SlideShare a Scribd company logo
1 of 30
Download to read offline
Patrick K. Barker       Glen B. Alleman
      MCR, LLC              Lewis & Fowler
   pbarker@mcri.com    galleman@lewisandfowler.com
    (703) – 898–6354         (303) – 241 9633

                                                     1/30
 Knowing what DONE looks like begins
                                     with the Integrated Master Plan.
                                    Recognizing what DONE looks like
                                     when it arrives means measuring the
                                     planned Technical Performance.
                                    Measuring Physical Percent Complete
                                     tells us how far we have moved
                                     toward DONE by calculating the
                                     “Earned Value” we’ve achieved.
                                    Connecting Earned Value, Technical
                                     Performance, and Physical Percent
Connect Quality with Performance     Complete in the IMP establishes a
                                     credible measure of Progress to Plan.
                                    Without these four elements we don’t
                                     have a clue to what DONE looks like or
                                     if we’ll ever get there as planned.

                                                                         2/30
Evidence of DONE         Measures of DONE             Beneficial Outcomes
     IMP           The collection of TPM, EV, and
                                                     The IMP then defines
Accomplishment     PPC measures defined as “exit
                                                     the measurable path to
    Criteria       criteria” for the Work Packages
                                                     the planned maturity.
     (AC)          performing the work.
   Technical       The actual technical              Evidence that the
  Performance      performance measured at a         product or service is
    Measure        defined date compared to          meeting the planned
     (TPM)         planned technical performance.    maturity or quality.
                                                   Evidence of completion
Physical Percent   Unit of measure to assess the
                                                   of the planned work in
   Complete        planned technical performance,
                                                   units meaningful to the
     (PPC)         evidenced by tangible outcomes.
                                                   customer.
                   Cost and schedule needed to       The performance
  Earned Value
                   deliver the planned technical     measured in units of
      (EV)
                   performance on baseline.          dollars.

                                                                              3/30
No Matter How Great and Destructive Your
Problems May Seem Now, Remember, You’ve
    Probably only Seen the Tip of Them


                                            4/30
5/30
A Technical Performance Measures …
 State how well the program is achieving the
  planned performance requirements at the
  planned delivery time.
 Use actual or predicted values from:
   –   Engineering measurements
   –   Tests
   –   Experiments
   –   Prototypes
 For Example:
   –   Response time
   –   Flight range
   –   Power consumption
   –   Static takeoff weight
   –   Product Quality

                                                6/30
Document, Baseline,
           IMS, EVM                         Parameter
 IMP, Functional Baseline        Measures Of Effectiveness (MOE)   

 IMP, WBS, Functional Baseline   Measures Of Performance (MOP)     
 IMP, Allocated Baseline         Technical Performance Measure     
                                  TPM Milestones And Planned
 IMS                                                               
                                  Values
 Work Packages                   TPM% Complete Criteria            




                                                                    7/30
Physical Percent Complete Requires A Tangible
         Measure of “Progress to Plan”
                           Tangible evidentiary
                            materials measure
                            progress to plan.
                           Pre–defined
                            existence of this
                            evidence in
                            meaningful units of
                            measure established
                            before starting work.
 No Hand Waving Allowed
  “Show Me The Money”      Progress is defined in
                            these same units of
                            measure.             8/30
IMP
Describes how the                       Major program milestones or assessment events that substantiate system
capabilities will be                    maturity (initial, progress, or final). These milestones or assessment events
delivered and             Events        deliver the specific capabilities for the system on planned dates.
how these                Milestones
capabilities will
be recognized                               Specified result, substantiating a Milestone or Event, that indicates
                       Accomplishment
                                            maturity or progress for each product or process
                                                   Definitive measures substantiating the Accomplishment maturity
                          Criteria                 level. Completion of specific work that ensures closure of a
                                                   specified Accomplishment
IMS                                                   Work activities performed to produce the deliverables that
                  Work Packages and Tasks             fulfill the requirements that enable the capabilities

                   Supplemental Schedules




                                                                                                                        9/30
Measure the progress to plan using Physical % Complete at the
               Accomplishment Criteria (AC) and CWBS level

      Program                               Statement of
                                                                                          CWBS
       Events                                   Work
               Completed SA’s are                                             Work structure
   Aligned     entry criteria for                                                 aligned to
               Program Events                                                          SOW


    Significant
 Accomplishments
               Completed Work
   Aligned     Packages are exit
                                                      Defines                                  Aligned
               criteria for Tasks


  Accomplishment                             CDRLs and                              Tasks Contained
      Criteria                 Aligned       Deliverables                Aligned   in Work Packages
Describes increasing                     Documents the product                     Work necessary to
product maturity as 0/100 or             maturity that is aligned with             mature products
EVMS SD guidance                         SOW and CWBS                              grouped by CWBS


                                                                                                         10/30
0.0                       TOTAL BRILLIANT EYES PROGRAM
                                                                                                                               Planned
                                                                                                                               Profile       Tolerance Band
  1.0                       SPACE BRILLIANT EYES SYSTEM




                                                                                  Technical Parameter Value
    1.1                     System-Level Costs




                                                                                  (e.g., Vehicle Weight, lb)
    1.2                     Space Vehicle (SV) Segment

                                                                                                               15
       1.2.1                SV Program Level
       1.2.2                Space Vehicle Prime Mission Equipment                                                                                          Achieved
                                                                                                                                                           To Date
            1.2.2.1         Space Software
            1.2.2.2         Space Vehicle
            1.2.2.2.1
            1.2.2.2.2
                            Space Vehicle IA&T
                            Sensor Payload
                                                                                                                                                                   Variation
            1.2.2.2.3
            1.2.2.2.4
                            Insertion Vehicle
                            Survivability                                                                      10
       1.2.3                Prototype Lot
       1.2.4
       1.2.5
                            Spare Parts
                            Technology and Producibility
                                                                                                                                                                        Threshold
       1.2.6                Aerospace Ground Equipment
                                                                                                               5                             Planned
    1.3
       1.2.7                Launch Support
                            Engineering Change Orders (ECOs)                                                                                 Value                       Current
    1.4
    1.5
                            Other Government Costs
                            Risk
                                                                                                                                                                         Estimate

A WBS can be displayed as a                                                                                                                  Milestones
“linear” List. Program Cost is often
Calculated by summing the Costs of                                                                                 Technical performance measurement have often been
All Items on That List … but that                                                                                  treated as an engineering function only, not typically
ignores correlation and basic math:                                                                                linked with EVM, although it shares a common, almost
distributions don’t add that way.                                                                                  identical, language structure with EVM.

                        2     1       6       4       3       5
                                                                                                                   The Schedule Network is Nonlinear, and Program Duration
                                                                                                                   Cannot be Calculated by Adding Together the Durations of
                                  3       1       6       9       2   4                                            All Activities in the Network. And since time is money it is
                                                                                                                   important for schedule slips to reflect cost
                                                      6       9       2   1   4   2                 1


                                                                                                                                                                                    11/30
 Neither cost performance nor schedule performance nor technical
  performance measurement can be fully evaluated by itself.




                                                                    12/30
How to Define DONE




 Determine Physical Percent Complete based in performance measurement
  – Compare actual performance against an integrated baseline planned performance of the
    integrated cost, schedule and technical goals.
 This measurement is possible within a performance measurement system
  – Use the organization’s internal management control system to provide decision makers with
    specific performance information about the progress and expenditures against the planed progress
    and expenditures.
 In many projects where EVM systems are implemented, what a CAM determines
  (“eyeballing”) as physical percent complete often differs from what is reported
  via the EV techniques.
  – This disconnect in measurement of “done–ness” is a clear sign that a cost, schedule and/or
    technical performance problem is going to materialize before the PM can properly react.
                                                                                                  13/30
Risk         Cost

IMS          PMB          SOW

      WBS          TPM


                                14/30
Perform     Determine                    Develop           Develop
                                                                              Approve
     Functional   Scope and                    Technical         Technical
                                                                               PMB
      Analysis    Approach                       Logic           Baseline



Technical         Develop
Performance        WBS
Baseline

                                   Estimate                                    Finalize
                   Define                          Sequence      Finalize
                                     Time                                    Apportioned
                  Activities                       Activities   Schedule
                                   Durations                                  Milestones


Schedule                                           Identify
Performance                                      Apportioned
                                                  Milestones
Baseline

Cost                            Determine          Prepare      Resource     Determine
                                 Resource            Cost         Load        Funding
Performance                    Requirement         Estimate     Schedule     Constraints
Baseline


                                                                                           15/30
Making Trades
     Between
  Cost, Schedule,
        and
   Performance
Baselines is a Ponzi
      Scheme
     When we’re on
 baseline, the algebraic
  relationship between
   C,S,P, means when
    there is a change
     everyone loses

                           16/30
A Really Simple Example of Physical
           Percent Complete
                          Painting a room is simple example to
                           focused on a notion of percent complete.
                          But how about a flight avionics system?
                          What are the measures of physical percent
                           complete?
                           ‒ Design basis complete and verified
                           ‒ Hardware platform increasing capabilities
                           ‒ Software system increasing capabilities
                           ‒ Integration and test of 1st flight article
                           ‒ Operational verification and validation
                             complete

 Where can we look for these measures of physical percent complete?
It’s Obvious – in the Integrated Master Plan’s Accomplishment Criteria
                                                                     17
18/30
 The notion of measuring physical percent
                            complete is at the core of every project
                            management method.
                           It answers the question of what DONE is
                            in units of measure meaningful to the
                            program.
                           This helps us determine answers to
No stretching the truth
  is allowed once we        questions that include, but are not limited
 start using Technical      to:
      Performance            – What does DONE look like for today, for this
     Measures with             week, or for this month?
   tangible evidence.        – What does DONE look like for entry/exit into
                               the technical review?
                             – What does DONE look like for quality control?
                             – What does DONE look like for the customer?
                                                                           19/30
 The increasing maturing of a product or service is described through Events or Milestones,
  Accomplishments, Criteria, and their Work Packages or Planning Packages.                                The Structure of a
 Each Event or Milestone represents the availability of one or more capabilities.                          Credible IMP
 The presence of these capabilities is measured by the Accomplishments and their Criteria.
 Accomplishments are the pre–conditions for the maturity assessment of the product or service at    Program Events
  each Event or Milestone.                                                                           Define the availability
 This hierarchy decomposes the System Capabilities into Requirements, Work Packages, and the        of a Capability at a point in
  activities which produce deliverables. This hierarchy also describes increasing program maturity   time.
  resulting from the activities contained in the Work Packages.
 Performance of the work activities, Work Packages, Criteria, Accomplishments, and Events or
  Milestones is measured in units of “physical percent complete” by connecting Earned Value with
  Technical Performance Measures.


                        Accomplishments
                        Represent requirements
                        that enable Capabilities.

Criteria
Represent Work Packages that
fulfill Requirements.


         Work                             Work                                      Work                               Each WP must
        Package                          Package                                   Package                            have a measure
                                                                                                                         of Physical
                                                                                                 Work                     Percent
                   Work                             Work                                                                 Complete
                  Package                          Package                                      Package

                                                                                                             Work
         Work                                                 Work                                          package
        Package                                              Package
                                                                                                                                 20/30
21/30
IEEE 1220: 6.8.1.5,             EIA–632: Glossary            CMMI for Development
   Performance–based                                            Requirements Development
  progress measurement
TPMs are key to                Predict future value of key      Specific Practice (SP) 3.3,
progressively assess           technical parameters of the      Analyze Requirements
technical progress             end system based on              Typical work product:
                               current assessments              Technical Performance
                                                                Measures

Establish dates for            Planned value profile is time–   Sub Practice (SP):
  – Checking progress          phased achievement projected
                                                                Identify TPMs that will be
  – Meeting full conformance     – Achievement to date          tracked during development
    to requirements              – Technical milestone where
                                   TPM evaluation is
                                   reported



                                                                                              22/30
23/30
EV TPM       What this tells the PM                    Derived Measurements
                                                                      Number of requirements approved, percentage
                            How well the system is maturing as        requirements growth, number TBD/TBR closure per plan,
           Requirements
                            compared to expectations                  estimated impact of changes, defect profile, defect density,
                                                                      cycle time for requirements changes
System Definition Change If changes are being made in a timely
                                                                      Approval rates, closure rates, cycle times, priority density
                 Backlog manner
                                                                      Number interfaces approved, percent interface growth,
                            Risk associated with interface            number TBD/TBR closure per plan, estimated impact of
                Interface
                            development and maturity                  interface changes, defect profile, defect density, cycle time
                                                                      for interface changes
                         If requirements are being validated with
                                                                      Requirements validation rate.
 Requirement Validation applicable stakeholders appropriate to
                                                                      Percent requirements validated
                         the level of requirement.
                         If requirements are being verified           Requirements verification rate.
Requirement Verification
                         appropriate to the level of requirement.     Percent requirements verified
                                                                      Approval rate, distribution of dispositions, approval rate
  Work Product Approval Work progress and approval efficiency
                                                                      performance
Technical/Design Review Progress in closing significant action        Closure rates, action item closure performance, variance
          Action Closure items from technical reviews                 from thresholds
                            Maturity of key components,               Component –Subsystem– Element –System TRL, Technology
    Technology Maturity
                            subsystems, elements to expectations      opportunity exposure, technology obsolescence exposure
                            Effectiveness of the risk management      Percentage of risk handling actions closed on time, percent
 Technical Risk Handling
                            process                                   overdue, percent of risks meeting handling expectations
   Technical Staffing And Adequacy of technical effort and            Technical effort staffing, variance.
                     Skills dynamics of actual staffing mix           Efficiency by labor category
                            Current performance status, projections   Delta performance (planned versus actual).
  Technical Performance
                            and associated risk                       Delta performance to thresholds, objectives

                                                                                                                                 24/30
Control Account
                      WP1: Chassis                      WP2: Array




              Completion Criteria & Taking “Value” for Work Packages
 Chassis            June                July               August               Sept
  Current           100                 150                  200                 250
Completion     Requirement      Design 80%             All TPM within      Build complete;
 Criteria      Quality          (drawings)             pre–build           All TPM
                                Completed; TPM         tolerances via      validated by
                                2, 5 and 6 within      refined             actual
                                PDR tolerances         performance         measurement
                                via basic              model; TPM 1
                                performance            and 6 verified
                                model                  via bench testing
Cummulative         100                 250                  450                 700

                                                                                        25/30
Using Periodic Program Events to Calibrate “Doneness”
                                                                            INPUT                                                                  PROCESS                                                                             OUTPUT

                          Program Requirements &                                                                                                                                                                  Program–level Risk Assessment of the
                                  Scope                                                                                                                                                                                   technical baseline
                                                          Lvl 1 WBS




                          Program Cost & Schedule
                                 Estimate
                                                          Cumulative Distribution Function
                            1
                          0.9


                                                                                                                                                                                                                                   IPT–level risks
                          0.8
                          0.7
            Probability




                          0.6
                          0.5
                          0.4
                                                                                                                                        When it comes right down to it, the                                                        (10’s)
                          0.3
                          0.2
                          0.1
                            0
                                                                                                                                       IBR is all about the technical baseline.
                                                                                                                                        IBRs should accompany each major
                           250000 300000 350000 400000 450000 500000 550000 600000 650000
                                                                                    Total Cost




                                                                                                                                                                                  Rollup of quantified process & product risks
            Date: 3/17/2009 8:35:32 AM
            Samples: 2000
            Unique ID: 114
            Name: FIST GEO-1
                                                                                            Completion Std Deviation: 71.23 days
                                                                                            95% Confidence Interval: 3.12 days
                                                                                            Each bar represents 25 days
                                                                                                                                                  baseline evolution.
                 0.16

                 0.14
                                                                                   1.0
                                                                                   0.9
                                                                                                   Completion Probability Table
                                                                                                                                         In the end, the question implicitly
                                 Cumulative Probability




                                                                                            Prob   Date            Prob    Date
                                                                                   0.8
                 0.12                                                                       0.05   10/21/2010      0.55    3/24/2011


                                                                                                                                            asked of the PM each time is:
                                                                                   0.7      0.10   11/11/2010      0.60    4/7/2011
Frequency




                 0.10                                                              0.6      0.15   12/2/2010       0.65    4/25/2011
                 0.08                                                              0.5      0.20   12/20/2010      0.70    5/10/2011
                                                                                   0.4      0.25   1/3/2011        0.75    5/27/2011
                 0.06


                                                                                                                                       “What is your confidence level in your
                                                                                            0.30   1/14/2011       0.80    6/16/2011
                 0.04

                 0.02
                                                                                   0.3
                                                                                   0.2
                                                                                   0.1
                                                                                            0.35
                                                                                            0.40
                                                                                            0.45
                                                                                                   1/28/2011
                                                                                                   2/9/2011
                                                                                                   2/22/2011
                                                                                                                   0.85
                                                                                                                   0.90
                                                                                                                   0.95
                                                                                                                           7/5/2011
                                                                                                                           7/26/2011
                                                                                                                           9/9/2011
                                                                                                                                                                                                                                 CA–level risks
                          7/6/2010                         3/17/2011
                                                          Completion Date
                                                                            3/16/2012
                                                                                            0.50   3/8/2011        1.00    3/16/2012

                                                                                                                                             program’s ability to hit cost,                                                      (100’s)
                                                                  IBR Guidance                                                               schedule, and scope targets
                                                                                                                                           associated with your technical
                                                                                                                                                      baseline”




                                                                                                                                                                                                                                                     26/30
Connecting Risk Management with Measures of DONE

                                                                    Risk: CEV-037 - Loss of Critical Functions During Descent


24
                                                                                Correlate the analytical model
22                                                                  Conduct focus splinter review

20                                             Develop analytical model to de
                            Conduct Force and Moment Wind
18
                                                                     Conduct Block 1 w ind tunnel te
16                                                                                                                    Conduct w ind tunnel testing of
                                                                                            Conduct w ind tunnel testing of
14
                                                                                                                                 Flight Application of Spacecra
12

10                                                                                                                                                    CEV block 5 w ind tunnel testin

 8

 6

 4
                                                                                                                          In-Flight development tests of
 2                                                                                                                                                            Damaged TPS flight test

 0
                                             3.Jul.06




                                                                                                                                                                                                    1.Jul.11
     31.Mar.05




                 5.Oct.05




                                                                                 1.Jun.07




                                                                                                                                                                   1.Jan.10




                                                                                                                                                                                        16.Dec.10
                                                        15.Sep.06
                                  3.Apr.06




                                                                                                           1.Apr.08


                                                                                                                      1.Aug.08




                                                                                                                                           1.Apr.09




                       Planned Risk Level                                                                                         Planned (Solid=Linked, Hollow =Unlinked, Filled=Complete)




                                        Risk Response                                                                                                           Milestone Date
                                        and Risk ID in                                                                                                        traceable between
                                             IMS                                                                                                               RM Tool and IMS




                                                                                                                                                                                                               27/30
Risk         Cost

IMS          PMB      SOW

      WBS          TPM




                            28/30
A Credible Performance Measurement System
     Assures the information is available to the decision maker, needed to deliver
                      on‒time, on‒budget, and on‒specification

                                               =
                               Technical Performance Measures
                 Cost                          +                     Schedule

                                 Conventional Earned Value

       Cost Baseline                 Technical Performance             Schedule Baseline

 The Master Schedule              Earned Value is diluted by     Requirements are
  used to derive Basis of           missing technical               decomposed into physical
  Estimate (BOE) not the            performance.                    deliverables.
  other way around.                Earned Value is diluted by     Deliverables are produced
 Probabilistic cost                postponed features.             through Work Packages.
  estimating uses past             Earned Value is diluted by     Work Packages are
  performance and cost risk         non compliant quality.          assigned to accountable
  modeling.                        All these dilutions require     manager.
 Labor, Materiel, and other        adjustments to the             Work Packages are
  direct costs accounted for        Estimate at Complete            sequenced to form the
  in Work Packages.                 (EAC) and the To                highest value stream with
 Risk adjustments for all          Complete Performance            the lowest technical and
  elements of cost.                 Index (TCPI).                   programmatic risk.
                                                                                            29/30
Connecting Measures of Cost, Schedule, and
Technical Performance
means the
difference
between …

Measuring Actual Physical Percent Complete
against the Planned Physical Percent Complete
at the time that Physical Percent Complete
was planned to be achieved is the foundation
of determining a program’s performance.
Doing anything else leads to disappointment.
                                                30/30

More Related Content

What's hot

Chambers.calvin
Chambers.calvinChambers.calvin
Chambers.calvinNASAPMC
 
Calculating Physical Percent Complete on Agile Projects
Calculating Physical Percent Complete on Agile ProjectsCalculating Physical Percent Complete on Agile Projects
Calculating Physical Percent Complete on Agile ProjectsGlen Alleman
 
Backup darren elliott
Backup darren elliottBackup darren elliott
Backup darren elliottNASAPMC
 
William.miller.pmc2010
William.miller.pmc2010William.miller.pmc2010
William.miller.pmc2010NASAPMC
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.garyNASAPMC
 
Eggert.joe
Eggert.joeEggert.joe
Eggert.joeNASAPMC
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News WebinarGlen Alleman
 
Jerald kerby
Jerald kerbyJerald kerby
Jerald kerbyNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
The Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software DevelopmentThe Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software DevelopmentGlen Alleman
 
Bobby.german
Bobby.germanBobby.german
Bobby.germanNASAPMC
 
C armstrong tbyers
C armstrong tbyersC armstrong tbyers
C armstrong tbyersNASAPMC
 
The integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleThe integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleGlen Alleman
 
Defining The Project
Defining The ProjectDefining The Project
Defining The ProjectEarl Tongol
 
Control Account Manager Short Course
Control Account Manager Short CourseControl Account Manager Short Course
Control Account Manager Short CourseGlen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 
Building a Credible Performance Measurement Baseling
Building a Credible Performance Measurement BaselingBuilding a Credible Performance Measurement Baseling
Building a Credible Performance Measurement BaselingGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthewNASAPMC
 

What's hot (20)

Chambers.calvin
Chambers.calvinChambers.calvin
Chambers.calvin
 
Calculating Physical Percent Complete on Agile Projects
Calculating Physical Percent Complete on Agile ProjectsCalculating Physical Percent Complete on Agile Projects
Calculating Physical Percent Complete on Agile Projects
 
Backup darren elliott
Backup darren elliottBackup darren elliott
Backup darren elliott
 
William.miller.pmc2010
William.miller.pmc2010William.miller.pmc2010
William.miller.pmc2010
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
 
Eggert.joe
Eggert.joeEggert.joe
Eggert.joe
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News Webinar
 
Jerald kerby
Jerald kerbyJerald kerby
Jerald kerby
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
The Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software DevelopmentThe Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software Development
 
Bobby.german
Bobby.germanBobby.german
Bobby.german
 
C armstrong tbyers
C armstrong tbyersC armstrong tbyers
C armstrong tbyers
 
The integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleThe integrated master plan and integrated master schedule
The integrated master plan and integrated master schedule
 
Symons
SymonsSymons
Symons
 
Defining The Project
Defining The ProjectDefining The Project
Defining The Project
 
Control Account Manager Short Course
Control Account Manager Short CourseControl Account Manager Short Course
Control Account Manager Short Course
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Building a Credible Performance Measurement Baseling
Building a Credible Performance Measurement BaselingBuilding a Credible Performance Measurement Baseling
Building a Credible Performance Measurement Baseling
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthew
 

Viewers also liked

Establishing the performance measurement baseline (pmi fort worth)(v4)
Establishing the performance measurement baseline (pmi fort worth)(v4)Establishing the performance measurement baseline (pmi fort worth)(v4)
Establishing the performance measurement baseline (pmi fort worth)(v4)Glen Alleman
 
A possible cure 2014 may9
A possible cure 2014 may9A possible cure 2014 may9
A possible cure 2014 may9Glen Alleman
 
Pedir lo mismo de diferentes maneras
Pedir lo mismo de diferentes manerasPedir lo mismo de diferentes maneras
Pedir lo mismo de diferentes manerasAntonio Salvadores
 
UIKit User Interface Catalog (iOS 7)
UIKit User Interface Catalog (iOS 7)UIKit User Interface Catalog (iOS 7)
UIKit User Interface Catalog (iOS 7)Evgeny Belyaev
 
Avoid software project horror stories - check the reality value of the estima...
Avoid software project horror stories - check the reality value of the estima...Avoid software project horror stories - check the reality value of the estima...
Avoid software project horror stories - check the reality value of the estima...Harold van Heeringen
 
Principles of program governance
Principles of program governancePrinciples of program governance
Principles of program governanceGlen Alleman
 
Immutable Principles Of Project Management (V7 Final Cmu)
Immutable Principles Of Project Management (V7 Final Cmu)Immutable Principles Of Project Management (V7 Final Cmu)
Immutable Principles Of Project Management (V7 Final Cmu)Glen Alleman
 
Customer Intelligence & Social Media
Customer Intelligence & Social MediaCustomer Intelligence & Social Media
Customer Intelligence & Social MediaAmplified Analytics
 
Inversion of Control
Inversion of ControlInversion of Control
Inversion of ControlGlen Alleman
 
Fix you some bad estimation habits
Fix you some bad estimation habitsFix you some bad estimation habits
Fix you some bad estimation habitsTed M. Young
 
PMI chapter meeting (v4)
PMI chapter meeting (v4)PMI chapter meeting (v4)
PMI chapter meeting (v4)Glen Alleman
 
The Social Shift Fund - Presentation
The Social Shift Fund - Presentation The Social Shift Fund - Presentation
The Social Shift Fund - Presentation Marine Aubin
 
Risk management processes
Risk management processesRisk management processes
Risk management processesGlen Alleman
 
Big data meets evm (submitted).pptx
Big data meets evm (submitted).pptxBig data meets evm (submitted).pptx
Big data meets evm (submitted).pptxGlen Alleman
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growthGlen Alleman
 
Architectured Centered Design
Architectured Centered DesignArchitectured Centered Design
Architectured Centered DesignGlen Alleman
 
Systems Engineering in One Picture
Systems Engineering in One PictureSystems Engineering in One Picture
Systems Engineering in One PictureGlen Alleman
 
iOS 7 Human Interface Guidelines
iOS 7 Human Interface GuidelinesiOS 7 Human Interface Guidelines
iOS 7 Human Interface GuidelinesEvgeny Belyaev
 
PM Chapter on Agile IT Project Management Methods
PM Chapter on Agile IT Project Management MethodsPM Chapter on Agile IT Project Management Methods
PM Chapter on Agile IT Project Management MethodsGlen Alleman
 

Viewers also liked (20)

Establishing the performance measurement baseline (pmi fort worth)(v4)
Establishing the performance measurement baseline (pmi fort worth)(v4)Establishing the performance measurement baseline (pmi fort worth)(v4)
Establishing the performance measurement baseline (pmi fort worth)(v4)
 
A possible cure 2014 may9
A possible cure 2014 may9A possible cure 2014 may9
A possible cure 2014 may9
 
Pedir lo mismo de diferentes maneras
Pedir lo mismo de diferentes manerasPedir lo mismo de diferentes maneras
Pedir lo mismo de diferentes maneras
 
UIKit User Interface Catalog (iOS 7)
UIKit User Interface Catalog (iOS 7)UIKit User Interface Catalog (iOS 7)
UIKit User Interface Catalog (iOS 7)
 
Avoid software project horror stories - check the reality value of the estima...
Avoid software project horror stories - check the reality value of the estima...Avoid software project horror stories - check the reality value of the estima...
Avoid software project horror stories - check the reality value of the estima...
 
Principles of program governance
Principles of program governancePrinciples of program governance
Principles of program governance
 
Immutable Principles Of Project Management (V7 Final Cmu)
Immutable Principles Of Project Management (V7 Final Cmu)Immutable Principles Of Project Management (V7 Final Cmu)
Immutable Principles Of Project Management (V7 Final Cmu)
 
Universidades
Universidades Universidades
Universidades
 
Customer Intelligence & Social Media
Customer Intelligence & Social MediaCustomer Intelligence & Social Media
Customer Intelligence & Social Media
 
Inversion of Control
Inversion of ControlInversion of Control
Inversion of Control
 
Fix you some bad estimation habits
Fix you some bad estimation habitsFix you some bad estimation habits
Fix you some bad estimation habits
 
PMI chapter meeting (v4)
PMI chapter meeting (v4)PMI chapter meeting (v4)
PMI chapter meeting (v4)
 
The Social Shift Fund - Presentation
The Social Shift Fund - Presentation The Social Shift Fund - Presentation
The Social Shift Fund - Presentation
 
Risk management processes
Risk management processesRisk management processes
Risk management processes
 
Big data meets evm (submitted).pptx
Big data meets evm (submitted).pptxBig data meets evm (submitted).pptx
Big data meets evm (submitted).pptx
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growth
 
Architectured Centered Design
Architectured Centered DesignArchitectured Centered Design
Architectured Centered Design
 
Systems Engineering in One Picture
Systems Engineering in One PictureSystems Engineering in One Picture
Systems Engineering in One Picture
 
iOS 7 Human Interface Guidelines
iOS 7 Human Interface GuidelinesiOS 7 Human Interface Guidelines
iOS 7 Human Interface Guidelines
 
PM Chapter on Agile IT Project Management Methods
PM Chapter on Agile IT Project Management MethodsPM Chapter on Agile IT Project Management Methods
PM Chapter on Agile IT Project Management Methods
 

Similar to Connecting Quality with Performance Measures

Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Cpm500 d _alleman__tpm lesson 3 (v1)
Cpm500 d _alleman__tpm lesson 3 (v1)Cpm500 d _alleman__tpm lesson 3 (v1)
Cpm500 d _alleman__tpm lesson 3 (v1)Glen Alleman
 
IIE Call For Paper
IIE Call For PaperIIE Call For Paper
IIE Call For Papermdmilward
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and AgileGlen Alleman
 
Integrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementIntegrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementGlen Alleman
 
EVMS for Commercial projects
EVMS for Commercial projectsEVMS for Commercial projects
EVMS for Commercial projectsGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
Physical Percent Complete for Agile Projects
Physical Percent Complete for Agile ProjectsPhysical Percent Complete for Agile Projects
Physical Percent Complete for Agile ProjectsGlen Alleman
 
Requirements elicitation
Requirements elicitationRequirements elicitation
Requirements elicitationGlen Alleman
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementGlen Alleman
 
How should we estimates agile projects (CAST)
How should we estimates agile projects (CAST)How should we estimates agile projects (CAST)
How should we estimates agile projects (CAST)Glen Alleman
 
Alleman ps03 - physical percent complete (v2)
Alleman   ps03 - physical percent complete (v2)Alleman   ps03 - physical percent complete (v2)
Alleman ps03 - physical percent complete (v2)Glen Alleman
 
Earned value in five easy pieces
Earned value in five easy piecesEarned value in five easy pieces
Earned value in five easy piecesGlen Alleman
 
10 taxonomy elements
10 taxonomy elements10 taxonomy elements
10 taxonomy elementsGlen Alleman
 
Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)Glen Alleman
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned ValueGlen Alleman
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)Glen Alleman
 
R simpson elee
R simpson eleeR simpson elee
R simpson eleeNASAPMC
 

Similar to Connecting Quality with Performance Measures (20)

Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Cpm500 d _alleman__tpm lesson 3 (v1)
Cpm500 d _alleman__tpm lesson 3 (v1)Cpm500 d _alleman__tpm lesson 3 (v1)
Cpm500 d _alleman__tpm lesson 3 (v1)
 
IIE Call For Paper
IIE Call For PaperIIE Call For Paper
IIE Call For Paper
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and Agile
 
Integrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementIntegrating Agile and Earned Value Management
Integrating Agile and Earned Value Management
 
EVMS for Commercial projects
EVMS for Commercial projectsEVMS for Commercial projects
EVMS for Commercial projects
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
Physical Percent Complete for Agile Projects
Physical Percent Complete for Agile ProjectsPhysical Percent Complete for Agile Projects
Physical Percent Complete for Agile Projects
 
Requirements elicitation
Requirements elicitationRequirements elicitation
Requirements elicitation
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value Management
 
How should we estimates agile projects (CAST)
How should we estimates agile projects (CAST)How should we estimates agile projects (CAST)
How should we estimates agile projects (CAST)
 
Alleman ps03 - physical percent complete (v2)
Alleman   ps03 - physical percent complete (v2)Alleman   ps03 - physical percent complete (v2)
Alleman ps03 - physical percent complete (v2)
 
DPPM1
DPPM1DPPM1
DPPM1
 
Earned value in five easy pieces
Earned value in five easy piecesEarned value in five easy pieces
Earned value in five easy pieces
 
10 taxonomy elements
10 taxonomy elements10 taxonomy elements
10 taxonomy elements
 
Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned Value
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)
 
R simpson elee
R simpson eleeR simpson elee
R simpson elee
 

More from Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management TheoryGlen Alleman
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesGlen Alleman
 

More from Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 

Recently uploaded

Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Commit University
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxLoriGlavin3
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxLoriGlavin3
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLScyllaDB
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfAddepto
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr BaganFwdays
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024Lonnie McRorey
 
SALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICESSALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICESmohitsingh558521
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenHervé Boutemy
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxLoriGlavin3
 
Ryan Mahoney - Will Artificial Intelligence Replace Real Estate Agents
Ryan Mahoney - Will Artificial Intelligence Replace Real Estate AgentsRyan Mahoney - Will Artificial Intelligence Replace Real Estate Agents
Ryan Mahoney - Will Artificial Intelligence Replace Real Estate AgentsRyan Mahoney
 
Sample pptx for embedding into website for demo
Sample pptx for embedding into website for demoSample pptx for embedding into website for demo
Sample pptx for embedding into website for demoHarshalMandlekar2
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxLoriGlavin3
 
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
What is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfWhat is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfMounikaPolabathina
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxLoriGlavin3
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxLoriGlavin3
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 

Recently uploaded (20)

Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptx
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQL
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdf
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024
 
SALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICESSALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICES
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache Maven
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
 
Ryan Mahoney - Will Artificial Intelligence Replace Real Estate Agents
Ryan Mahoney - Will Artificial Intelligence Replace Real Estate AgentsRyan Mahoney - Will Artificial Intelligence Replace Real Estate Agents
Ryan Mahoney - Will Artificial Intelligence Replace Real Estate Agents
 
Sample pptx for embedding into website for demo
Sample pptx for embedding into website for demoSample pptx for embedding into website for demo
Sample pptx for embedding into website for demo
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
 
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
What is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfWhat is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdf
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 

Connecting Quality with Performance Measures

  • 1. Patrick K. Barker Glen B. Alleman MCR, LLC Lewis & Fowler pbarker@mcri.com galleman@lewisandfowler.com (703) – 898–6354 (303) – 241 9633 1/30
  • 2.  Knowing what DONE looks like begins with the Integrated Master Plan.  Recognizing what DONE looks like when it arrives means measuring the planned Technical Performance.  Measuring Physical Percent Complete tells us how far we have moved toward DONE by calculating the “Earned Value” we’ve achieved.  Connecting Earned Value, Technical Performance, and Physical Percent Connect Quality with Performance Complete in the IMP establishes a credible measure of Progress to Plan.  Without these four elements we don’t have a clue to what DONE looks like or if we’ll ever get there as planned. 2/30
  • 3. Evidence of DONE Measures of DONE Beneficial Outcomes IMP The collection of TPM, EV, and The IMP then defines Accomplishment PPC measures defined as “exit the measurable path to Criteria criteria” for the Work Packages the planned maturity. (AC) performing the work. Technical The actual technical Evidence that the Performance performance measured at a product or service is Measure defined date compared to meeting the planned (TPM) planned technical performance. maturity or quality. Evidence of completion Physical Percent Unit of measure to assess the of the planned work in Complete planned technical performance, units meaningful to the (PPC) evidenced by tangible outcomes. customer. Cost and schedule needed to The performance Earned Value deliver the planned technical measured in units of (EV) performance on baseline. dollars. 3/30
  • 4. No Matter How Great and Destructive Your Problems May Seem Now, Remember, You’ve Probably only Seen the Tip of Them 4/30
  • 6. A Technical Performance Measures …  State how well the program is achieving the planned performance requirements at the planned delivery time.  Use actual or predicted values from: – Engineering measurements – Tests – Experiments – Prototypes  For Example: – Response time – Flight range – Power consumption – Static takeoff weight – Product Quality 6/30
  • 7. Document, Baseline, IMS, EVM Parameter  IMP, Functional Baseline Measures Of Effectiveness (MOE)   IMP, WBS, Functional Baseline Measures Of Performance (MOP)   IMP, Allocated Baseline Technical Performance Measure  TPM Milestones And Planned  IMS  Values  Work Packages TPM% Complete Criteria  7/30
  • 8. Physical Percent Complete Requires A Tangible Measure of “Progress to Plan”  Tangible evidentiary materials measure progress to plan.  Pre–defined existence of this evidence in meaningful units of measure established before starting work. No Hand Waving Allowed “Show Me The Money”  Progress is defined in these same units of measure. 8/30
  • 9. IMP Describes how the Major program milestones or assessment events that substantiate system capabilities will be maturity (initial, progress, or final). These milestones or assessment events delivered and Events deliver the specific capabilities for the system on planned dates. how these Milestones capabilities will be recognized Specified result, substantiating a Milestone or Event, that indicates Accomplishment maturity or progress for each product or process Definitive measures substantiating the Accomplishment maturity Criteria level. Completion of specific work that ensures closure of a specified Accomplishment IMS Work activities performed to produce the deliverables that Work Packages and Tasks fulfill the requirements that enable the capabilities Supplemental Schedules 9/30
  • 10. Measure the progress to plan using Physical % Complete at the Accomplishment Criteria (AC) and CWBS level Program Statement of CWBS Events Work Completed SA’s are Work structure Aligned entry criteria for aligned to Program Events SOW Significant Accomplishments Completed Work Aligned Packages are exit Defines Aligned criteria for Tasks Accomplishment CDRLs and Tasks Contained Criteria Aligned Deliverables Aligned in Work Packages Describes increasing Documents the product Work necessary to product maturity as 0/100 or maturity that is aligned with mature products EVMS SD guidance SOW and CWBS grouped by CWBS 10/30
  • 11. 0.0 TOTAL BRILLIANT EYES PROGRAM Planned Profile Tolerance Band 1.0 SPACE BRILLIANT EYES SYSTEM Technical Parameter Value 1.1 System-Level Costs (e.g., Vehicle Weight, lb) 1.2 Space Vehicle (SV) Segment 15 1.2.1 SV Program Level 1.2.2 Space Vehicle Prime Mission Equipment Achieved To Date 1.2.2.1 Space Software 1.2.2.2 Space Vehicle 1.2.2.2.1 1.2.2.2.2 Space Vehicle IA&T Sensor Payload Variation 1.2.2.2.3 1.2.2.2.4 Insertion Vehicle Survivability 10 1.2.3 Prototype Lot 1.2.4 1.2.5 Spare Parts Technology and Producibility Threshold 1.2.6 Aerospace Ground Equipment 5 Planned 1.3 1.2.7 Launch Support Engineering Change Orders (ECOs) Value Current 1.4 1.5 Other Government Costs Risk Estimate A WBS can be displayed as a Milestones “linear” List. Program Cost is often Calculated by summing the Costs of Technical performance measurement have often been All Items on That List … but that treated as an engineering function only, not typically ignores correlation and basic math: linked with EVM, although it shares a common, almost distributions don’t add that way. identical, language structure with EVM. 2 1 6 4 3 5 The Schedule Network is Nonlinear, and Program Duration Cannot be Calculated by Adding Together the Durations of 3 1 6 9 2 4 All Activities in the Network. And since time is money it is important for schedule slips to reflect cost 6 9 2 1 4 2 1 11/30
  • 12.  Neither cost performance nor schedule performance nor technical performance measurement can be fully evaluated by itself. 12/30
  • 13. How to Define DONE  Determine Physical Percent Complete based in performance measurement – Compare actual performance against an integrated baseline planned performance of the integrated cost, schedule and technical goals.  This measurement is possible within a performance measurement system – Use the organization’s internal management control system to provide decision makers with specific performance information about the progress and expenditures against the planed progress and expenditures.  In many projects where EVM systems are implemented, what a CAM determines (“eyeballing”) as physical percent complete often differs from what is reported via the EV techniques. – This disconnect in measurement of “done–ness” is a clear sign that a cost, schedule and/or technical performance problem is going to materialize before the PM can properly react. 13/30
  • 14. Risk Cost IMS PMB SOW WBS TPM 14/30
  • 15. Perform Determine Develop Develop Approve Functional Scope and Technical Technical PMB Analysis Approach Logic Baseline Technical Develop Performance WBS Baseline Estimate Finalize Define Sequence Finalize Time Apportioned Activities Activities Schedule Durations Milestones Schedule Identify Performance Apportioned Milestones Baseline Cost Determine Prepare Resource Determine Resource Cost Load Funding Performance Requirement Estimate Schedule Constraints Baseline 15/30
  • 16. Making Trades Between Cost, Schedule, and Performance Baselines is a Ponzi Scheme When we’re on baseline, the algebraic relationship between C,S,P, means when there is a change everyone loses 16/30
  • 17. A Really Simple Example of Physical Percent Complete  Painting a room is simple example to focused on a notion of percent complete. But how about a flight avionics system?  What are the measures of physical percent complete? ‒ Design basis complete and verified ‒ Hardware platform increasing capabilities ‒ Software system increasing capabilities ‒ Integration and test of 1st flight article ‒ Operational verification and validation complete Where can we look for these measures of physical percent complete? It’s Obvious – in the Integrated Master Plan’s Accomplishment Criteria 17
  • 18. 18/30
  • 19.  The notion of measuring physical percent complete is at the core of every project management method.  It answers the question of what DONE is in units of measure meaningful to the program.  This helps us determine answers to No stretching the truth is allowed once we questions that include, but are not limited start using Technical to: Performance – What does DONE look like for today, for this Measures with week, or for this month? tangible evidence. – What does DONE look like for entry/exit into the technical review? – What does DONE look like for quality control? – What does DONE look like for the customer? 19/30
  • 20.  The increasing maturing of a product or service is described through Events or Milestones, Accomplishments, Criteria, and their Work Packages or Planning Packages. The Structure of a  Each Event or Milestone represents the availability of one or more capabilities. Credible IMP  The presence of these capabilities is measured by the Accomplishments and their Criteria.  Accomplishments are the pre–conditions for the maturity assessment of the product or service at Program Events each Event or Milestone. Define the availability  This hierarchy decomposes the System Capabilities into Requirements, Work Packages, and the of a Capability at a point in activities which produce deliverables. This hierarchy also describes increasing program maturity time. resulting from the activities contained in the Work Packages.  Performance of the work activities, Work Packages, Criteria, Accomplishments, and Events or Milestones is measured in units of “physical percent complete” by connecting Earned Value with Technical Performance Measures. Accomplishments Represent requirements that enable Capabilities. Criteria Represent Work Packages that fulfill Requirements. Work Work Work Each WP must Package Package Package have a measure of Physical Work Percent Work Work Complete Package Package Package Work Work Work package Package Package 20/30
  • 21. 21/30
  • 22. IEEE 1220: 6.8.1.5, EIA–632: Glossary CMMI for Development Performance–based Requirements Development progress measurement TPMs are key to Predict future value of key Specific Practice (SP) 3.3, progressively assess technical parameters of the Analyze Requirements technical progress end system based on Typical work product: current assessments Technical Performance Measures Establish dates for Planned value profile is time– Sub Practice (SP): – Checking progress phased achievement projected Identify TPMs that will be – Meeting full conformance – Achievement to date tracked during development to requirements – Technical milestone where TPM evaluation is reported 22/30
  • 23. 23/30
  • 24. EV TPM What this tells the PM Derived Measurements Number of requirements approved, percentage How well the system is maturing as requirements growth, number TBD/TBR closure per plan, Requirements compared to expectations estimated impact of changes, defect profile, defect density, cycle time for requirements changes System Definition Change If changes are being made in a timely Approval rates, closure rates, cycle times, priority density Backlog manner Number interfaces approved, percent interface growth, Risk associated with interface number TBD/TBR closure per plan, estimated impact of Interface development and maturity interface changes, defect profile, defect density, cycle time for interface changes If requirements are being validated with Requirements validation rate. Requirement Validation applicable stakeholders appropriate to Percent requirements validated the level of requirement. If requirements are being verified Requirements verification rate. Requirement Verification appropriate to the level of requirement. Percent requirements verified Approval rate, distribution of dispositions, approval rate Work Product Approval Work progress and approval efficiency performance Technical/Design Review Progress in closing significant action Closure rates, action item closure performance, variance Action Closure items from technical reviews from thresholds Maturity of key components, Component –Subsystem– Element –System TRL, Technology Technology Maturity subsystems, elements to expectations opportunity exposure, technology obsolescence exposure Effectiveness of the risk management Percentage of risk handling actions closed on time, percent Technical Risk Handling process overdue, percent of risks meeting handling expectations Technical Staffing And Adequacy of technical effort and Technical effort staffing, variance. Skills dynamics of actual staffing mix Efficiency by labor category Current performance status, projections Delta performance (planned versus actual). Technical Performance and associated risk Delta performance to thresholds, objectives 24/30
  • 25. Control Account WP1: Chassis WP2: Array Completion Criteria & Taking “Value” for Work Packages Chassis June July August Sept Current 100 150 200 250 Completion Requirement Design 80% All TPM within Build complete; Criteria Quality (drawings) pre–build All TPM Completed; TPM tolerances via validated by 2, 5 and 6 within refined actual PDR tolerances performance measurement via basic model; TPM 1 performance and 6 verified model via bench testing Cummulative 100 250 450 700 25/30
  • 26. Using Periodic Program Events to Calibrate “Doneness” INPUT PROCESS OUTPUT Program Requirements & Program–level Risk Assessment of the Scope technical baseline Lvl 1 WBS Program Cost & Schedule Estimate Cumulative Distribution Function 1 0.9 IPT–level risks 0.8 0.7 Probability 0.6 0.5 0.4 When it comes right down to it, the (10’s) 0.3 0.2 0.1 0 IBR is all about the technical baseline. IBRs should accompany each major 250000 300000 350000 400000 450000 500000 550000 600000 650000 Total Cost Rollup of quantified process & product risks Date: 3/17/2009 8:35:32 AM Samples: 2000 Unique ID: 114 Name: FIST GEO-1 Completion Std Deviation: 71.23 days 95% Confidence Interval: 3.12 days Each bar represents 25 days baseline evolution. 0.16 0.14 1.0 0.9 Completion Probability Table In the end, the question implicitly Cumulative Probability Prob Date Prob Date 0.8 0.12 0.05 10/21/2010 0.55 3/24/2011 asked of the PM each time is: 0.7 0.10 11/11/2010 0.60 4/7/2011 Frequency 0.10 0.6 0.15 12/2/2010 0.65 4/25/2011 0.08 0.5 0.20 12/20/2010 0.70 5/10/2011 0.4 0.25 1/3/2011 0.75 5/27/2011 0.06 “What is your confidence level in your 0.30 1/14/2011 0.80 6/16/2011 0.04 0.02 0.3 0.2 0.1 0.35 0.40 0.45 1/28/2011 2/9/2011 2/22/2011 0.85 0.90 0.95 7/5/2011 7/26/2011 9/9/2011 CA–level risks 7/6/2010 3/17/2011 Completion Date 3/16/2012 0.50 3/8/2011 1.00 3/16/2012 program’s ability to hit cost, (100’s) IBR Guidance schedule, and scope targets associated with your technical baseline” 26/30
  • 27. Connecting Risk Management with Measures of DONE Risk: CEV-037 - Loss of Critical Functions During Descent 24 Correlate the analytical model 22 Conduct focus splinter review 20 Develop analytical model to de Conduct Force and Moment Wind 18 Conduct Block 1 w ind tunnel te 16 Conduct w ind tunnel testing of Conduct w ind tunnel testing of 14 Flight Application of Spacecra 12 10 CEV block 5 w ind tunnel testin 8 6 4 In-Flight development tests of 2 Damaged TPS flight test 0 3.Jul.06 1.Jul.11 31.Mar.05 5.Oct.05 1.Jun.07 1.Jan.10 16.Dec.10 15.Sep.06 3.Apr.06 1.Apr.08 1.Aug.08 1.Apr.09 Planned Risk Level Planned (Solid=Linked, Hollow =Unlinked, Filled=Complete) Risk Response Milestone Date and Risk ID in traceable between IMS RM Tool and IMS 27/30
  • 28. Risk Cost IMS PMB SOW WBS TPM 28/30
  • 29. A Credible Performance Measurement System Assures the information is available to the decision maker, needed to deliver on‒time, on‒budget, and on‒specification = Technical Performance Measures Cost + Schedule Conventional Earned Value Cost Baseline Technical Performance Schedule Baseline  The Master Schedule  Earned Value is diluted by  Requirements are used to derive Basis of missing technical decomposed into physical Estimate (BOE) not the performance. deliverables. other way around.  Earned Value is diluted by  Deliverables are produced  Probabilistic cost postponed features. through Work Packages. estimating uses past  Earned Value is diluted by  Work Packages are performance and cost risk non compliant quality. assigned to accountable modeling.  All these dilutions require manager.  Labor, Materiel, and other adjustments to the  Work Packages are direct costs accounted for Estimate at Complete sequenced to form the in Work Packages. (EAC) and the To highest value stream with  Risk adjustments for all Complete Performance the lowest technical and elements of cost. Index (TCPI). programmatic risk. 29/30
  • 30. Connecting Measures of Cost, Schedule, and Technical Performance means the difference between … Measuring Actual Physical Percent Complete against the Planned Physical Percent Complete at the time that Physical Percent Complete was planned to be achieved is the foundation of determining a program’s performance. Doing anything else leads to disappointment. 30/30