Marginal offshore production platform feasibility
Upcoming SlideShare
Loading in...5
×
 

Like this? Share it with your network

Share

Marginal offshore production platform feasibility

on

  • 6,379 views

Final presentation of a feasibility study performed this year (2009) covering many aspects of marginal platform design, fabrication, transport and installation.

Final presentation of a feasibility study performed this year (2009) covering many aspects of marginal platform design, fabrication, transport and installation.

Statistics

Views

Total Views
6,379
Views on SlideShare
6,359
Embed Views
20

Actions

Likes
3
Downloads
0
Comments
0

1 Embed 20

http://www.slideshare.net 20

Accessibility

Upload Details

Uploaded via as Microsoft PowerPoint

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

Marginal offshore production platform feasibility Presentation Transcript

  • 1. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING Iv-Oil & Gas www.iv-groep.nl DEVELOPMENT OF A MARGINAL SATTELITE FIELD
  • 2. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING INTRODUCTION Iv-Oil & Gas www.iv-groep.nl
  • 3. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING INTRODUCTION
    • Wintershall Noordzee BV is investigating the feasibility to utilize a low cost option to develop satellite fields located in the Dutch Sector of the North Sea where the water depth ranging from 20 to 35 meters.
    • PHILOSOPHY:
      • The design shall allow for re-use after field depletion
      • Lifecycle cost shall always be considered
      • Simple installation/de-installation methodology
      • An ergonomic acceptable lay out
      • Free water knock out
      • Renewable energy
    Iv-Oil & Gas www.iv-groep.nl
  • 4. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING INTRODUCTION
    • STUDY OBJECTIVES
      • Define a concept,
      • Define a generic topside,
      • Estimate topside weight and space requirements,
      • Recommend a transport, assembly and installation method,
      • Cover implementation aspects of project execution,
      • Estimate capital expenditure.
    Iv-Oil & Gas www.iv-groep.nl
  • 5. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING INTRODUCTION
    • STUDY PARAMETERS
      • Site data (20 to 35m water depth)
      • Base process data (2 producing wells, 1.8 mln m 3 /d)
      • Materials of construction (Duplex stainless steel)
      • Utilities (Emergency diesel, solar cells and wind turbines)
      • Emergency overnight shelter (4 persons)
      • Design and fatigue life (20 years, Fatigue: x5, x10)
      • Other (wire line operations, no crane)
    Iv-Oil & Gas www.iv-groep.nl
  • 6. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SUBSTRUCTURES Iv-Oil & Gas www.iv-groep.nl
  • 7. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SUBSTRUCTURES
    • INSTALLATION OPTIONS
      • Crane barge installed with driven piles
      • Installed by jack-up rig or construction barge
      • Self installing
    • SUBSTRUCTURES
      • Conventional multi-legged jacket
      • Minimal braced tower jacket
      • Conductor supported modular structure
      • Monotower
      • Self installing platforms
    Iv-Oil & Gas www.iv-groep.nl
  • 8. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SUBSTRUCTURES CRANE/BARGE INSTALLED - MULTILEGGED JACKET
    • Advantages
    • Proven concept
    • Supports all marginal topsides
    • Can support work-over units
    • Disadvantages
    • Requires heavy lift vessel
    • Main pile jackets require field welds
    • High installation costs
    Iv-Oil & Gas www.iv-groep.nl
  • 9. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SUBSTRUCTURES CRANE/BARGE INSTALLED – MINIMAL BRACED
    • Advantages
    • Low weight
    • Disadvantages
    • Requires heavy lift vessel
    • Limited future expansion
    • Jack-up rig required for work-over
    Iv-Oil & Gas www.iv-groep.nl
  • 10. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SUBSTRUCTURES RIG/BARGE INSTALLED – CONDUCTOR SUPPORTED
    • Advantages
    • Cost effective
    • Disadvantages
    • Topsides limited to 200 tonnes
    • Permitting
    • Not to be pursued
    Iv-Oil & Gas www.iv-groep.nl
  • 11. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SUBSTRUCTURES RIG/BARGE INSTALLED – MONOTOWER
    • Advantages
    • Low weight
    • Protected conductors and risers
    • Disadvantages
    • Cannot pre-drill wells
    • Work-over requires drilling rig
    • Limited topside weight
    • Sensitive to dynamic motions  fatigue  additional bracings
    Iv-Oil & Gas www.iv-groep.nl
  • 12. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SUBSTRUCTURES SELF INSTALLING – SIP I
    • Advantages
    • Transport floating on suction piles
    • Disadvantages
    • Separately installed topsides
    Iv-Oil & Gas www.iv-groep.nl
  • 13. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SUBSTRUCTURES SELF INSTALLING – SIP II
    • Advantages
    • No lifting required at location
    • Docking over pre-drilled wells
    • Re-usable
    • Maximized onshore commissioning
    • Disadvantages
    • Too large to be considered marginal
    • Larger deck width
    Iv-Oil & Gas www.iv-groep.nl
  • 14. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SUBSTRUCTURES SELF INSTALLING – SIP III
    • Advantages
    • No heavy lift vessel
    • Docking over pre-drilled wells
    • Re-usable
    • Maximized onshore commissioning
    • Disadvantages
    • Topside weight limited
    • Temporary frame required on barge
    Iv-Oil & Gas www.iv-groep.nl
  • 15. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SUBSTRUCTURES SELF INSTALLING – SIP IV
    • Advantages
    • No heavy lift vessel
    • Docking over pre-drilled wells
    • Re-usable
    • Maximized onshore commissioning
    • Disadvantages
    • Deck and substructure weight too
    • high for a marginal concept
    Iv-Oil & Gas www.iv-groep.nl
  • 16. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SUBSTRUCTURES
    • CONCEPT SELECTION
    • Installable without a heavy lift vessel
      • Ability to support a 3-well 400 tonnes topside
      • Low weight
      • Minimum decommissioning costs
      • The SIP 3 concept satisfies the criteria of the study and therefore it is selected as the preferred substructure for this study .
    Iv-Oil & Gas www.iv-groep.nl
  • 17. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SIP 3 Iv-Oil & Gas www.iv-groep.nl
  • 18. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SIP 3
    • SIP 3 CONCEPT
      • SPT patent
      • Barge installed, fully pre-installed and commissioned
    Iv-Oil & Gas www.iv-groep.nl
  • 19. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SIP 3
    • SIP 3 SUBSTRUCTURE
      • 3.5 m OD mono column, 3 suction piles
      • Horizontal mono column orientation for fabrication
      • Upending of the mono column from horizontal to vertical
      • Vertical (lifted) load out with the suction piles attached
      • Installation of topside (substructure at quay / harbour floor)
      • Vertical transportation of the total platform
      • Suitable transportation barge
      • Docking over existing pre-drilled wells
      • Future abandonment and re-installation
    Iv-Oil & Gas www.iv-groep.nl
  • 20. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING TOPSIDES Iv-Oil & Gas www.iv-groep.nl
  • 21. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING TOPSIDES
    • SIP 3 TOPSIDES
      • Main deck
      • Intermediate deck
      • Top deck (helideck)
    • PROCESS
      • 1.8 mln Nm 3 /d capacity
      • MOC: 900# Duplex
      • Free water Knockout (3 phase separation)
      • Oil skimmer tank
      • Clean water (<30 ppmv oil) overboard
      • 10” pipeline
    Iv-Oil & Gas www.iv-groep.nl
  • 22. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING TOPSIDES
    • CONTROL, SAFETY AND SHUT DOWN
      • Unmanned autonomous operating classification
      • Control via fibre optics by means of a DCS extension of the host platform
      • Gas detection and intruder alarm
      • Rig connected deluge system (dry)
      • H60 wall (E/I facilities and refuge)
    Iv-Oil & Gas www.iv-groep.nl
  • 23. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING TOPSIDES
    • ENERGY
      • 2400 watt energy consumption (unmanned mode)
      • Renewable energy sources (wind turbines and solar)
    • WEIGHT
      • Topsides : 340 tonnes
      • Substructure : 860 tonnes
      • Total : 1200 tonnes
    Iv-Oil & Gas www.iv-groep.nl
  • 24. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING FABRICATION, TRANSPORT AND INSTALLATION Iv-Oil & Gas www.iv-groep.nl
  • 25. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING FABRICATION, TRANSPORT AND INSTALLATION
    • FABRICATION
    • Fabrication at a facility which has unrestricted access to the North Sea.
      • Delivery of mono column (rolled and pre-welded)
      • Delivery of suction piles
      • Fabrication substructure
      • Integration of suction piles with the substructure
      • Installation of sacrificial anodes
      • Installation of SW pump, J-tube and riser inside column
    Iv-Oil & Gas www.iv-groep.nl
  • 26. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING FABRICATION, TRANSPORT AND INSTALLATION
    • TRANSPORT AND INSTALLATION
      • Marine spread :
        • Main tow tug 60-80 TBP
        • Assisting tug 40 TBP
        • Barge 300 – 400 ft
      • Strand jacks (4 x 600 ton)
      • Suction pumps (3 x)
      • Hang-off frame (at stern of barge)
      • Mooring winches (4 x allows for accurate manoeuvring)
      • ROV spread (seabed survey and wellhead inspection)
      • Survey & positioning spread (platform position monitoring)
    Iv-Oil & Gas www.iv-groep.nl
  • 27. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING FABRICATION, TRANSPORT AND INSTALLATION
    • INSTALLATION OPTIONS
      • Topside pre-installed at top of column, transport with barge SIP3, offshore lowered with strand jacks (1x jacking),
      • Topside pre-installed at lower section of column, transport with barge SIP3, substructure lowered offshore using strand jacks, deck lifted with strand jacks (2x jacking),
      • Topside installed at top of column, transport on barge, offshore single lift HLV/SSCV (1x lifting),
      • Topside on barge, substructure on barge, offshore installation deck with sheerleg/HLV/SSCV (2x lifting),
      • Transport topside on barge, substructure in hooks sheerleg (1x lowering, 1x lifting).
    Iv-Oil & Gas www.iv-groep.nl
  • 28. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING FABRICATION, TRANSPORT AND INSTALLATION
    • INSTALLATION
    • The installation of the platform consists of the following phases:
      • Preparation phase
      • Barge mooring
      • Platform lowering
      • Foundation installation
      • Completion activities
    Iv-Oil & Gas www.iv-groep.nl
  • 29. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING FABRICATION, TRANSPORT AND INSTALLATION
    • INSTALLATION
      • Sea fastening of substructure to the barge using hydraulic pins for swift release of the substructure from the barge after mooring,
      • Tow to the field using tugs,
      • Transport positive range of stability more than 50
      • degrees (criterion > 36 degrees),
      • Lowering stability (hydrostatic and hydrodynamic)
      • provided by ballast on the suction piles,
      • Lowering and lifting systems using strand jacks,
      • Suction pumps for the installation and future removal of the suction pile foundation,
      • No divers required for installation and removal of
      • installation equipment.
    Iv-Oil & Gas www.iv-groep.nl
  • 30. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SCHEDULE Iv-Oil & Gas www.iv-groep.nl
  • 31. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SCHEDULE
    • DEFINITION OF PROJECT PHASES
      • Conceptual design
      • Detail design
      • Procurement
      • Construction
      • Onshore test/commissioning
      • Transportation and installation
    Iv-Oil & Gas www.iv-groep.nl
  • 32. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING SCHEDULE
    • CONCEPT PLANNING
    Iv-Oil & Gas www.iv-groep.nl
  • 33. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING COST ESTIMATE Iv-Oil & Gas www.iv-groep.nl
  • 34. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING COST ESTIMATE OVERVIEW Iv-Oil & Gas www.iv-groep.nl --- --- --- --- Grand Total           --- ---     Overall contingency ~15% --- ---     Certification --- ---     Insurance --- ---     Fabrication and installation --- ---     Design & Procurement --- --- --- --- Equipment (incl commisioning) ---   --- --- Helideck ---   --- --- Topsides structual steel ---   --- --- Substructure (€·10 3 ) (€·10 3 ) (€·10 3 ) (€·10 3 )     costs costs Total Other Fabrication FoB Description
  • 35. PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING END OF PRESENTATION
    • QUESTIONS?
    Iv-Oil & Gas www.iv-groep.nl