS
• 

Railway line Ringsted-Rødby to be electrified

• 

Railway line Rødby–Vordingborg to be expanded ...
Bro COMPETITION BETWEEN TUNNEL
eller Tunnel
AND BRIDGE

RAMBØLL
ARUP
TEC

Fehmarnbelt Fixed Link – Tunnel Design Services
MAIN ALTERNATIVES
Cable Stayed Bridge :

Cable Stayed Bridge :
Feasibility Study :
4,4 bill EUR
Conceptual Design : 5,1 bi...
ALTERNATIVE - BORED TUNNEL

RAMBØLL
ARUP
TEC

Fehmarnbelt Fixed Link – Tunnel Design Services
THE TUNNEL

RAMBØLL
ARUP
TEC

Fehmarnbelt Fixed Link – Tunnel Design Services
PREFERRED ALIGNMENT

• Close to existing
infrastructure
• Rail east of the road,
same as in the hinterland
• Almost straig...
Tunnel Length and Depth

Tunnel Length

18.1 km

Fehmarnbelt Fixed Link
Trans Bay Tube BART Tunnel
Øresund Tunnel

Immerse...
PORTAL AREA - FEHMARN

RAMBØLL
ARUP
TEC

Fehmarnbelt Fixed Link – Tunnel Design Services
PORTAL AREA - LOLLAND

RAMBØLL
ARUP
TEC

Fehmarnbelt Fixed Link – Tunnel Design Services
LAGOON AREA

RAMBØLL
ARUP
TEC

Fehmarnbelt Fixed Link – Tunnel Design Services
ENVIRONMENTAL ISSUES

• Sea water

• Landscape and soil

• Seabed and coasts

• Vegetation on land

• Watercourses and lak...
IMMERSED TUBE TUNNEL DESIGN

RAMBØLL
ARUP
TEC

Fehmarnbelt Fixed Link – Tunnel Design Services
CHOICE OF CROSS SECTIONS

?
RAMBØLL
ARUP
TEC

Fehmarnbelt Fixed Link – Tunnel Design Services
TUNNEL ELEMENTS

Standard
element

Special
element

RAMBØLL
ARUP
TEC

Fehmarnbelt Fixed Link – Tunnel Design Services
SOIL CONDITIONS

RAMBØLL
ARUP
TEC

Fehmarnbelt Fixed Link – Tunnel Design Services

20
Standard element
• 79 Standard elements divided into 9 segments of approx. 24 m,
weight 76.600 tons
• Niche at centre of t...
SPECIAL ELEMENT
• Need for transformers and other M & E equipment in the tunnel
• Standard elements do not have sufficient...
TUNNEL
SPECIAL ELEMENT
•  Size [l/b/h]: 39m/45m/
13m
•  10 Special elements

•  Lay by for parking of
maintenance staff

•...
CONSTRUCTION

RAMBØLL
ARUP
TEC

Fehmarnbelt Fixed Link – Tunnel Design Services
CONTRACT PRINCIPLES
•  Four Civil Works Contracts:
•  Tunnel North
•  Tunnel South
•  Portal Structures and Ramps
•  Dredg...
THE FOUR CIVIL WORK CONTRACTS

IMT North (TUN)
IMT South (TUS)
RAMBØLL
ARUP
TEC

Tunnel Portals & Ramps (TPR)
Dredging & R...
CONSTRUCTION PRINCIPLE FOR
STANDARD ELEMENTS
Production of tunnel elements
for Øresund
- Controlled environment
- Straight...
PRODUCTION SITE - PERSPECTIVE

RAMBØLL
ARUP
TEC

Fehmarnbelt Fixed Link – Tunnel Design Services

28
BASIC DATA
Approximate
numbers

Length of standard tunnel element

217 m

Height of standard tunnel element

8,9 m

Weight...
QUANTITIES FOR STANDARD ELEMENTS
Required materials per week
Concrete

Delivery of concrete

24,000 m³

Reinforcement

3,2...
CONSTRUCTION SITE - FEHMARN

RAMBØLL
ARUP
TEC

Fehmarnbelt Fixed Link – Tunnel Design Services
DREDGING

RAMBØLL
ARUP
TEC

Fehmarnbelt Fixed Link – Tunnel Design Services
ON-GOING ACTIVITIES

RAMBØLL
ARUP
TEC

Fehmarnbelt Fixed Link – Tunnel Design Services
PROJECT TIMESCHEDULE

RAMBØLL
ARUP
TEC

Fehmarnbelt Fixed Link – Tunnel Design Services
PROCUREMENT PROCESS

• Prequalification – already completed
• Tendering with a Competitive dialogue:
1. the provisional bi...
THANK YOU FOR YOUR
ATTENTION

2011/01/05
GO-HOME MEETING
Upcoming SlideShare
Loading in...5
×

Dr Alun Thomas, Ramboll: Fehmarnbelt Fixed Link Tunnel

841

Published on

Dr Alun Thomas, Head of Tunnels, Ramboll delivered this presentation at the 2013 Australian Tunnelling conference. The two day conference is supported by the Australasian Tunnelling Society and brings together tunnelling leaders, engineers and industry experts to share best practice in tunnelling design, construction, safety and maintenance.

The 2012 program focussed on updates from Australasia’s current and future projects, plus case studies from leading International projects - sharing best practice and lessons learnt from the forefront of the latest tunnelling projects. For more information about the event, please visit the conference website: http://www.informa.com.au/tunnellingconference

Published in: Technology, Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
841
On Slideshare
0
From Embeds
0
Number of Embeds
1
Actions
Shares
0
Downloads
29
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Dr Alun Thomas, Ramboll: Fehmarnbelt Fixed Link Tunnel

  1. 1. Fehmarnbelt Fixed Link Tunnel Alun Thomas Ramboll RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  2. 2. CONTENT 1. The Project in general 2. The Tunnel •  •  •  •  Tunnel Layout Safety Concept IMT Design Construction 4.  Environmental issues 5.  Procurement RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services 2
  3. 3. LOCATION Store Baelt Link Øresund Link Femern Baelt Link RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  4. 4. FEHMARNBELT FIXED LINK Treaty between Denmark and Sweden 1991 Trans European Network priority Treaty between Denmark and Germany 2008 Multiple solutions investigated, including:   mmersed tunnel I   ored tunnel B   able stayed bridge C   uspension bridge S Immersed tunnel solution adopted 2011 RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  5. 5. OVERALL PROGRAMME February 2011: Minister of Transport selects IMT as preferred solution for the German Plan Approval procedure 2013: Publication of the environmental impact statement and EIShearing in Denmark. 2013: Application for the plan approval procedure in Germany. Expected to start in September End 2012: Prequalification of contractors Mid 2013: Start of Tender process End 2014: Anticipated presentation of the Danish construction law 2015 – 2021: Construction phase for the coast-to-coast segment End 2021: Prospective opening of the Fehmarnbelt Fixed Link RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  6. 6. ADDITIONAL LANDWORKS •  Railway line Ringsted-Rødby to be electrified •  Railway line Rødby–Vordingborg to be expanded to doubletrack excluding the Storstrøm bridge •  Upgrading and environmental improvements for the motorway Sakskøbing – Rødby to be investigated •  Germany shall ensure a sufficient capacity on the railway line from Bad Schwartau to Puttgarden •  The railway line Lübeck-Puttgarden shall be electrified •  The German landworks shall include a double track connection (excluding the Fehmarnsundbrücke) •  Heiligenhafen-Puttgarden road expanded to four lanes •  RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  7. 7. Bro COMPETITION BETWEEN TUNNEL eller Tunnel AND BRIDGE RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  8. 8. MAIN ALTERNATIVES Cable Stayed Bridge : Cable Stayed Bridge : Feasibility Study : 4,4 bill EUR Conceptual Design : 5,1 bill EUR (COWI /Obemeyer) RAMBØLL ARUP TEC Immersed Tunnel: Immersed Tunnel: Feasibility Study : 5,5 bill EUR Conceptual Design : 5,0 bill EUR (Ramboll /Arup/TEC) Fehmarnbelt Fixed Link – Tunnel Design Services
  9. 9. ALTERNATIVE - BORED TUNNEL RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  10. 10. THE TUNNEL RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  11. 11. PREFERRED ALIGNMENT • Close to existing infrastructure • Rail east of the road, same as in the hinterland • Almost straight alignment RAMBØLL ARUP TEC 11 Fehmarnbelt Fixed Link – Tunnel Design Services
  12. 12. Tunnel Length and Depth Tunnel Length 18.1 km Fehmarnbelt Fixed Link Trans Bay Tube BART Tunnel Øresund Tunnel Immersed Tunnel Length Busan-Geoje Fixed Link 17.6 km Hampton Roads Tunnel Cross Harbour Tunnel Tama River Tunnel Tunnel Depth 40 m Marmaray Crossing 0 5 WORLD IMT RECORD ! RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services 10 15 20
  13. 13. PORTAL AREA - FEHMARN RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  14. 14. PORTAL AREA - LOLLAND RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  15. 15. LAGOON AREA RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  16. 16. ENVIRONMENTAL ISSUES • Sea water • Landscape and soil • Seabed and coasts • Vegetation on land • Watercourses and lakes • Animal life on land • Ground water • Birds • Animal life in the sea • Barriers for animals and plants • Marine flora • Drainage • Barriers to water flow • Contamination and vibrations • Sediment spill • Social impact RAMBØLL ARUP TEC www.femernenvironment.com Fehmarnbelt Fixed Link – Tunnel Design Services 16
  17. 17. IMMERSED TUBE TUNNEL DESIGN RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  18. 18. CHOICE OF CROSS SECTIONS ? RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  19. 19. TUNNEL ELEMENTS Standard element Special element RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  20. 20. SOIL CONDITIONS RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services 20
  21. 21. Standard element • 79 Standard elements divided into 9 segments of approx. 24 m, weight 76.600 tons • Niche at centre of the element for ventilation or traffic information signs • Same layout for all standard elements e.g. box-outs, cast-in items, cable ducts, etc. RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  22. 22. SPECIAL ELEMENT • Need for transformers and other M & E equipment in the tunnel • Standard elements do not have sufficient space. • Special elements to cluster mechanical and electrical equipment • Maintenance staff better working conditions and higher safety • Installations and system divided into units • Concentrate extra space in the tunnel at special elements RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  23. 23. TUNNEL SPECIAL ELEMENT •  Size [l/b/h]: 39m/45m/ 13m •  10 Special elements •  Lay by for parking of maintenance staff •  Access to all rooms and tubes above RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  24. 24. CONSTRUCTION RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  25. 25. CONTRACT PRINCIPLES •  Four Civil Works Contracts: •  Tunnel North •  Tunnel South •  Portal Structures and Ramps •  Dredging and Reclamation •  Design and Build Contracts •  Competitive Dialogue Procedure •  Other contracts will follow later •  Electrical and Mechanical Works •  Railway RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  26. 26. THE FOUR CIVIL WORK CONTRACTS IMT North (TUN) IMT South (TUS) RAMBØLL ARUP TEC Tunnel Portals & Ramps (TPR) Dredging & Reclamation (TDR ) Fehmarnbelt Fixed Link – Tunnel Design Services
  27. 27. CONSTRUCTION PRINCIPLE FOR STANDARD ELEMENTS Production of tunnel elements for Øresund - Controlled environment - Straight elements RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  28. 28. PRODUCTION SITE - PERSPECTIVE RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services 28
  29. 29. BASIC DATA Approximate numbers Length of standard tunnel element 217 m Height of standard tunnel element 8,9 m Weight of standard tunnel element 76,000 tonnes Number of tunnel elements Structural Concrete (total) Reinforcement (total) Tie-down anchors (total) Total dredged volume in trench 79 pcs 2,6 million m3 300.000 tonnes 1400 pcs 15,5 million m3 Trench backfill volumes 7 million m3 Reclaimed areas 3 million m2 RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  30. 30. QUANTITIES FOR STANDARD ELEMENTS Required materials per week Concrete Delivery of concrete 24,000 m³ Reinforcement 3,200 tonnes Water 4,400 m³ Cement 8,000 tonnes Sand 16,800 tonnes Gravel 16 trucks every hour Or 28,800 tonnes (1 day = 24 hours) Delivery of materials 1 coaster every day RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services Co
  31. 31. CONSTRUCTION SITE - FEHMARN RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  32. 32. DREDGING RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  33. 33. ON-GOING ACTIVITIES RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  34. 34. PROJECT TIMESCHEDULE RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services
  35. 35. PROCUREMENT PROCESS • Prequalification – already completed • Tendering with a Competitive dialogue: 1. the provisional bids in which the prequalified contractors describe how they will solve the tasks in technical terms, but without pricing information (submitted in January 2014). 2. the dialogue phase will then last until the end of June 2014. 3. in September 2014 the contractors must submit binding bids with prices specified. RAMBØLL ARUP TEC Fehmarnbelt Fixed Link – Tunnel Design Services 35/15
  36. 36. THANK YOU FOR YOUR ATTENTION 2011/01/05 GO-HOME MEETING