Integrating Risk With Earned Value V5

Loading...

Flash Player 9 (or above) is needed to view presentations.
We have detected that you do not have it on your computer. To install it, go here.

0 comments

Post a comment

    Post a comment
    Embed Video
    Edit your comment Cancel

    3 Favorites

    Integrating Risk With Earned Value V5 - Presentation Transcript

    1. Integrating Risk with Earned Value Pikes Peak Regional Chapter Project Management Productivity Tools Symposium Saturday, February 28th, 2009 Glen B. Alleman VP, Program Planning and Controls Lewis & Fowler www.lewisandfowler.com The notion of integrating cost, schedule, technical performance, and risk is possible in theory. In practice care is needed to assure credible information is provided to the Program Manager. 1
    2. Today's Learning Objectives  Cost, Schedule, Technical Performance, and Risk Are Inseparable  All numeric values of cost, schedule, technical performance, and risk assessment are random variables drawn from some underlying probability distribution  Managing these variables must be done through the eyes of a Risk Manager 2
    3. There are usually two phases to many projects … 1. Too early to tell 2. Too late to stop 3
    4. Dependencies Between The Inseparable Variables Cost Funding margin for Schedule margin for over under performance target baseline (OTB) Over cost or Over cost or over under schedule performance Over schedule Technical Schedule or under Performance performing Schedule margin for underperformance or schedule extension 4
    5. But Many Times, The Information from Cost, Schedule, Techncial Performance, and Risk Management Systems Gets Mixed Up When We Try to Put Them Together 5
    6. Some Useful EV Information EAC Floor Performance Factor BAC B C W Pcum BAC EAC ACW P C P Icum C P Icum EAC Ceiling Performance Factor BAC B C W Pcum BAC EAC ACW P C P Icum S P Icum C P Icum EVM Analyst’s EAC Range • Addresses Risk • Based on CPI & SPI trend analysis not on plugging numbers into a formula • Incorporates technical performance, schedule progress, CAIV and other program information http://www.daytonaero.com/Files/resource/31.pdf 6
    7. Some Criteria for Successful EVMS Beyond Full Compliance of the 32 Criteria Define a Work Identify the Integrate WBS Schedule all Indentify Products Breakdown Organizations and OBS into a Planned Work and Milestones Structure doing the work RAM Time Phase the Record all Direct Determine all Sum These Manage Action Budget Costs Variances Variances Plans 7 Incorporate Changes
    8. At The Same Time, Risk Management is Commonly Misunderstood It’s not about random chance, it’s about defining mitigations and retirement plans in the presence of uncertainty 8
    9. Five Fundamental Principles of Risk Management 1. Hope is not a strategy 2. No single point estimate of cost or schedule can be correct 3. Cost, Schedule, and Technical Performance are inseparable 4. Risk management requires adherence to a well defined process 5. Communication is the Number One success factor 9
    10. Revisions & Change Control Define and Establish MR Authorize Work Organize the Issue Budget Establish PMB Measure Analyze Results Work Authorize Plan Performance Integrating I think you Earned Value should be more and Risk explicit about Management the steps here. Plan Risk Perform Risk Develop Risk Assign Monitor and Activities Assessment Handling Plans Responsibilities Communicate Update Risk Register 10
    11. Some Actionable Details For Putting These Four Concepts Together In Theory there is no difference between Theory and Practice. In Practice there is — Yogi Berra 11
    12. The Difference Between Technical and Programmatic Risk  There are two types of ―uncertainty‖ on any sufficiently complex program – Technical – uncertainty about the functional and performance aspects of the program’s technology that impacts the produceability of the product or creates delays in the schedule – Programmatic – uncertainty about the duration and cost of the activities that deliver the So much for our strategy of winning through technical dominance functional and performance elements of the program, independent of the technical risk  We’re interested in connecting the two in the schedule and cost model(s) – When the technical uncertainty arises what is the impact on the schedule and cost? – When the schedule or cost uncertainty arises what is the impact on the functional and performance aspects? 12
    13. Deterministic Versus Probabilistic Deterministic Probabilistic  Each activity has a planned value  The program elements are not random, but they are random  For the schedule each task has a variables drawn from a probability predecessor and a successor. distribution.  The longest path through the  Three point estimates \"can\" be network is the critical path used to describe task duration  The total duration of the project is random variables a fixed value - it is deterministic  The total duration of the project is  The total cost is the sum of all the a random number activity costs  The total cost is a random number  Risks are defined and handled as  Risks are stochastic processes static entities that have probabilistic outcomes for cost, schedule and technical performance 13
    14. Without these Principles The Program Train Wreck Starts When…  Inattention to  Lack of predictive budgetary variance analysis  Untimely and unrealistic responsibilities  Work authorizations Latest Revised Estimates that are not always (LRE)  Progress not monitored followed  Issues with Budget and in a regular and data reconciliation consistent manner  Lack of an integrated  Lack of vertical and management system horizontal traceability  Baseline fluctuations cost and schedule data and frequent replanning for corrective action  Current period and  Lack of internal retroactive changes surveillance and  Improper use of controls  Managerial actions not management reserve Mary K. Evans Picture Library  EV techniques that do demonstrated using not reflect actual Earned Value 14 performance
    15. Continuous Risk Management has Six Components http://www.sei.cmu.edu/risk/index.html 15
    16. This All Comes Together in The Risk Registry http://www.mitre.org/work/sepo/toolkits/risk/ToolsTechniques/RiskMatrix.html 16
    17. First, A (Notional) Big Picture Risk ID Traceable to IMS work elements in the IMS within the WBS Containing Risk Database the Risk Activities Risk reduction Standard program waterfall metrics performance of TCPI connected to Earned and IEAC Value program performance Program Performance Metrics no·tion·al 1. Of, containing, or being a notion; mental or imaginary. 17 2. Speculative or theoretical
    18. Modeling Schedule Risk Cost, Schedule, Technical Model†  Research the Project  Find Analogies  Ask Endless Questions Days, Facilities,  Analyze the Results Parts and People WBS  What can go wrong? Probability Density Function  How likely is it to go wrong? Task 100  What is the cause?  What is the consequence? Task 101 Task 102 Monte Carlo Simulation Task 103 Tool is Mandatory Task 104 Cumulative Distribution Function 1.0 .8 Task 105 .6 .4 Task 106 .2 0 † This is a Key concept. This is the part of the process that Days, Facilities, Parts, People integrates the cost and schedule risk impacts to provide the basis of a credible schedule. 18
    19. Modeling Cost Risk Combined Cost Modeling and Technical Uncertainty Cost = a + bXc Cost Modeling Uncertainty Cost Estimate Historical data point $ Cost estimating relationship Standard percent error bounds Technical Uncertainty Cost Driver (Weight) 19
    20. Modeling Technical Performance Measures 20
    21. One Approach to Integrating Risk Management with Earned Value Control  Integrate across functions Program Manager  Reprioritize  Authorize project Top N risks resources Decisions Assign Control  Functional Managers Integrate Responsibility  Reprioritize  Authorize Top N risks  Functional area resources Work Package Managers Analyze Plan  Review  Approve plans  Prioritize EV Data  Recommend actions  Evaluate  Develop plans  Classify 1 Individuals/Team Members risks Risk Status EV Data EV Data Identify Track Trends Required Indicators 2 3 21
    22. Example Schedule Risk Analysis Monte Carlo tools model the task durations with random variables for the durations and build ―pictures‖ of the likelihood of a task completely on or before a specific date. 22 Deliverables Based Planning Handbook for A&D, Copyright © 2008, 2009, Lewis & Fowler
    23. @Risk and Risk+ Sample Screens 23
    24. Schedule for a Monte Carlo Risk analysis starts with a credible schedule and defines the probabilistic behavior of each activities and how it drives the deliverables 24 The Risk+ tool sets the upper and lower bounds of the possible durations
    25. The output of Risk+ is a Probability Distribution Function and a Cumulative Distribution of all the possible dates that ―watched‖ activity could take. The result is a picture of the Confidence that the target date of 2/10/3 – can be met. It shows 40% – which is not good Date: 2/25/2009 3:34:12 PM Completion Std Deviation: 5.51d Samples: 300 95% Confidence Interval: 0.62d Unique ID: 30 Each bar represents 2d Name: Final Testing 0.16 1.0 Completion Probability Table 0.9 0.14 Cumulative Probability Prob Date Prob Date 0.8 0.05 Wed 1/29/03 0.55 Wed 2/12/03 0.12 0.7 0.10 Fri 1/31/03 0.60 Thu 2/13/03 Frequency 0.10 0.6 0.15 Tue 2/4/03 0.65 Fri 2/14/03 0.20 Wed 2/5/03 0.70 Fri 2/14/03 0.5 0.08 0.25 Wed 2/5/03 0.75 Mon 2/17/03 0.4 0.06 0.30 Thu 2/6/03 0.80 Tue 2/18/03 0.3 0.35 Fri 2/7/03 0.85 Wed 2/19/03 0.04 0.2 0.40 Mon 2/10/03 0.90 Thu 2/20/03 0.02 0.1 0.45 Mon 2/10/03 0.95 Tue 2/25/03 0.50 Tue 2/11/03 1.00 Mon 3/3/03 Mon 1/20/03 Tue 2/11/03 Mon 3/3/03 Completion Date 25
    26. So with this information we can ask …  What cost impact will there be?  What resource impacts?  What technical dependencies?  What mitigation or retirement plans must be in place to increase the probability of success to something greater than 40%?  What other interdependencies are there in the program? 26
    27. Program Management is Risky Business  Traditional Approaches Are Seriously Flawed  Risk Management Is Not About Preventing Risk  Risk Management Is About Managing In The Presence Of Risk  This means managing Cost, Schedule, and Technical Performance 27
    28. Source Materials  Interfacing Risk & Earned Value: Management Reserve,  ―Technical Performance Measurement, Earned Value, and Risk Management: An Integrated Diagnostic Tool for Program Management,‖ Commander N. D. Pisano, SC, USN, Program Executive Office for Air ASW, Assault, and Special Mission Programs (PEO(A))  Practical Risk Management: The ATOM Method, David Hillson and Peter Simon, Management Concepts.  Project Risk Analysis and Management Guide, APM Publishing.  ―Formal Risk Management,‖ DACS Gold Practices  ―Quantify Risk to Manage Cost and Schedule,‖ Fred Raymond, Acquisition Review Quarterly, Spring 1999, pp. 147–154  Probabilistic Risk Assessment Procedures Guide for NASA Managers and Practitioners, Office of Safety and Mission Assurance, April 2002  Development Of Risk Management Defense Extensions To The PMI Project Management Body Of Knowledge – Tutorial,‖ Edmund Conrow, Acquisition Review Quarterly, Spring, 2003.  Effective Risk management: Some Keys to Success, Edmund Conrow, American Institute of Aeronautics and Astronautics, 2000. 28
    29. 29
    SlideShare Zeitgeist 2009

    + Glen AllemanGlen Alleman Nominate

    custom

    914 views, 3 favs, 0 embeds more stats

    Coonecting risk with earned value management presen more

    More info about this document

    © All Rights Reserved

    Go to text version

    • Total Views 914
      • 914 on SlideShare
      • 0 from embeds
    • Comments 0
    • Favorites 3
    • Downloads 0
    Most viewed embeds

    more

    All embeds

    less

    Flagged as inappropriate Flag as inappropriate
    Flag as inappropriate

    Select your reason for flagging this presentation as inappropriate. If needed, use the feedback form to let us know more details.

    Cancel
    File a copyright complaint
    Having problems? Go to our helpdesk?

    Categories