Bpd Presentation Elnaranjito
Upcoming SlideShare
Loading in...5
×
 

Like this? Share it with your network

Share

Bpd Presentation Elnaranjito

on

  • 506 views

 

Statistics

Views

Total Views
506
Views on SlideShare
487
Embed Views
19

Actions

Likes
0
Downloads
0
Comments
0

2 Embeds 19

http://www.gfa-uk.org 18
http://gfa-uk.org 1

Accessibility

Categories

Upload Details

Uploaded via as Microsoft PowerPoint

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

Bpd Presentation Elnaranjito Presentation Transcript

  • 1. ADVANCE REPORT, WATER AND GRAY WATER FILTERS PROJECT EL NARANJITO, SAN MARTIN JILOTEPEQUE. Prepared by Natanael Jocholá November 2009
  • 2. Running Water
    • This component is 90% completed. It was started on August of this year.
    • The Municipality from San Martín Jilotepeque is supporting the project through 3 masons and the technical supervision of an engineer.
    • The village provided wood and unskilled labor
  • 3.
    • BPD thanks to the funds donated by Guatemalan Families Association, an anonymous family foundation connected to Guatemala through adoption and Virginia May, is providing the construction materials, pipes and accessories
    Running Water Villagers laying the pipes for the distribution network
  • 4.
    • The components already built are:
    • Catchment tank
    • Air and pressure relief valves boxes
    • Distribution tank 50 cubic meters
    • Conduction line
    • Distribution network
    • Pending:
    • Spigots installation
    Catchment tank Running Water
  • 5. Running Water
    • According to the schedule, this component will be finished by November 20th.
    • The inauguration will be on Friday, November 27th, 2009
    Women hauling water from a contaminated river
  • 6.
    • 46 gray water filters are under construction. This component it is in the final stage.
    Gray Water Filters Woman with her gray water filter already installed
  • 7.
    • Beneficiaries have received educational talks about the problems caused by gray waters and training for the construction of the gray water
    Gray Water Filters Beneficiaries installing their gray water filter
  • 8.
    • We estimate to complete this component by November 25th
    Gray Water Filters Women in front of her absorption grave
  • 9. PROGRESS REPORT, INTEGRAL PROJECT VILLAGE CHUAQUENUN, PATZÚN Prepared by Natanael Jocholá November 2009
  • 10. BPD thanks to the funds donated by Guatemalan Families Association, an anonymous family foundation connected to Guatemala through adoption and Virginia May, is providing the construction materials, pipes and accessories The water project will benefit 37 families Beneficiaries digging trenches for the distribution network Running Water
  • 11.
    • The families hauled water from a communitarian sink located on the edge of the village.
    • This activity required between 30 minutes to 1 hour. In the dry season they had to walk farther as the water is insufficient for the whole village. All the family participated in the activity boys, girls and even elders.
    • This project will avoid diarrhoeas and skin problems to the villagers.
    Girls washing clothes at the public pila Running Water
  • 12. In the rainy season the road to the village is impassable, so the delivery of construction materials has been difficult. However the villagers have worked really hard that is why we estimate to finish the project by the end of this month Beneficiaries digging trenches for the distribution network Running Water
  • 13.
    • It was started on August of this year. Currently it is 80% completed.
    • Components completed:
    • Two catchment tanks
    • Distribution tank (30 cubic meters capacity)
    Catchment tank Running Water
  • 14.
    • Pending components:
    • Distribution network.
    • Spigot installation
    • Staff has developed two training sessions for the maintenance and repairs to the water system. The rules for the appropriate use of the water system were also created
    Distribution Tank Running Water
  • 15.
    • This project is 90% done. We estimate it will be completed by the end of this month.
    • Beneficiaries have been trained for the construction, installation and use of the filters.
    Gray Water Filters Benefited families with their absorption grave already dug ready for the gray water filters installation
  • 16.
    • Benefited families with their absorption grave already dug, ready for the gray water filters installation.
    Gray Water Filters
  • 17. VENTED LATRINES & IMPROVED STOVES
    • VENTED LATRINES.
    • Staff has developed training sessions. All the latrines will be installed by December 20th, 2009
    • IMPROVED STOVES
    • Beneficiaries have received training for its construction as well as educational talks about the importance of having an improved stove at home
    OBSERVATIONS: As soon as we have availability of funds for the construction of the stoves and latrines, we’ll be delivering the construction materials