Project Management using MS Project 2010
Upcoming SlideShare
Loading in...5
×
 

Like this? Share it with your network

Share

Project Management using MS Project 2010

on

  • 491 views

Project Management Basic concepts with Microsoft® Project 2010

Project Management Basic concepts with Microsoft® Project 2010

Statistics

Views

Total Views
491
Views on SlideShare
488
Embed Views
3

Actions

Likes
2
Downloads
9
Comments
0

2 Embeds 3

http://www.linkedin.com 2
https://www.linkedin.com 1

Accessibility

Upload Details

Uploaded via as Microsoft PowerPoint

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

Project Management using MS Project 2010 Presentation Transcript

  • 1. Project Management Basic concepts with Microsoft ® Project 2010 By: Abdul Ghaffar PMP ghaffarsarwar@gmail.com +923434017209
  • 2. Objective • Projects Management Basics – What is a Project – Project Constraints – Project Planning, Monitoring & control – WBS • Getting started with MS Project (General Schedule Settings and Currency) • Creating Project in MS Project – Project Calendar – Task List – Task Notes – Duration – Linking Tasks 6/10/2014 By : Abdul Ghaffar, PMP 3
  • 3. Objective … – Lead & Lag – MileStone – Network Diagram – Critical Path – Adding Resource and its cost – Creating Baseline – Custom Fields • Tracking Project • Other Views and Reports 6/10/2014 By : Abdul Ghaffar, PMP 4
  • 4. What is a Project? A project is a temporary endeavor that helps to accomplish some specific objective by utilizing definite interconnected tasks and the effective utilization of resources. • To achieve an objective • One Time (Start and finish dates) • Constraints of time, cost and resources • Performed by People – Single or Group • Coordinated and controlled activities • Specific Deliverables • Progressive Elaboration 6/10/2014 By : Abdul Ghaffar, PMP 5
  • 5. Major Constraint on Project 6/10/2014 By : Abdul Ghaffar, PMP 6
  • 6. Project Process Groups 6/10/2014 By : Abdul Ghaffar, PMP 7
  • 7. PMBOK 5 6/10/2014 By : Abdul Ghaffar, PMP 8
  • 8. WBS for MS Project Training 1. Soft ware Development Plan 1.1 Scope 1.2 Analysis/Soft ware Requirements 1.3 Design 1.4 Developme nt 1.5 Testing 1.5.1 Unit Testing 1.5.2 Integration Testing 1.6 Training 1.7 Documenta tion 1.8 Pilot 1.9 Deploymen t 1.10 Post Implement ation Review 6/10/2014 By : Abdul Ghaffar, PMP 9
  • 9. Starting With MS Project 2010 File ->options -> Display 6/10/2014 By : Abdul Ghaffar, PMP 10
  • 10. Starting With MS Project 2010 File ->options -> Schedule 6/10/2014 By : Abdul Ghaffar, PMP 11
  • 11. MS Project 2010 6/10/2014 By : Abdul Ghaffar, PMP 12
  • 12. Task List 6/10/2014 By : Abdul Ghaffar, PMP 13
  • 13. Task Duration 6/10/2014 By : Abdul Ghaffar, PMP 14
  • 14. WBS Code 6/10/2014 By : Abdul Ghaffar, PMP 15
  • 15. Sub Task 6/10/2014 By : Abdul Ghaffar, PMP 16
  • 16. Link Task.. Finish to Start (FS), where the first must be finished before the next begins. Start to Start (SS), where 2 tasks must start at the same time. Finish to Finish (FF), where 2 tasks must end at the same time. Start to Finish (SF) , where the start of the first is linked to the completion of the second (with a lag time specified as well. 6/10/2014 By : Abdul Ghaffar, PMP 17
  • 17. Link Task 6/10/2014 By : Abdul Ghaffar, PMP 18
  • 18. Predecessors 6/10/2014 By : Abdul Ghaffar, PMP 19
  • 19. Lead & Lag Time • Lead time causes a successor task to overlap a predecessor even though they are linked finish to start (FS). • Lag time allows you to add a delay between the start of the successor and the end of the predecessor. – Simply specify lead or lag time in the Predecessor column. • Lead time is represented with a minus sign (-) • Lag time is represented with a plus sign (+). 6/10/2014 By : Abdul Ghaffar, PMP 20
  • 20. Lead and Lag 6/10/2014 By : Abdul Ghaffar, PMP 21
  • 21. Calendar 6/10/2014 By : Abdul Ghaffar, PMP 22
  • 22. MileStone Milestones let you gauge your progress through the project. It’s good practice to include a Start and Finish Milestone for each division/part of your WBS.6/10/2014 By : Abdul Ghaffar, PMP 23
  • 23. Resource 6/10/2014 By : Abdul Ghaffar, PMP 24
  • 24. Assign Resources to Tasks 6/10/2014 By : Abdul Ghaffar, PMP 25
  • 25. The Critical Path The Critical path is the flow of tasks, of which, a delay in any one of these tasks will cause a delay to the project. It is the longest path through the project network diagram and the shortest possible time to complete the project 6/10/2014 By : Abdul Ghaffar, PMP 26
  • 26. Critical Path 6/10/2014 By : Abdul Ghaffar, PMP 27
  • 27. Critical Path.. 6/10/2014 By : Abdul Ghaffar, PMP 28
  • 28. Slack 6/10/2014 By : Abdul Ghaffar, PMP 29 Slack is the amount of time that a task can slip before it affects another task or the project's finish date.
  • 29. Custom Field 6/10/2014 By : Abdul Ghaffar, PMP 30
  • 30. Tracking Project To control the variations from actual plan (baseline) we need to track project and continuously check the health of the project. • EVM is a financial measurement tool that combines the conflicting aspects of scope, schedule and cost into a unified set of metrics. • These metrics can be used for measuring, monitoring, reporting and forecasting project performance. It can be used through all the phases of a project, from initiation to closure. 6/10/2014 By : Abdul Ghaffar, PMP 31
  • 31. Earned Value … 6/10/2014 By : Abdul Ghaffar, PMP 32
  • 32. Example You have a project to build a new fence. the fence is four sided as shown. Each side is to take one day to build and is budgeted for $1000 per side. The sides are planed to be completed one after the other. Today is the end of day three. • Calculate AC, BAC, CV, CPI,SV, SPI, EAC etc. 6/10/2014 By : Abdul Ghaffar, PMP 33
  • 33. Plan Tasks 6/10/2014 By : Abdul Ghaffar, PMP 34
  • 34. Set Baseline 6/10/2014 By : Abdul Ghaffar, PMP 35
  • 35. Actual Status 6/10/2014 By : Abdul Ghaffar, PMP 36
  • 36. Check Status 6/10/2014 By : Abdul Ghaffar, PMP 37
  • 37. Status Summary 6/10/2014 By : Abdul Ghaffar, PMP 38
  • 38. Calendar View 6/10/2014 By : Abdul Ghaffar, PMP 39
  • 39. Network Diagram 6/10/2014 By : Abdul Ghaffar, PMP 40
  • 40. Other Reports 6/10/2014 By : Abdul Ghaffar, PMP 41
  • 41. THANKS 6/10/2014 By : Abdul Ghaffar, PMP 42