The evolution of EPC contracting
Upcoming SlideShare
Loading in...5
×
 

The evolution of EPC contracting

on

  • 4,280 views

Shows how contracting for capital projects has evolved over the last 30 year or so

Shows how contracting for capital projects has evolved over the last 30 year or so

Statistics

Views

Total Views
4,280
Views on SlideShare
4,280
Embed Views
0

Actions

Likes
4
Downloads
881
Comments
2

0 Embeds 0

No embeds

Accessibility

Upload Details

Uploaded via as Adobe PDF

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel

12 of 2

  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
  • As you know every project is UNIQUE .How is it possible to use your valuable slides to another project
    Kindest regards
    Are you sure you want to
    Your message goes here
    Processing…
  • I posted the tutorials on dropbox also.

    Hopefully you will be able to download the files from there.

    Here are the links:

    https://www.dropbox.com/s/h99vuhvriyaybgv/Contracts%20Terms%20and%20Conditions.pdf

    https://www.dropbox.com/s/2hwlwisavezegko/Cost%20estimate.pdf

    https://www.dropbox.com/s/l3369udivstsr26/EPC%20Project%20execution%20orientation%20course.pdf

    https://www.dropbox.com/s/fghw0qi0ie9b3dq/Process%20diagrams.pdf

    https://www.dropbox.com/s/r25kfc5jemgtabh/The%20evolution%20of%20EPC%20contracting.pdf
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

    The evolution of EPC contracting The evolution of EPC contracting Presentation Transcript

    • HERVE The evolution of EPC contractingBARONWelcome to this presentation.It shows the evolution that took place in EPC contrcting schemes over the last 30 years.Comments are most welcome (herve.baron@gmail.com), which I will incorporate for the benefit of all. Hervé © 2013 – Hervé Baron
    • HERVE Contracting schemesBARON EPC ContractsClients contracting strategy Phase 1 © 2013 – Hervé Baron
    • HERVE Contracting schemesBARONClients contracting strategy Phase 1 • EPCM • Re-imbursable © 2013 – Hervé Baron
    • HERVE Contracting schemesBARONClients contracting strategy Pro’s and Cont’s Phase 1 • EPCM • Re-imbursable © 2013 – Hervé Baron
    • HERVE Contracting schemesBARON EPC ContractsClients contracting strategy Pro’s and Cont’s Phase 1 Phase 1 • All risks with Client • EPCM • Budget and schedule slippage • Re-imbursable • Extensive supervision staff © 2013 – Hervé Baron
    • HERVE Contracting schemesBARONClients contracting strategy Pro’s and Cont’s Phase 1 Phase 1 • All risks with Client • EPCM • Slippage budget and schedule • Re-imbursable • Extensive supervision staff Phase 2 © 2013 – Hervé Baron
    • HERVE Contracting schemesBARONClients contracting strategy Pro’s and Cont’s Phase 1 Phase 1 • All risks with Client • EPCM • Slippage budget and schedule • Re-imbursable • Extensive supervision staff Phase 2 • EPCM • LS E&P © 2013 – Hervé Baron
    • HERVE Contracting schemesBARON EPC ContractsClients contracting strategy Pro’s and Cont’s Phase 1 Phase 1 • All risks with Client • EPCM • Slippage budget and schedule • Re-imbursable • Extensive supervision staff Phase 2 • EPCM • LS E&P © 2013 – Hervé Baron
    • HERVE Contracting schemesBARONClients contracting strategy Pro’s and Cont’s Phase 1 Phase 1 • All risks with Client • EPCM • Slippage budget and schedule • Re-imbursable • Extensive supervision staff Phase 2 Phase 2 • Improvement over Phase 1 on • EPCM schedule and budget • LS E&P • Extensive supervision staff © 2013 – Hervé Baron
    • HERVE Contracting schemesBARONClients contracting strategy Pro’s and Cont’s Phase 1 Phase 1 • All risks with Client • EPCM • Slippage budget and schedule • Re-imbursable • Extensive supervision staff Phase 2 Phase 2 • Improvement over Phase 1 on • EPCM schedule and budget • LS E&P • Extensive supervision staff © 2013 – Hervé Baron What difference did Phase 2 bring compared to Phase 1 for Engineering development?
    • HERVE Contracting schemesBARONClients contracting strategy Pro’s and Cont’s Phase 1 Phase 1 • All risks with Client • EPCM • Slippage budget and schedule • Re-imbursable • Extensive supervision staff Engineering continuum Phase 2 Phase 2 • Improvement over Phase 1 on • EPCM schedule and budget • LS E&P • Extensive supervision staff FEED then CFT for EPC © 2013 – Hervé Baron
    • HERVE Contracting schemesBARONClients contracting strategy Pro’s and Cont’s Phase 1 Phase 1 • All risks with Client • EPCM • Slippage budget and schedule • Re-imbursable • Extensive supervision staff Phase 2 Phase 2 • Improvement over Phase 1 on • EPCM schedule and budget • LS E&P • Extensive supervision staff © 2013 – Hervé Baron Phase 3
    • HERVE Contracting schemesBARONClients contracting strategy Pro’s and Cont’s Phase 1 Phase 1 • All risks with Client • EPCM • Slippage budget and schedule • Re-imbursable • Extensive supervision staff Phase 2 Phase 2 • Improvement over Phase 1 on • EPCM schedule and budget • LS E&P • Extensive supervision staff © 2013 – Hervé Baron Phase 3 • LSTK
    • HERVE Contracting schemesBARONClients contracting strategy Pro’s and Cont’s Phase 1 Phase 1 • All risks with Client • EPCM • Slippage budget and schedule • Re-imbursable • Extensive supervision staff Phase 2 Phase 2 • Improvement over Phase 1 on • EPCM schedule and budget • LS E&P • Extensive supervision staff © 2013 – Hervé Baron Phase 3 • LSTK
    • HERVE Contracting schemesBARONClients contracting strategy Pro’s and Cont’s Phase 1 Phase 1 • All risks with Client • EPCM • Slippage budget and schedule • Re-imbursable • Extensive supervision staff Phase 2 Phase 2 • Improvement over Phase 1 on • EPCM schedule and budget • LS E&P • Extensive supervision staff Phase 3 © 2013 – Hervé Baron • All risks with Contractor Phase 3 • LSTK
    • HERVE Contracting schemesBARONClients contracting strategy Pro’s and Cont’s Phase 1 Phase 1 • All risks with Client • EPCM • Slippage budget and schedule • Re-imbursable • Extensive supervision staff Less and less need for a PMC Phase 2 Phase 2 • Improvement over Phase 1 on • EPCM schedule and budget • LS E&P • Extensive supervision staff Phase 3 © 2013 – Hervé Baron • All risks with Contractor Phase 3 • LSTK
    • HERVE Contracting schemes BARON EPC ContractsContractor’s strategy Phase 3 • LSTK How does the Contractor mitigate risks? © 2013 – Hervé Baron
    • HERVE Contracting schemes BARON EPC ContractsContractor’s strategy Phase 3 • LSTK • Construction sub-contract © 2013 – Hervé Baron
    • HERVE Contracting schemes BARON EPC ContractsContractor’s strategy Pro’s and Cont’s Phase 3 • LSTK • Construction sub-contract © 2013 – Hervé Baron
    • HERVE Contracting schemes BARON EPC ContractsContractor’s strategy Pro’s and Cont’s Phase 3 Phase 3 • Partial risk sharing • LSTK • Construction sub-contract © 2013 – Hervé Baron
    • HERVE Contracting schemes BARON EPC ContractsContractor’s strategy Pro’s and Cont’s Phase 3 Phase 3 • Partial risk sharing • LSTK • Construction sub-contract 2 different schemes: 3a and 3b © 2013 – Hervé Baron
    • HERVE Contracting schemes BARON EPC ContractsContractor’s strategy Pro’s and Cont’s Phase 3 Phase 3 • Partial risk sharing • LSTK • Construction sub-contract • Phase 3a − General Construction Contractor © 2013 – Hervé Baron
    • HERVE Contracting schemes BARON EPC ContractsContractor’s strategy Pro’s and Cont’s Phase 3 Phase 3 • Partial risk sharing • LSTK • Construction sub-contract • Phase 3a − General Construction Contractor © 2013 – Hervé Baron
    • HERVE Contracting schemes BARON EPC ContractsContractor’s strategy Pro’s and Cont’s Phase 3 Phase 3 • Partial risk sharing • LSTK • Construction sub-contract • Phase 3a • Phase 3a − Reduced risk and supervision − General Construction Contractor © 2013 – Hervé Baron
    • HERVE Contracting schemes BARON EPC ContractsContractor’s strategy Pro’s and Cont’s Phase 3 Phase 3 • Partial risk sharing • LSTK • Construction sub-contract • Phase 3a • Phase 3a − Reduced risk and supervision − General Construction Contractor • Phase 3b – intense cost pressure © 2013 – Hervé Baron
    • HERVE Contracting schemes BARON EPC ContractsContractor’s strategy Pro’s and Cont’s Phase 3 Phase 3 • Partial risk sharing • LSTK • Construction sub-contract • Phase 3a • Phase 3a − Reduced risk and supervision − General Construction Contractor • Phase 3b – intense cost pressure − Multiple Construction Sub- Contractors © 2013 – Hervé Baron
    • HERVE Contracting schemes BARON EPC ContractsContractor’s strategy Pro’s and Cont’s Phase 3 Phase 3 • Partial risk sharing • LSTK • Construction sub-contract • Phase 3a • Phase 3a − Reduced risk and supervision − General Construction Contractor • Phase 3b – intense cost pressure − Multiple Construction Sub- Contractors © 2013 – Hervé Baron
    • HERVE Contracting schemes BARON EPC ContractsContractor’s strategy Pro’s and Cont’s Phase 3 Phase 3 • Partial risk sharing • LSTK • Construction sub-contract • Phase 3a • Phase 3a − Reduced risk and supervision − General Construction Contractor • Phase 3b − Increased competition • Phase 3b – intense cost pressure − Extensive coordination − Multiple Construction Sub- Contractors © 2013 – Hervé Baron
    • HERVE Contracting schemes BARON EPC ContractsContractor’s strategy Pro’s and Cont’s Phase 3 Phase 3 • Partial risk sharing • LSTK • Construction sub-contract © 2013 – Hervé Baron
    • HERVE Contracting schemes BARON EPC ContractsContractor’s strategy Pro’s and Cont’s Phase 3 Phase 3 • Partial risk sharing • LSTK • Construction sub-contract What usually happened? © 2013 – Hervé Baron
    • HERVE Contracting schemes BARON EPC ContractsContractor’s strategy Pro’s and Cont’s Phase 3 Phase 3 • Partial risk sharing • LSTK • E&P delays => Sub-contractor has • Construction sub-contract to accelerate hence claims © 2013 – Hervé Baron
    • HERVE Contracting schemes BARON EPC ContractsContractor’s strategy Pro’s and Cont’s Phase 3 Phase 3 • Partial risk sharing • LSTK • E&P delays => Sub-contractor has • Construction sub-contract to accelerate hence claims What new scheme was introduced to mitigate? © 2013 – Hervé Baron
    • HERVE Contracting schemes BARON EPC ContractsContractor’s strategy Pro’s and Cont’s Phase 3 Phase 3 • Partial risk sharing • LSTK • E&P delays => Sub-contractor has • Construction sub-contract to accelerate hence claims Phase 4 © 2013 – Hervé Baron
    • HERVE Contracting schemes BARONContractor’s strategy Pro’s and Cont’s EPC Contracts Phase 3 Phase 3 • LSTK • Partial risk sharing • Construction sub-contract • E&P delays => Sub-contractor has to accelerate hence claims Phase 4 • EP / C in Consortium or JV © 2013 – Hervé Baron
    • HERVE Contracting schemes BARONContractor’s strategy EPC Contracts Pro’s and Cont’s Phase 3 Phase 3 • LSTK • Partial risk sharing • Construction sub-contract • E&P delays => Sub-contractor has to accelerate hence claims Phase 4 • EP / C in Consortium or JV © 2013 – Hervé Baron
    • HERVE Contracting schemes BARONContractor’s strategy EPC Contracts Pro’s and Cont’s Phase 3 Phase 3 • LSTK • Partial risk sharing • Construction sub-contract • E&P delays => Sub-contractor has to accelerate hence claims Phase 4 Phase 4 • EP / C in Consortium or JV − Improved risk sharing − No claims − Less competitive © 2013 – Hervé Baron
    • HERVE Contracting schemes BARONContractor’s strategy EPC Contracts Pro’s and Cont’s Phase 3 Phase 3 • LSTK • Partial risk sharing • Construction sub-contract • E&P delays => Sub-contractor has to accelerate hence claims Phase 4 Phase 4 • EP / C in Consortium or JV − Improved risk sharing − No claims − Less competitive © 2013 – Hervé Baron Which scheme is better for COMPANY: 3 or 4? Why?