    Glen Ellyn Library Public Meetings - Presentation Transcript

    1. GEPL Public Meetings
      October 5, 6,and 10, 2009
    2. History
      Architect selected– Cordogan, Clark & Associates~1993
      Open bid process– E.W. Corrigan Construction~1994
      Owners Rep./Building Consultant – None
      Village Inspections– Passed
      Final Occupancy Permit ~1995
    3. History cont.
      1995-2001 Building Issues
      Stairs from 1st to 2nd floor
      Broken pipes outside front entrance and 3rd floor
      Mechanical failure
      Roof leak – East end
      Insurance Claims Filed
      First Roof Consultant Hired
      Multiple Consultants Later – Better Understanding of the Multiple Building Issues
    4. Current Building Conditions2007-Now
      Roof and Walls
      Cracks in interior walls
      Bread pan inside wall
      Soggy interior walls
      Cracks in between exterior wall joints
      Exterior EIFS cladding
      Lack of flashings
      Windows in upside down
      Shingles over exhaust pipe
    5. Current Building Conditions cont.
      HVAC
      Mechanical system issues
      Building envelope not sealed
      Lack of insulation
      Not energy efficient
      Often inappropriate temperatures
    6. Current Building Conditions cont.
      Other Capital Repairs
      Relamping
      Soffit Control Joints
      Basement Mechanical Pumps
      Carpeting
      Parking Lot
    7. Known and Unknown Future Capital Repairs
      Engberg Anderson Capital Repair Study
      Mechanical Systems
      Electrical Systems
      Architectural Systems
      Unknown
      Leaky Water Main
      Leaky Sprinkler System Valve
      Exterior Light Failure
    8. Two Part ProblemTwo Part Solution
      Problem
      Building not built as well as it could have been
      Lack of funds to maintain and repair the building
      Solution
      Bond Issue to Repair Existing Building Issues
      .03 Operating Tax Rate Increase for ongoing known and unknown repairs
    9. Sample Village Tax Bill
    10. Library Portion of Tax Bill
    11. Library Budget
    12. Line By Line 2009 Budget
    13. Library Revenues
    14. Line by Line 2009 Revenues
    15. Revenues cont.
    16. Anticipated Tax Increase
    17. Bond Issuance Building Repairs
    18. Current Capital Repairs
    19. Bond Issuance Tax Increase by Repair Category
    20. Historical Library Tax Rates
    21. More Information
      www.gepl.org
      Questions

    + Glen Ellyn Public LibraryGlen Ellyn Public Library, 1 month ago

    custom

    65 views, 0 favs, 2 embeds more stats

    Powerpoint Presentation From Public Meetings

    More info about this document

    © All Rights Reserved

    Go to text version

    • Total Views 65
      • 60 on SlideShare
      • 5 from embeds
    • Comments 0
    • Favorites 0
    • Downloads 0
    Most viewed embeds
    • 4 views on http://www.gepl.org
    • 1 views on http://gepl.org

    more

    All embeds
    • 4 views on http://www.gepl.org
    • 1 views on http://gepl.org

    less

    Flagged as inappropriate Flag as inappropriate
    Flag as inappropriate

    Select your reason for flagging this presentation as inappropriate. If needed, use the feedback form to let us know more details.

    Cancel
    File a copyright complaint
    Having problems? Go to our helpdesk?

    Categories