SlideShare a Scribd company logo
1 of 39
Download to read offline
INTEGRATING RISK WITH
              EARNED VALUE
        PIKES PEAK REGIONAL CHAPTER
  PROJECT MANAGEMENT PRODUCTIVITY TOOLS
                 SYMPOSIUM
        SATURDAY, FEBRUARY 28TH, 2009

                            GLEN B. ALLEMAN
The notion of integrating cost, schedule, technical performance, and risk is
possible in theory. In practice care is needed to assure credible information is
provided to the Program Manager.
Today's Learning Objectives
            Cost, Schedule, Technical
             Performance, and Risk Are
             Inseparable
            All numeric values of cost,
             schedule, technical
             performance, and risk
             assessment are random
             variables drawn from some
             underlying probability
             distribution
            Managing these variables
             must be done through the
             eyes of a Risk Manager        2
There are
  usually two
phases to many
  projects …
1. Too early to tell
2. Too late to stop



                       3
The Fundamental
Program Management Question
               Can we plan with
               sufficient accuracy, to
               allocate resources to
               reduce risk while
               meeting requirements,
               and obtain timely
               feedback in order to
               adjust plans and
               performance goals?


                                         4
Dependencies Between The Inseparable Variables


                                      Cost


  Funding margin for                                      Schedule margin for over
  under performance    Over cost or      Over cost or       target baseline (OTB)
                          under             over
                       performance        schedule




                                 Over schedule
              Technical
             Performance
                                   or under             Schedule
                                  performing



                              Schedule margin for
                              underperformance or
                               schedule extension                                    5
Some Simple Definitions
                        Programmatic and            Technical
  Earned Value
                          Technical Risk           Performance
  Management
                           Management               Measures
Establishes project     Looks to the             A time phased
performance status      unknown future to        progress plan for
and extrapolates        identify risks and       the achievement of
that information to     recommend early          the Technical
understand future       action to be taken       Performance
trends and              to limit the threat or   Parameters (TPP)
allocation of           maximize the             that indicate key
resources needed        exploitation of          areas for risk
to successfully         opportunities            reduction and
meet project                                     program success
milestones
       APM EV-Risk Working Group, 2007            INCOSE G2SEBOK   6
The Integration of Risk and Earned Value is a Systems
Engineering Paradigm

                                              Cost


   Systems Engineering states                                         Integrated Master Schedule &
  deliverables performance and                                          Earned Value Management
         associated risks                                                  tracks risk activities




                   Technical
                  Performance
                                                                 Schedule



                                   Structure WBS contains risk
                                 mitigations and retirement efforts                              7
But Many Times, The Information from Cost,
 Schedule, Techncial Performance, and Risk
Management Systems Gets Mixed Up When We
         Try to Put Them Together




                                          8
Every Program Manager Should Know…
9

       When will this project finish?
       What is the statistical confidence in this date?
       Is the project’s schedule realistic and achievable?
       What will it cost when we are done?
       How is the project performing against its plan?
       What deliverables are slipping?
       How are we going to get the deliverables back on schedule?
       What does past performance say about the future performance?
       What is the impact on the schedule of any change requests?
       Is there enough schedule slack and cost reserve to cover the risk?
       Where is the risk in the schedule?
       How can we get the work done sooner to reduce risk?
       How can we recover from any foreseen delays?
       How can we work around a problem?
The First Step is to Start with Key Elements of
                      Earned Value
10




                    BCWS
                                                 SV
                    BCWP
      CV
                    ACWP
        The Work planned, performed, and the cost of
     performing that work, is the common variable across
                 each Earned Value variable
Some Useful EV Information

               EAC Floor Performance Factor

                                   BAC  BCWPcum    BAC
               EAC  ACWP                       
                                      CPIcum       CPIcum

               EAC Ceiling Performance Factor

                                   BAC  BCWPcum     BAC
               EAC  ACWP                         
                                    CPIcum  SPIcum CPIcum

           EVM Analyst’s EAC Range
           •    Addresses Risk
           •    Based on CPI & SPI trend analysis not on
                plugging numbers into a formula
           •    Incorporates technical performance, schedule
                progress, CAIV and other program information




          http://www.daytonaero.com/Files/resource/31.pdf
                                                               11
ANSI 748B Says on Page 1
12


      Plan all work scope for the program to completion.
      Integrate program work scope, schedule, and cost
       objectives into a baseline plan against which
       accomplishments may be measured.
      Objectively assess accomplishments at the work
       performance level.
      Analyze significant variances from the plan and
       forecast impacts.
      Provide data to higher levels for management
       decision making and implementation of
       management actions.
Some Criteria for Successful EVMS
                      Beyond Full Compliance of the 32 Criteria




                       Identify the
   Define a Work                           Integrate WBS and     Schedule all   Indentify Products
                      Organizations
Breakdown Structure                          OBS into a RAM     Planned Work      and Milestones
                      doing the work
  Time Phase the      Record all Direct      Determine all       Sum These       Manage Action
     Budget                Costs              Variances          Variances          Plans
13                                        Incorporate Changes
At The Same Time, Risk Management is
        Commonly Misunderstood
 It’s not about random chance, it’s about defining
mitigations and retirement plans in the presence of
                     uncertainty




                                                      14
Five Fundamental Principles of Risk Management




1. Hope is not a strategy
2. No single point estimate of cost or schedule can be correct
3. Cost, Schedule, and Technical Performance are inseparable
4. Risk management requires adherence to a well defined process
5. Communication is the Number One success factor            15
DoD’s Approach to Successful Risk Management
16
But ANSI 748B Also Says …
17


      Identify physical products, milestones, technical
       performance goals, or other indicators that will be
       used to measure progress.
      So why the disconnect between Risk and Earned
       Value?

        Isn’t the measure of risk, the rate of risk reduction
         an “…other indicators…”
Revisions & Change Control


 Define and    Establish MR                      Authorize Work
Organize the   Issue Budget     Establish PMB       Measure         Analyze Results
   Work        Authorize Plan                     Performance




  Integrating                                                I think you
Earned Value                                                 should be more
    and Risk                                                 explicit about
Management                                                   the steps here.




 Plan Risk     Perform Risk      Develop Risk       Assign           Monitor and
 Activities    Assessment       Handling Plans   Responsibilities   Communicate


                                    Update Risk Register                         18
SOME ACTIONABLE DETAILS FOR
PUTTING THESE FOUR CONCEPTS
TOGETHER
In Theory there is no difference between Theory and Practice.
In Practice there is — Yogi Berra
The Difference Between
Technical and Programmatic
            Risk
 There are two types of “uncertainty” on any
  sufficiently complex program
  – Technical – uncertainty about the functional and
    performance aspects of the program’s
    technology that impacts the produceability of
    the product or creates delays in the schedule
  – Programmatic – uncertainty about the duration
    and cost of the activities that deliver the        So much for our strategy of winning
    functional and performance elements of the            through technical dominance
    program, independent of the technical risk
 We’re interested in connecting the two in the schedule and cost
  model(s)
  – When the technical uncertainty arises what is the impact on the schedule
    and cost?
  – When the schedule or cost uncertainty arises what is the impact on the
    functional and performance aspects?                                                  20
Deterministic Versus
                   Probabilistic
           Deterministic                            Probabilistic

• Each activity has a planned value      • The program elements are not
• For the schedule each task has a         random, but they are random
  predecessor and a successor.             variables drawn from a probability
• The longest path through the             distribution.
  network is the critical path           • Three point estimates "can" be
• The total duration of the project is     used to describe task duration
  a fixed value - it is deterministic      random variables
• The total cost is the sum of all the   • The total duration of the project is
  activity costs                           a random number
• Risks are defined and handled as       • The total cost is a random number
  static entities                        • Risks are stochastic processes
                                           that have probabilistic outcomes
                                           for cost, schedule and technical
                                           performance

                                                                                  21
Without these Principles The Program Train Wreck Starts When…
 Inattention to             Lack of predictive
  budgetary                   variance analysis
  responsibilities           Untimely and unrealistic
 Work authorizations         Latest Revised Estimates
  that are not always         (LRE)
  followed                   Progress not monitored
 Issues with Budget and      in a regular and
  data reconciliation         consistent manner
 Lack of an integrated      Lack of vertical and
  management system           horizontal traceability
 Baseline fluctuations       cost and schedule data
  and frequent replanning     for corrective action
 Current period and         Lack of internal
  retroactive changes         surveillance and
 Improper use of             controls
  management reserve         Managerial actions not     Mary K. Evans Picture Library


 EV techniques that do       demonstrated using
  not reflect actual          Earned Value
                                                                                         22
  performance
AN INTRODUCTION TO SOFTWARE
ENGINEERING INSTITUTE’S
CONTINUOUS RISK MANAGEMENT
(CRM)
CRM is the Software Engineering Institute’s framework for managing risk in the
context of system integration, COTS based product development, and the
management of these activities.
Continuous Risk Management has Six Components




            http://www.sei.cmu.edu/risk/index.html
                                                     24
Putting Continuous Risk Management Work
25



     CRM Activity Project Representation
                     Risk items with IMP/IMS #’s, CA/WP & resource
          Identify
                     assignments
          Analyze Risk management responsibilities assigned
                  Mitigation plans with durations and resource
             Plan
                  assignments
            Track Status reported from Risk Management to IMS
          Control Risk tasks reporting in weekly status process
                     Integrated Master Schedule (IMS) status reporting
     Communicate
                     as Physical Percent Complete
This All Comes Together in The Risk Registry
26




 http://www.mitre.org/work/sepo/toolkits/risk/ToolsTechniques/RiskMatrix.html
PHYSICALLY CONNECTING
EARNED VALUE WITH RISK
MANAGEMENT
Some Historical Background†
28


      Cost and schedule growth have been persistent
       problems for decades
      The use of Earned Value is common in DoD
       environments
      As is the use of Risk Management

      It’s the integration that is missing




     † “Integrating Risk Management with Earned Value Management,” NDIA
       Report, www.ndia.org
The Core Problems Before We Start
29


      Earned Value is a measure of quantity not quality
      Risk measures the probability of an unfavorable
       occurrence but rarely monetizes this outcome
      Risk management focuses on dealing with future
       events
      Earned Value focuses on reporting past
       performance
Starting with the Individual Elements
30

                     Identify          Analyze              Plan                Track              Control
                                      Risk board       Mitigation and
                   Identify risk                                           Connect PMB         Vet members of
Organization                         assessment of       retirement
                     owners                                               with Risk registry    the leadership
                                        impact             owners

                      Identify        Probability     PMB contains all                              Transfer
 Planning &                                                               Baseline the risk
                  uncertainty and      impact in        risk active                            mitigation to PMB
 Budgeting                                                                    registry
                     response          schedule          activities                              and close risk

                   Assign risk to                       Risk budgets        Risk Board         Transfer through
                                       Probability
 Accounting        CA/WP cost                           defined and       management of           EV change
                                     impact on cost
                     baseline                            allocated         cost impacts        control processes

                                                         Risk registry
                  Asses impacts                                           Risk Board and       Manage budget
                                                           contains
     Analysis         and                                                    IMS Board          assignment by
                                                       probabilities of
                  dependencies                                            impact analysis          risk level
                                                      cost and schedule

                                                       Updated PMB
                  Keep historical   Update ETC from                                               Revise PMB
     Revisions                                           from risk           Risk review
                     records        risk management                                                forecast
                                                         activities
First, A (Notional) Big Picture
31


                      Risk ID Traceable to
                      work elements in the
                      IMS within the WBS




     Risk reduction                        Standard program
     waterfall metrics                   performance of TCPI
     connected to Earned                           and IEAC
     Value program
     performance
One Approach to Integrating Risk Management with
                        Earned Value
32                                                    Control
                                               Integrate across
                                                functions
          Program Manager                      Reprioritize
                                               Authorize project
                              Top N risks       resources            Decisions

                                                       Control      Assign
        Functional Managers                      Integrate
                                                 Reprioritize
                                                                    Responsibility
                                                 Authorize
                         Top N risks             Functional area
                                                  resources


     Work Package Managers         Analyze                                   Plan
                                Review                               Approve plans
                                Prioritize                                                  EV Data

                                                                      Recommend actions
                                Evaluate                             Develop plans
                                Classify
           Individuals/Team                                                                              1
                   Members risks
                                                           Risk Status
                   EV Data         Identify                                 Track          EV Data
                                                  Trends
                                                                          Required
                              3                                          Indicators                  2
EXAMPLE SCHEDULE RISK
ANALYSIS
Monte Carlo tools model the task durations with random variables for the
durations and build “pictures” of the likelihood of a task completely on or
before a specific date.
@Risk and Risk+ Sample Screens




                                 34
Schedule for a Monte Carlo Risk analysis starts with a
credible schedule and defines the probabilistic behavior
  of each activities and how it drives the deliverables




                                                                               35
    The Risk+ tool sets the upper and lower bounds of the possible durations
The output of Risk+ is a Probability Distribution Function and a
Cumulative Distribution of all the possible dates that “watched”
                       activity could take.
The result is a picture of the Confidence that the target date of
                      2/10/3 – can be met.
               It shows 40% – which is not good

               Date: 2/25/2009 3:34:12 PM                                         Completion Std Deviation: 5.51d
               Samples: 300                                                       95% Confidence Interval: 0.62d
               Unique ID: 30                                                      Each bar represents 2d
               Name: Final Testing
                0.16                                                        1.0           Completion Probability Table
                                                                            0.9
                0.14
                         Cumulative Probability




                                                                                  Prob   Date              Prob     Date
                                                                            0.8
                0.12                                                              0.05   Wed 1/29/03       0.55     Wed 2/12/03
                                                                            0.7   0.10   Fri 1/31/03       0.60     Thu 2/13/03
   Frequency




                0.10                                                        0.6   0.15   Tue 2/4/03        0.65     Fri 2/14/03
                0.08                                                        0.5   0.20   Wed 2/5/03        0.70     Fri 2/14/03
                                                                            0.4   0.25   Wed 2/5/03        0.75     Mon 2/17/03
                0.06
                                                                            0.3   0.30   Thu 2/6/03        0.80     Tue 2/18/03
                0.04                                                              0.35   Fri 2/7/03        0.85     Wed 2/19/03
                                                                            0.2
                0.02
                                                                                  0.40   Mon 2/10/03       0.90     Thu 2/20/03
                                                                            0.1   0.45   Mon 2/10/03       0.95     Tue 2/25/03
                 Mon 1/20/03                          Tue 2/11/03   Mon 3/3/03
                                                                                  0.50   Tue 2/11/03       1.00     Mon 3/3/03
                                                  Completion Date                                                                 36
So with this information we can ask …
37


      What cost impact will there be?
      What resource impacts?

      What technical dependencies?

      What mitigation or retirement plans must be in
       place to increase the probability of success to
       something greater than 40%?
      What other interdependencies are there in the
       program?
Program Management is Risky Business
 Traditional Approaches Are Seriously Flawed
 Risk Management Is Not About Preventing Risk
 Risk Management Is About Managing In The Presence Of
  Risk
 This means managing Cost, Schedule, and Technical
  Performance




                                                         38
Source Materials
39

        Interfacing Risk & Earned Value: Management Reserve,
        “Technical Performance Measurement, Earned Value, and Risk Management: An Integrated
         Diagnostic Tool for Program Management,” Commander N. D. Pisano, SC, USN, Program
         Executive Office for Air ASW, Assault, and Special Mission Programs (PEO(A))
        Practical Risk Management: The ATOM Method, David Hillson and Peter Simon, Management
         Concepts.
        Project Risk Analysis and Management Guide, APM Publishing.
        “Formal Risk Management,” DACS Gold Practices
        “Quantify Risk to Manage Cost and Schedule,” Fred Raymond, Acquisition Review Quarterly,
         Spring 1999, pp. 147–154
        Probabilistic Risk Assessment Procedures Guide for NASA Managers and Practitioners, Office of
         Safety and Mission Assurance, April 2002
        Development Of Risk Management Defense Extensions To The PMI Project Management Body
         Of Knowledge – Tutorial,” Edmund Conrow, Acquisition Review Quarterly, Spring, 2003.
        Effective Risk management: Some Keys to Success, Edmund Conrow, American Institute of
         Aeronautics and Astronautics, 2000.

More Related Content

What's hot

Metrics-Based Process Mapping
Metrics-Based Process MappingMetrics-Based Process Mapping
Metrics-Based Process MappingTKMG, Inc.
 
different techniques to productivity improvement
different techniques to productivity improvementdifferent techniques to productivity improvement
different techniques to productivity improvementHemant Patil
 
Kaizen PDCA Cycle Process PowerPoint Presentation Slides
Kaizen PDCA Cycle Process PowerPoint Presentation Slides Kaizen PDCA Cycle Process PowerPoint Presentation Slides
Kaizen PDCA Cycle Process PowerPoint Presentation Slides SlideTeam
 
SMED - Single Minute Exchange Died
SMED - Single Minute Exchange DiedSMED - Single Minute Exchange Died
SMED - Single Minute Exchange DiedFigliolino Venanzio
 
Productivity measurement approaches
Productivity measurement approachesProductivity measurement approaches
Productivity measurement approachesAmit Verma
 
SMED - Single Minute Exchange of Dies
SMED - Single Minute Exchange of DiesSMED - Single Minute Exchange of Dies
SMED - Single Minute Exchange of Dies5S BALAMURUGAN
 
New 7 QC Tools Module 3 | Tree diagram
New 7 QC Tools Module 3 | Tree diagramNew 7 QC Tools Module 3 | Tree diagram
New 7 QC Tools Module 3 | Tree diagramShakehand with Life
 
8 Lean Wastes PowerPoint Presentation Slides
8 Lean Wastes PowerPoint Presentation Slides 8 Lean Wastes PowerPoint Presentation Slides
8 Lean Wastes PowerPoint Presentation Slides SlideTeam
 
Jeu lean manufacturing
Jeu lean manufacturingJeu lean manufacturing
Jeu lean manufacturingCIPE
 
PID Controllers
PID Controllers PID Controllers
PID Controllers Hussain K
 
Chapter 4 software project planning
Chapter 4 software project planningChapter 4 software project planning
Chapter 4 software project planningdespicable me
 
jeu dispersion 6 sigma
jeu dispersion 6 sigmajeu dispersion 6 sigma
jeu dispersion 6 sigmaCIPE
 

What's hot (20)

Metrics-Based Process Mapping
Metrics-Based Process MappingMetrics-Based Process Mapping
Metrics-Based Process Mapping
 
Value Stream Mapping in the Office
Value Stream Mapping in the Office Value Stream Mapping in the Office
Value Stream Mapping in the Office
 
different techniques to productivity improvement
different techniques to productivity improvementdifferent techniques to productivity improvement
different techniques to productivity improvement
 
Kaizen PDCA Cycle Process PowerPoint Presentation Slides
Kaizen PDCA Cycle Process PowerPoint Presentation Slides Kaizen PDCA Cycle Process PowerPoint Presentation Slides
Kaizen PDCA Cycle Process PowerPoint Presentation Slides
 
Kaizen (Continual Improvement)
Kaizen (Continual Improvement)Kaizen (Continual Improvement)
Kaizen (Continual Improvement)
 
SMED - Single Minute Exchange Died
SMED - Single Minute Exchange DiedSMED - Single Minute Exchange Died
SMED - Single Minute Exchange Died
 
Productivity measurement approaches
Productivity measurement approachesProductivity measurement approaches
Productivity measurement approaches
 
SMED - Single Minute Exchange of Dies
SMED - Single Minute Exchange of DiesSMED - Single Minute Exchange of Dies
SMED - Single Minute Exchange of Dies
 
New 7 QC Tools Module 3 | Tree diagram
New 7 QC Tools Module 3 | Tree diagramNew 7 QC Tools Module 3 | Tree diagram
New 7 QC Tools Module 3 | Tree diagram
 
Smed smpl 1
Smed smpl 1Smed smpl 1
Smed smpl 1
 
Poka yoke
Poka yokePoka yoke
Poka yoke
 
8 Lean Wastes PowerPoint Presentation Slides
8 Lean Wastes PowerPoint Presentation Slides 8 Lean Wastes PowerPoint Presentation Slides
8 Lean Wastes PowerPoint Presentation Slides
 
Oee and its Application
Oee and its ApplicationOee and its Application
Oee and its Application
 
Six sigma-black-belt-project-sample
Six sigma-black-belt-project-sampleSix sigma-black-belt-project-sample
Six sigma-black-belt-project-sample
 
Jeu lean manufacturing
Jeu lean manufacturingJeu lean manufacturing
Jeu lean manufacturing
 
PID Controllers
PID Controllers PID Controllers
PID Controllers
 
Chapter 4 software project planning
Chapter 4 software project planningChapter 4 software project planning
Chapter 4 software project planning
 
jeu dispersion 6 sigma
jeu dispersion 6 sigmajeu dispersion 6 sigma
jeu dispersion 6 sigma
 
Kaizen
KaizenKaizen
Kaizen
 
The Lean Game
The Lean GameThe Lean Game
The Lean Game
 

Viewers also liked

Schedule variance = 0 and we’re a year late
Schedule variance = 0 and we’re a year lateSchedule variance = 0 and we’re a year late
Schedule variance = 0 and we’re a year lateGlen Alleman
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value AnalysisSaqib Raza
 
Earned value analysis training
Earned value analysis trainingEarned value analysis training
Earned value analysis trainingPaul King
 
Earned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examEarned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examManish Purwar
 
Earned value
Earned valueEarned value
Earned valueOliver
 
Earned value in five easy pieces
Earned value in five easy piecesEarned value in five easy pieces
Earned value in five easy piecesGlen Alleman
 
Présentation Evm V00.7
Présentation Evm V00.7Présentation Evm V00.7
Présentation Evm V00.7sbrigand
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)Ejaz Bhatti
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementBaroness PM
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value ManagementMansoor Shoaib
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlM Maged Hegazy, LLM, MBA, CCP, P3O
 
Earned Value Reporting
Earned Value ReportingEarned Value Reporting
Earned Value Reportingcfreema7
 
Successfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueSuccessfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueGlen Alleman
 
Earned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPEarned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPJustAcademy
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)Glen Alleman
 

Viewers also liked (20)

Schedule variance = 0 and we’re a year late
Schedule variance = 0 and we’re a year lateSchedule variance = 0 and we’re a year late
Schedule variance = 0 and we’re a year late
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Earned value analysis training
Earned value analysis trainingEarned value analysis training
Earned value analysis training
 
Earned Value
Earned ValueEarned Value
Earned Value
 
Earned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examEarned value for pmp and pmi acp exam
Earned value for pmp and pmi acp exam
 
Earned value
Earned valueEarned value
Earned value
 
Earned value in five easy pieces
Earned value in five easy piecesEarned value in five easy pieces
Earned value in five easy pieces
 
Earned Value fundamentals
Earned Value fundamentalsEarned Value fundamentals
Earned Value fundamentals
 
Présentation Evm V00.7
Présentation Evm V00.7Présentation Evm V00.7
Présentation Evm V00.7
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
 
Earned Value Reporting
Earned Value ReportingEarned Value Reporting
Earned Value Reporting
 
Successfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueSuccessfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned Value
 
Earned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPEarned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMP
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 

Similar to Integrating Risk and Earned Value Management

Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value ManagementGlen Alleman
 
Cpm500 d _alleman__tpm lesson 3 (v1)
Cpm500 d _alleman__tpm lesson 3 (v1)Cpm500 d _alleman__tpm lesson 3 (v1)
Cpm500 d _alleman__tpm lesson 3 (v1)Glen Alleman
 
Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Glen Alleman
 
You don’t need agile to avoid the seven deadly sins of pm
You don’t need agile to avoid the seven deadly sins of pmYou don’t need agile to avoid the seven deadly sins of pm
You don’t need agile to avoid the seven deadly sins of pmGlen Alleman
 
Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)Glen Alleman
 
From WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleFrom WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleGlen Alleman
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbookGlen Alleman
 
Assessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPIAssessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPIGlen Alleman
 
Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeffNASAPMC
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and AgileGlen Alleman
 
Integrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementIntegrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementGlen Alleman
 
Build an integrated master plan and integrated master
Build an integrated master plan and integrated masterBuild an integrated master plan and integrated master
Build an integrated master plan and integrated masterGlen Alleman
 
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...Glen Alleman
 
Building risk tolerance
Building risk toleranceBuilding risk tolerance
Building risk toleranceGlen Alleman
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.garyNASAPMC
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.garyNASAPMC
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Building A Credible Measurement Baseline
Building A Credible Measurement BaselineBuilding A Credible Measurement Baseline
Building A Credible Measurement BaselineGlen Alleman
 

Similar to Integrating Risk and Earned Value Management (20)

Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
 
Cpm500 d _alleman__tpm lesson 3 (v1)
Cpm500 d _alleman__tpm lesson 3 (v1)Cpm500 d _alleman__tpm lesson 3 (v1)
Cpm500 d _alleman__tpm lesson 3 (v1)
 
Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®
 
You don’t need agile to avoid the seven deadly sins of pm
You don’t need agile to avoid the seven deadly sins of pmYou don’t need agile to avoid the seven deadly sins of pm
You don’t need agile to avoid the seven deadly sins of pm
 
Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)
 
From WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleFrom WBS to Integrated Master Schedule
From WBS to Integrated Master Schedule
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbook
 
Assessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPIAssessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPI
 
Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeff
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and Agile
 
Integrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementIntegrating Agile and Earned Value Management
Integrating Agile and Earned Value Management
 
DPPM1
DPPM1DPPM1
DPPM1
 
Build an integrated master plan and integrated master
Build an integrated master plan and integrated masterBuild an integrated master plan and integrated master
Build an integrated master plan and integrated master
 
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
 
Building risk tolerance
Building risk toleranceBuilding risk tolerance
Building risk tolerance
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Building A Credible Measurement Baseline
Building A Credible Measurement BaselineBuilding A Credible Measurement Baseline
Building A Credible Measurement Baseline
 

More from Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management TheoryGlen Alleman
 

More from Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
 

Recently uploaded

Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity PlanDatabarracks
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxLoriGlavin3
 
A Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersA Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersNicole Novielli
 
Generative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersGenerative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersRaghuram Pandurangan
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Mark Simos
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxhariprasad279825
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Manik S Magar
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rick Flair
 
Advanced Computer Architecture – An Introduction
Advanced Computer Architecture – An IntroductionAdvanced Computer Architecture – An Introduction
Advanced Computer Architecture – An IntroductionDilum Bandara
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxLoriGlavin3
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfAddepto
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024Lorenzo Miniero
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 3652toLead Limited
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embeddingZilliz
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfLoriGlavin3
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 

Recently uploaded (20)

Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity Plan
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptx
 
A Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersA Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software Developers
 
Generative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersGenerative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information Developers
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptx
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...
 
Advanced Computer Architecture – An Introduction
Advanced Computer Architecture – An IntroductionAdvanced Computer Architecture – An Introduction
Advanced Computer Architecture – An Introduction
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdf
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embedding
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdf
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 

Integrating Risk and Earned Value Management

  • 1. INTEGRATING RISK WITH EARNED VALUE PIKES PEAK REGIONAL CHAPTER PROJECT MANAGEMENT PRODUCTIVITY TOOLS SYMPOSIUM SATURDAY, FEBRUARY 28TH, 2009 GLEN B. ALLEMAN The notion of integrating cost, schedule, technical performance, and risk is possible in theory. In practice care is needed to assure credible information is provided to the Program Manager.
  • 2. Today's Learning Objectives  Cost, Schedule, Technical Performance, and Risk Are Inseparable  All numeric values of cost, schedule, technical performance, and risk assessment are random variables drawn from some underlying probability distribution  Managing these variables must be done through the eyes of a Risk Manager 2
  • 3. There are usually two phases to many projects … 1. Too early to tell 2. Too late to stop 3
  • 4. The Fundamental Program Management Question Can we plan with sufficient accuracy, to allocate resources to reduce risk while meeting requirements, and obtain timely feedback in order to adjust plans and performance goals? 4
  • 5. Dependencies Between The Inseparable Variables Cost Funding margin for Schedule margin for over under performance Over cost or Over cost or target baseline (OTB) under over performance schedule Over schedule Technical Performance or under Schedule performing Schedule margin for underperformance or schedule extension 5
  • 6. Some Simple Definitions Programmatic and Technical Earned Value Technical Risk Performance Management Management Measures Establishes project Looks to the A time phased performance status unknown future to progress plan for and extrapolates identify risks and the achievement of that information to recommend early the Technical understand future action to be taken Performance trends and to limit the threat or Parameters (TPP) allocation of maximize the that indicate key resources needed exploitation of areas for risk to successfully opportunities reduction and meet project program success milestones APM EV-Risk Working Group, 2007 INCOSE G2SEBOK 6
  • 7. The Integration of Risk and Earned Value is a Systems Engineering Paradigm Cost Systems Engineering states Integrated Master Schedule & deliverables performance and Earned Value Management associated risks tracks risk activities Technical Performance Schedule Structure WBS contains risk mitigations and retirement efforts 7
  • 8. But Many Times, The Information from Cost, Schedule, Techncial Performance, and Risk Management Systems Gets Mixed Up When We Try to Put Them Together 8
  • 9. Every Program Manager Should Know… 9  When will this project finish?  What is the statistical confidence in this date?  Is the project’s schedule realistic and achievable?  What will it cost when we are done?  How is the project performing against its plan?  What deliverables are slipping?  How are we going to get the deliverables back on schedule?  What does past performance say about the future performance?  What is the impact on the schedule of any change requests?  Is there enough schedule slack and cost reserve to cover the risk?  Where is the risk in the schedule?  How can we get the work done sooner to reduce risk?  How can we recover from any foreseen delays?  How can we work around a problem?
  • 10. The First Step is to Start with Key Elements of Earned Value 10 BCWS SV BCWP CV ACWP The Work planned, performed, and the cost of performing that work, is the common variable across each Earned Value variable
  • 11. Some Useful EV Information EAC Floor Performance Factor BAC  BCWPcum BAC EAC  ACWP   CPIcum CPIcum EAC Ceiling Performance Factor BAC  BCWPcum BAC EAC  ACWP   CPIcum  SPIcum CPIcum EVM Analyst’s EAC Range • Addresses Risk • Based on CPI & SPI trend analysis not on plugging numbers into a formula • Incorporates technical performance, schedule progress, CAIV and other program information http://www.daytonaero.com/Files/resource/31.pdf 11
  • 12. ANSI 748B Says on Page 1 12  Plan all work scope for the program to completion.  Integrate program work scope, schedule, and cost objectives into a baseline plan against which accomplishments may be measured.  Objectively assess accomplishments at the work performance level.  Analyze significant variances from the plan and forecast impacts.  Provide data to higher levels for management decision making and implementation of management actions.
  • 13. Some Criteria for Successful EVMS Beyond Full Compliance of the 32 Criteria Identify the Define a Work Integrate WBS and Schedule all Indentify Products Organizations Breakdown Structure OBS into a RAM Planned Work and Milestones doing the work Time Phase the Record all Direct Determine all Sum These Manage Action Budget Costs Variances Variances Plans 13 Incorporate Changes
  • 14. At The Same Time, Risk Management is Commonly Misunderstood It’s not about random chance, it’s about defining mitigations and retirement plans in the presence of uncertainty 14
  • 15. Five Fundamental Principles of Risk Management 1. Hope is not a strategy 2. No single point estimate of cost or schedule can be correct 3. Cost, Schedule, and Technical Performance are inseparable 4. Risk management requires adherence to a well defined process 5. Communication is the Number One success factor 15
  • 16. DoD’s Approach to Successful Risk Management 16
  • 17. But ANSI 748B Also Says … 17  Identify physical products, milestones, technical performance goals, or other indicators that will be used to measure progress.  So why the disconnect between Risk and Earned Value?  Isn’t the measure of risk, the rate of risk reduction an “…other indicators…”
  • 18. Revisions & Change Control Define and Establish MR Authorize Work Organize the Issue Budget Establish PMB Measure Analyze Results Work Authorize Plan Performance Integrating I think you Earned Value should be more and Risk explicit about Management the steps here. Plan Risk Perform Risk Develop Risk Assign Monitor and Activities Assessment Handling Plans Responsibilities Communicate Update Risk Register 18
  • 19. SOME ACTIONABLE DETAILS FOR PUTTING THESE FOUR CONCEPTS TOGETHER In Theory there is no difference between Theory and Practice. In Practice there is — Yogi Berra
  • 20. The Difference Between Technical and Programmatic Risk  There are two types of “uncertainty” on any sufficiently complex program – Technical – uncertainty about the functional and performance aspects of the program’s technology that impacts the produceability of the product or creates delays in the schedule – Programmatic – uncertainty about the duration and cost of the activities that deliver the So much for our strategy of winning functional and performance elements of the through technical dominance program, independent of the technical risk  We’re interested in connecting the two in the schedule and cost model(s) – When the technical uncertainty arises what is the impact on the schedule and cost? – When the schedule or cost uncertainty arises what is the impact on the functional and performance aspects? 20
  • 21. Deterministic Versus Probabilistic Deterministic Probabilistic • Each activity has a planned value • The program elements are not • For the schedule each task has a random, but they are random predecessor and a successor. variables drawn from a probability • The longest path through the distribution. network is the critical path • Three point estimates "can" be • The total duration of the project is used to describe task duration a fixed value - it is deterministic random variables • The total cost is the sum of all the • The total duration of the project is activity costs a random number • Risks are defined and handled as • The total cost is a random number static entities • Risks are stochastic processes that have probabilistic outcomes for cost, schedule and technical performance 21
  • 22. Without these Principles The Program Train Wreck Starts When…  Inattention to  Lack of predictive budgetary variance analysis responsibilities  Untimely and unrealistic  Work authorizations Latest Revised Estimates that are not always (LRE) followed  Progress not monitored  Issues with Budget and in a regular and data reconciliation consistent manner  Lack of an integrated  Lack of vertical and management system horizontal traceability  Baseline fluctuations cost and schedule data and frequent replanning for corrective action  Current period and  Lack of internal retroactive changes surveillance and  Improper use of controls management reserve  Managerial actions not Mary K. Evans Picture Library  EV techniques that do demonstrated using not reflect actual Earned Value 22 performance
  • 23. AN INTRODUCTION TO SOFTWARE ENGINEERING INSTITUTE’S CONTINUOUS RISK MANAGEMENT (CRM) CRM is the Software Engineering Institute’s framework for managing risk in the context of system integration, COTS based product development, and the management of these activities.
  • 24. Continuous Risk Management has Six Components http://www.sei.cmu.edu/risk/index.html 24
  • 25. Putting Continuous Risk Management Work 25 CRM Activity Project Representation Risk items with IMP/IMS #’s, CA/WP & resource Identify assignments Analyze Risk management responsibilities assigned Mitigation plans with durations and resource Plan assignments Track Status reported from Risk Management to IMS Control Risk tasks reporting in weekly status process Integrated Master Schedule (IMS) status reporting Communicate as Physical Percent Complete
  • 26. This All Comes Together in The Risk Registry 26 http://www.mitre.org/work/sepo/toolkits/risk/ToolsTechniques/RiskMatrix.html
  • 27. PHYSICALLY CONNECTING EARNED VALUE WITH RISK MANAGEMENT
  • 28. Some Historical Background† 28  Cost and schedule growth have been persistent problems for decades  The use of Earned Value is common in DoD environments  As is the use of Risk Management  It’s the integration that is missing † “Integrating Risk Management with Earned Value Management,” NDIA Report, www.ndia.org
  • 29. The Core Problems Before We Start 29  Earned Value is a measure of quantity not quality  Risk measures the probability of an unfavorable occurrence but rarely monetizes this outcome  Risk management focuses on dealing with future events  Earned Value focuses on reporting past performance
  • 30. Starting with the Individual Elements 30 Identify Analyze Plan Track Control Risk board Mitigation and Identify risk Connect PMB Vet members of Organization assessment of retirement owners with Risk registry the leadership impact owners Identify Probability PMB contains all Transfer Planning & Baseline the risk uncertainty and impact in risk active mitigation to PMB Budgeting registry response schedule activities and close risk Assign risk to Risk budgets Risk Board Transfer through Probability Accounting CA/WP cost defined and management of EV change impact on cost baseline allocated cost impacts control processes Risk registry Asses impacts Risk Board and Manage budget contains Analysis and IMS Board assignment by probabilities of dependencies impact analysis risk level cost and schedule Updated PMB Keep historical Update ETC from Revise PMB Revisions from risk Risk review records risk management forecast activities
  • 31. First, A (Notional) Big Picture 31 Risk ID Traceable to work elements in the IMS within the WBS Risk reduction Standard program waterfall metrics performance of TCPI connected to Earned and IEAC Value program performance
  • 32. One Approach to Integrating Risk Management with Earned Value 32 Control  Integrate across functions Program Manager  Reprioritize  Authorize project Top N risks resources Decisions Control Assign Functional Managers  Integrate  Reprioritize Responsibility  Authorize Top N risks  Functional area resources Work Package Managers Analyze Plan  Review  Approve plans  Prioritize EV Data  Recommend actions  Evaluate  Develop plans  Classify Individuals/Team 1 Members risks Risk Status EV Data Identify Track EV Data Trends Required 3 Indicators 2
  • 33. EXAMPLE SCHEDULE RISK ANALYSIS Monte Carlo tools model the task durations with random variables for the durations and build “pictures” of the likelihood of a task completely on or before a specific date.
  • 34. @Risk and Risk+ Sample Screens 34
  • 35. Schedule for a Monte Carlo Risk analysis starts with a credible schedule and defines the probabilistic behavior of each activities and how it drives the deliverables 35 The Risk+ tool sets the upper and lower bounds of the possible durations
  • 36. The output of Risk+ is a Probability Distribution Function and a Cumulative Distribution of all the possible dates that “watched” activity could take. The result is a picture of the Confidence that the target date of 2/10/3 – can be met. It shows 40% – which is not good Date: 2/25/2009 3:34:12 PM Completion Std Deviation: 5.51d Samples: 300 95% Confidence Interval: 0.62d Unique ID: 30 Each bar represents 2d Name: Final Testing 0.16 1.0 Completion Probability Table 0.9 0.14 Cumulative Probability Prob Date Prob Date 0.8 0.12 0.05 Wed 1/29/03 0.55 Wed 2/12/03 0.7 0.10 Fri 1/31/03 0.60 Thu 2/13/03 Frequency 0.10 0.6 0.15 Tue 2/4/03 0.65 Fri 2/14/03 0.08 0.5 0.20 Wed 2/5/03 0.70 Fri 2/14/03 0.4 0.25 Wed 2/5/03 0.75 Mon 2/17/03 0.06 0.3 0.30 Thu 2/6/03 0.80 Tue 2/18/03 0.04 0.35 Fri 2/7/03 0.85 Wed 2/19/03 0.2 0.02 0.40 Mon 2/10/03 0.90 Thu 2/20/03 0.1 0.45 Mon 2/10/03 0.95 Tue 2/25/03 Mon 1/20/03 Tue 2/11/03 Mon 3/3/03 0.50 Tue 2/11/03 1.00 Mon 3/3/03 Completion Date 36
  • 37. So with this information we can ask … 37  What cost impact will there be?  What resource impacts?  What technical dependencies?  What mitigation or retirement plans must be in place to increase the probability of success to something greater than 40%?  What other interdependencies are there in the program?
  • 38. Program Management is Risky Business  Traditional Approaches Are Seriously Flawed  Risk Management Is Not About Preventing Risk  Risk Management Is About Managing In The Presence Of Risk  This means managing Cost, Schedule, and Technical Performance 38
  • 39. Source Materials 39  Interfacing Risk & Earned Value: Management Reserve,  “Technical Performance Measurement, Earned Value, and Risk Management: An Integrated Diagnostic Tool for Program Management,” Commander N. D. Pisano, SC, USN, Program Executive Office for Air ASW, Assault, and Special Mission Programs (PEO(A))  Practical Risk Management: The ATOM Method, David Hillson and Peter Simon, Management Concepts.  Project Risk Analysis and Management Guide, APM Publishing.  “Formal Risk Management,” DACS Gold Practices  “Quantify Risk to Manage Cost and Schedule,” Fred Raymond, Acquisition Review Quarterly, Spring 1999, pp. 147–154  Probabilistic Risk Assessment Procedures Guide for NASA Managers and Practitioners, Office of Safety and Mission Assurance, April 2002  Development Of Risk Management Defense Extensions To The PMI Project Management Body Of Knowledge – Tutorial,” Edmund Conrow, Acquisition Review Quarterly, Spring, 2003.  Effective Risk management: Some Keys to Success, Edmund Conrow, American Institute of Aeronautics and Astronautics, 2000.