SPRING 2011 RENOVATION PROJECT UPDATE
CENTER FOR INNOVATION VISUALIZATION & SIMULATION  CIVS  - POWERS EXPANSION  PROJECT  TOTAL SQUARE FOOTAGE 11,271  1 ST  FL...
REMOTE VIS LAB VISUALIZATION THEATER THEATER LOBBY VIS BOX STAFF WORKROOM STAFF OFFICES/ PRODUCTION AREA CVIS CIVS-FIRST F...
<ul><li>CIVS - VIEW OF COORIDOR TO THEATER ENTRANCE </li></ul>
 
 
 
 
<ul><li>CIVS – VISUALIZATION THEATER </li></ul>
 
 
POWERS 2 ND  FLOOR - FACULTY OFFICE EXPANSION DEPARTMENT OFFICE & 10 ADDITIONAL FACULTY OFFICES
HOSPITALITY & TOURISM MANAGEMENT THE CENTER REMODEL PROJECT  TOTAL SQUARE FOOTAGE 20,145  TOTAL PROJECT BUDGET $4.7M CONST...
STAFF   OFFICES  LOCKER ROOM/ STORAGE LEARNING  LAB BEVERAGE LAB 63 SEAT RESTAURANT COMMERCIAL KITCHEN FOODS LAB CLASSROOM...
HTM – VIEW LOOKING SOUTH INTO COORIDOR OUTSIDE THE STUDENT COMPUTER LAB
HTM – LEARN LAB  STUDENT COMPUTING
 
VIEW LOOKING SOUTH INTO COORIDOR  OUTSIDE THE BEVERAGE LAB
HTM – BEVERAGE LAB
HTM-BEVERAGE LAB - MILLWORK DETAIL
HTM – OVERHEAD VIEW OF THE RESTRAURANT  seating for 63
HTM – RESTRAURANT ENTRY
HTM – VIEW OF THE RESTRAURANT
HTM – VIEW OF THE RESTRAURANT & BAR AREA
HTM - RESTRAURANT
VIEWS OF RESTURANT SEATING
<ul><li>The office move plan started with the opening & occupancy of  the Schneider Avenue  Building - March 2010. </li></...
RECENTLY COMPLETED STUDENT UNION LIBRARY BOOKSTORE ENTRANCE
Water Institute Laboratory – Schneider Avenue West Total Project Cost:  $1.9M Target Completion Date:  April 2012
Energy Center Laboratory – Schneider Avenue West
 
 
Upcoming SlideShare
Loading in …5
×

Spring 2011 Current Projects

210 views
157 views

Published on

0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
210
On SlideShare
0
From Embeds
0
Number of Embeds
5
Actions
Shares
0
Downloads
0
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Spring 2011 Current Projects

  1. 1. SPRING 2011 RENOVATION PROJECT UPDATE
  2. 2. CENTER FOR INNOVATION VISUALIZATION & SIMULATION CIVS - POWERS EXPANSION PROJECT TOTAL SQUARE FOOTAGE 11,271 1 ST FLOOR 8,789 2 ND FLOOR 2,482 TOTAL PROJECT BUDGET $3.7M CONSTRUCTION BEGAN – NOVEMBER 2010 CONSTRUCTION COMPLETION - JULY 28, 2011 OCCUPANCY TO OCCUR LATE AUGUST 2011 OPERATIONAL FOR FALL 2011
  3. 3. REMOTE VIS LAB VISUALIZATION THEATER THEATER LOBBY VIS BOX STAFF WORKROOM STAFF OFFICES/ PRODUCTION AREA CVIS CIVS-FIRST FLOOR PLAN
  4. 4. <ul><li>CIVS - VIEW OF COORIDOR TO THEATER ENTRANCE </li></ul>
  5. 9. <ul><li>CIVS – VISUALIZATION THEATER </li></ul>
  6. 12. POWERS 2 ND FLOOR - FACULTY OFFICE EXPANSION DEPARTMENT OFFICE & 10 ADDITIONAL FACULTY OFFICES
  7. 13. HOSPITALITY & TOURISM MANAGEMENT THE CENTER REMODEL PROJECT TOTAL SQUARE FOOTAGE 20,145 TOTAL PROJECT BUDGET $4.7M CONSTRUCTION BEGAN – NOVEMBER 2010 CONSTRUCTION COMPLETION - JULY 18, 2011 OCCUPANCY TO OCCUR EARLY AUGUST 2011 OPERATIONAL FOR FALL 2011
  8. 14. STAFF OFFICES LOCKER ROOM/ STORAGE LEARNING LAB BEVERAGE LAB 63 SEAT RESTAURANT COMMERCIAL KITCHEN FOODS LAB CLASSROOMS STUDY ROOMS FACULTY OFFICES CLASSROOMS CONFERENCE ROOM PLAN VIEW OF HTM
  9. 15. HTM – VIEW LOOKING SOUTH INTO COORIDOR OUTSIDE THE STUDENT COMPUTER LAB
  10. 16. HTM – LEARN LAB STUDENT COMPUTING
  11. 18. VIEW LOOKING SOUTH INTO COORIDOR OUTSIDE THE BEVERAGE LAB
  12. 19. HTM – BEVERAGE LAB
  13. 20. HTM-BEVERAGE LAB - MILLWORK DETAIL
  14. 21. HTM – OVERHEAD VIEW OF THE RESTRAURANT seating for 63
  15. 22. HTM – RESTRAURANT ENTRY
  16. 23. HTM – VIEW OF THE RESTRAURANT
  17. 24. HTM – VIEW OF THE RESTRAURANT & BAR AREA
  18. 25. HTM - RESTRAURANT
  19. 26. VIEWS OF RESTURANT SEATING
  20. 27. <ul><li>The office move plan started with the opening & occupancy of the Schneider Avenue Building - March 2010. </li></ul><ul><li>To date 73 moves have been completed. </li></ul><ul><li>284 staff members have changed offices as a result of this project. </li></ul><ul><li>The next major phase will begin in early August as we occupy the offices created by the CIVS & HTM renovation projects. A total of 27 new offices have been created. </li></ul><ul><li>The next phase is to develop a new move plan </li></ul><ul><li>that will reallocate offices vacated by </li></ul><ul><li>the CIVS staff, ME & HTM. </li></ul><ul><li>University goals for the assignment of offices include: </li></ul><ul><li>Vacating the ANNEX offices </li></ul><ul><li>Consolidating departments that are currently located in more than one area. </li></ul>
  21. 28. RECENTLY COMPLETED STUDENT UNION LIBRARY BOOKSTORE ENTRANCE
  22. 29. Water Institute Laboratory – Schneider Avenue West Total Project Cost: $1.9M Target Completion Date: April 2012
  23. 30. Energy Center Laboratory – Schneider Avenue West

×