The document provides an assessment of the status of fundamental safety functions for Unit 1 of the Fukushima Daiichi Nuclear Power Plant as of May 18, 2011. It finds that stable cooling is not achieved and long-term closed-loop heat removal capability has not been established. Containment integrity is achieved but the reactor pressure vessel is assumed to be leaking. Radiation monitoring is available but additional releases are anticipated and radioactive releases should be limited and monitored.