Slideshow transcript
Slide 1: CASE ANALYSIS Denver International Airport Baggage-Handling System (DIABHS) by Karla Aguilar Setiawan Soekamtoputra Course MGT 565 Project Management
Slide 2: Agenda Project Background Project Outline Project Execution Primary Theme Players Gantt Chart Six Important Issues Recommendations News beyond case
Slide 3: Project Background Construction of Denver International Airport started in 1989 No considerations for baggage handling system were made United Airlines contracted BAE to implement baggage handling system Airport-wide integrated baggage system was suggested
Slide 4: Project Outline Objectives: Improve baggage delivery cycle time and ground efficiency Reduce close-out time for hub operation Decrease manual sorting/handling Scheduled Budget: $193 million Scheduled Completion: October ‘93 Scheduled Duration: 18 months Financing: Bond Issuances
Slide 5: Project Actual Execution Spending: $300 million + $1 million/day excess expense Additional sub-project: back-up baggage system Start date : August 1994 Spending : $51 million Finish date : 28 February 1995 Late from scheduled: 16 months
Slide 6: Project Primary Theme Delays in construction and implementation of baggage system Pressure from stakeholders The city’s handling of the situation Technical and organizational problems Leadership, communication and organization
Slide 7: Players Client: City of Denver Mayor Wellington Webb Developer: BEA Automated Systems, Inc. Gene Di Fonso, President Slinger, Chief Airport Engineer Gail Edmond, Slinger’s replacement Other Stakeholders: DIA Program management team (PMT) German Logplan consultants
Slide 8: Gantt Chart
Slide 9: Six Most Important Issues Problems: Bad communication among players Lack of compliance with preset conditions Poor planning during early stage Failure to objectively assess situation and escalating commitment Best Practices: Quick back-up plan after experiencing multiple delays BAE was the right guy for the job (world-wide reputation as superior baggage system builder)
Slide 10: Recommendations Define a clear leadership, roles and hierarchies- chain of command Take time to carefully plan and determine reasonable finish time Get buy-in from stakeholders and necessary commitments Communicate often and thoroughly with all players Build smaller scale system first Test mechanical, hardware, and software reliability in real environment
Slide 11: News 6 months after opening, baggage handling system was abandoned till now Logplan is working with DIA on a master plan update for 2015 and 2030 August 2005: UA abandoned the system to save $1 million maintenance costs DIA: to spend $1.2 billion over the next seven years (2008) on improvement of a new automated baggage system
Slide 12: Thank You Q & A Session




Add a comment on Slide 1
If you have a SlideShare account, login to comment; else you can comment as a guest- Favorites & Groups
Showing 1-50 of 1 (more)