• Share
  • Email
  • Embed
  • Like
  • Save
  • Private Content
339 solar power plant deepak
 
  • 170 views

 

Statistics

Views

Total Views
170
Views on SlideShare
155
Embed Views
15

Actions

Likes
0
Downloads
4
Comments
0

1 Embed 15

http://www.ese.iitb.ac.in 15

Accessibility

Categories

Upload Details

Uploaded via as Microsoft PowerPoint

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

    339 solar power plant deepak 339 solar power plant deepak Presentation Transcript

    • Experience in Commissioning of a 1MWe Solar Thermal Power Plant in Gurgaon N.G.R. Kartheek1*, Deepak Yadav 1, Rangan Banerjee1, J.K. Nayak1, Santanu Bandyopadhyay1 Shireesh B. Kedare1 1 Department of energy science and engineering, IIT Bombay Funded by Ministry of New and Renewable Energy Corresponding Author. Tel: +91 22 25764794, E-mail: solarthermaliitb@gmail.com
    • Schematic of process flow for the solar thermal power plant Process flow diagram
    • Unique features of the project Demonstration of solar thermal technology for power generation Combination of collector technologies Project Landmarks January 2010 different Direct and indirect steam generation to be demonstrated Simulation package for scale-up January 2011 Test facility for solar thermal applications to facilitate the development of indigenous technology Consortium based approach involving government and industry July 2013
    • Parabolic Trough Solar Field
    • Linear Fresnel Reflector
    • Commissioning Experience Classification of commissioning experience
    • Operational Problems
    • Linear Fresnel Reflector
    • Receiver tube leakage of the LFR system Receiver Tube leakage Leakage in the receiver tube • Operating Pressure: 40 kg/cm2 (g) saturated steam pressure • Hydro test Pressure: 120 kg/cm2 (g) • Leakages were found in 12 welding joints during hot commissioning
    • Equipment Problems
    • Leakages in instrument stub connections on heat exchanger Leakage from Screwed connection Temperature Transmitters showing Leakages Temperature Transmitters with sealant • Vapor pressure of Therminol VP 1 at 257 C is 1 bar (a) • Ignition temperature of Therminol VP 1 is 621 C • No screw joints and minimum flanged connections
    • System Problems
    • HTF Freezing Ambient Temperature (oC) 15 14 13 12 11 10 Time (hr: min) Ambient temperature profile at the project site on February 24th, 2013 • Crystallization temperature of HTF Therminol VP1 is 12 C 8:30 AM 8:00 AM 7:30 AM 7:00 AM 6:30 AM 6:00 AM 5:30 AM 5:00 AM 4:30 AM 4:00 AM 3:30 AM 3:00 AM 2:30 AM 2:00 AM 1:30 AM 1:00 AM 12:30 AM 12:00 AM 9
    • HTF Freezing  Manual Operation  Temperature gauge readings at Main HTF Pump discharge and outlet of solar field Temperature of HTF ~350C  Pump at minimum flow rate Schematic of Oil System
    • HTF Freezing TG TG Schematic of Oil System
    • Pump Seal Failure: February, 2013
    • Dirt/Oil particles collected from the drain point near heat exchanger (March 17, 2013)
    • Summary and Lesson Learnt • Operational Problem – Time consuming, delay in commissioning  Leakages in superheater: Torque spanner  Receiver tube and window glass: Spot Welding, Continuous power  Water Entry in IA line: NRV  Dry run of the BFP: Level Switches • Equipment problems – Good engineering practise  NRV Selection: Horizontal & Vertical line  Instrument Stub: No threaded parts  Compressed air line: No threaded joints  Communication failure: Preconsidered  Steam Valves: Control, Manual handle, Station
    • Summary and Lesson Learnt • System Problem HTF Freezing: Unfreezes only in summer. UPS and Tracker failure: Continuous Power supply
    • Commissioning problems in chronological order
    • THANK YOU
    • Project Objectives • 1MWe Solar Thermal Power Plant  Design & Development of a 1 MW plant.  Generation of Electricity for supply to the grid. • National Test Facility  Development of facility for component testing and characterization. • Development of Simulation Package  Simulation software for solar thermal power plant scale-up  Compatibility for various solar applications.
    • receiver glass window breakage the LFR system Receiver Window Glass Breakage Breakage of the receiver window glass Interruption in power supply to the tracking motors, focus shifted partially
    • Leakages in the superheater – 10/03/2013 Steam Leakage
    • Water entry in instrumentation air line •Compressed air required in the Demineralisation plant (DM) in mixed bed unit • No NRV in IA line • DM water entered into the airline •4 control valve damaged Dry run of the boiler feed pump • Malfunction of Level transmitter on the Deaerator led to dry of pump
    • NRV at BFP exit Failure Process flow from Deaerator to Steam generator
    • Leakages in compressed air piping Schematic sketch of compressed air flow
    • Communication problem between level I and level II Control System Hierarchy for the solar thermal power plant
    • Steam System valves •Problem in complete closing of the valve • Manual closing of Valve – Not possible • Control Valve in the Steam Line – Regulate pressure Control Valve without Handle Control Valve with Handle
    • Mechanical Seal-Frozen Oil Particles (March 17, 2013)
    • Dirt/Oil particles collected from the basket filter at suction of Main HTF Pumps (March 17, 2013)