Project Management 4
Module 3: Develop schedules for project management
Module 3; Develop schedules for project management
After completing this module, you will be able to:
demonstrate an understanding of the purpose and process of scheduling project activities
define and gather information about project activities from technical (subject matter) experts and within own field of expertise
develop a simple schedule for a project or part thereof
1. DEMONSTRATE AND UNDERSTANDING OF THE PROCESS AND PURPOSE OF SCHEDULING PROJECT ACTIVITIES
After completing this outcome, you will be able to:
explain the purpose and importance of a schedule of activities on a project
explain the development process of a schedule in accordance with industry practices
differentiate between completing a project within the shortest possible time, and at specified due date
explain the use of a work breakdown structure in the development of a schedule
1.1 Explain the purpose and importance of a schedule of activities on a project
Normalising the schedule:
You must review the schedule to determine whether the resources you assigned are actually available within each task’s schedule window
Start with the activities on the critical path and work the rest of the schedule from there
Move things around based on the float available to ensure that you don’t overload someone and that others are fully utilised
1.1 Explain the purpose and importance of a schedule of activities on a project
Three strategies to normalise the schedule:
Schedule all non-critical tasks at the earliest date possible
Schedule all non-critical tasks as late as possible
Schedule a subset of non-critical tasks
1.1 Explain the purpose and importance of a schedule of activities on a project
Loading up and levelling up:
Some members will likely be overloaded and others may not have enough work
Scheduled work should be redistributed from those who have too much work to those not fully booked – this is called levelling out
1.1 Explain the purpose and importance of a schedule of activities on a project
International and local professional bodies linked to project management practice and standards
PMBOK
APM BOK
PMI
APMA and AIPM
1.2 Differentiate between completing a project within the shortest possible time and at specified due dates
Project managers can do the following to shorten the time:
Overlapping of activities
Crashing
Work overtime or 24 hour shifts
1.3 Explain the use of a Work Breakdown Structure in the development of a schedule
The purpose of a WBS is to subdivide the scope of the work into manageable packages
In a WBS a project is broken down into the following levels or parts:
The total project
Sub-projects
Milestones
Major activities
Work packages
1.3 Explain the use of a Work Breakdown Structure in the development of a schedule
The answers a project manager got from a well organised WBS refer to:
How long (time duration) will it take to complete the activity?
What skill(s) are required to perform the activity?
What is the estimates cost (cost will be finalised at a later stage) to complete/perform the activity?
The resources required to do the work – machinery, raw material and other equipment
Does the work on the activity depend on the completion of any other activities?
1.3 Explain the use of a Work Breakdown Structure in the development of a schedule
The WBS should be able to help you do the following:
Identify the major parts of the project so that all the work needing to be done is clearly indicated
Organise the work in the most logical sequence so the work packages can be efficiently scheduled
Identify work packages that need to be assigned to various team members
Identify the resources necessary to complete each work package so a budget can be developed
Communicate the work to be done in a unambiguous way so that team members understand their assigned jobs and responsibilities for completing the project
Organise related work packages using logical milestones
1.3 Explain the use of a Work Breakdown Structure in the development of a schedule
Four steps to the work breakdown structure
Break the work into independent work packages that can be sequenced, assigned, scheduled and monitored
Define the work packages at a level of detail appropriate for the length and complexity of the project
Integrate the work packages in a format that can be easily communicated to people assigned to complete them during the project
Verify that completion of the work packages will result in attainment of all the project goals and objectives
1.3 Explain the use of a Work Breakdown Structure in the development of a schedule
Work packages – what are they?
Each work package represents the lowest level of project activity that has both time and cost associated with it
Work packages are useful in the following ways:
They are a way of modularising the project into manageable segments
By breaking work into work packages, you can determine the skills you need to complete the work on a project, and you can quantify how many people will be required to do the work
They allow you to communicate the work that needs to be done to other team members without getting into too much detail
Breaking the work into work packages ensures that all the work sequences are identified and understood
DEFINE AND GATHER INFORMATION ABOUT PROJECT ACTIVITIES FROM TECHNICAL EXPERTS AND WITHIN OWN FIELD OF EXPERTISE
After completing this outcome, you will be able to:
identify activities for the identified project
prioritise activities within scope of project
identify and explain the use of documents required for identified activities
explain the need for documents to reflect activities at a level of detail to support further planning activities
2.1 Identify activities for the identified project
WBS for house project
1.1 Civil
1.1.1 Lay foundations
1.1.2 Walls and roof
1.2 Plumbing
1.2.1 Piping
1.2.2 Sewerage
1.3 Electrical
1.3.1 Wiring
1.3.2 Appliances
1.4 Security wall and gates
1.5 Landscaping
1.5.1 Garden outlay, trees and shrubs
1.5.2 Irrigation system
2.2 Prioritise activities within the scope of project
2.2 Prioritise activities within the scope of project
2.3 Identify and explain the use of documents required for identified activities
Work Breakdown Structure
Task list
Risk Plan
Quality plan
3. DEVELOP A SIMPLE SCHEDULE FOR A PROJECT OR PART THEREOF
After completing this outcome, you will be able to:
develop a simple schedule for the identified project to reflect the following components
WBS as a horizontal presentation House project Civil Plumbing Security wall and gates Electrical Landscaping Foundations Walls and roof Piping Sewerage Wiring Appliances Garden outlay Water irrigation system
WBS as an organogram illustration House project Civil work Plumbing work Electrical work Security walls and gates Landscaping Foundations Walls and roof Piping Sewerage Wiring Appliances Garden outlay Water irrigation
House project R84 000 Civil work 1.1 R44 000 Plumbing work 1.2 R8 000 Electrical work 1.3 R11 000 Security walls and gates 1.4 R12 000 Landscaping 1.5 R9 000 Foundations 1.1.1 R15 000 Walls and roof 1.1.2 R29 000 Piping 1.2.1 R6000 Sewerage 1.2.2 R2 000 Wiring 1.3.1 R3 000 Appliances 1.3.2 R8 000 Garden outlay 1.5.1 R3 000 Water irrigation 1.5.2 R6 000
Definition of an activity
An activity may be defined as any task, job or operation that must be performed to complete the work packages or project
Activities in series
Activities in parallel
Characteristics of an activity
An activity must have a unique activity code or number (A or 1 or 100, 200, etc). The code may be alpha, numeric or alpha-numeric
An activity must have a description
There will be logical relationships between the activities
All activities will have a time duration for completing the task, even if it is zero
All activities will have a calendar or work pattern to indicate when the work can be scheduled, even it is seven days a week
The activity can have target start and finish dates assigned. Certainly a starting date or finishing date for the project is required
An activity may need items to be procured, by linking the procurement to the activity a procurement schedule can be produced
An activity may need resources, by linking the resources to the activity they can be scheduled to produce a resource histogram
An activity will incur expenses. If these costs are linked to the activities the costs can be scheduled and rolled-up to produce a cash-flow statement and plan expenditure curves.
If a WBS is used, the activities can be linked to the work packages. This will enable the costs to be entered at the activity level and roll-up to be reported at a higher level
Example of an activity
Activity box
Network diagram
What is a network diagram?
The network diagram shows the path of the project, lists starting and completion dates, and names the responsible party for each task.
Networks are usually drawn from left to right with times drawn between activities to indicate the procedure among activities in the project
If properly sequenced, a network diagram will:
Show the sequence and relationships among activities necessary to complete a project
Identify relationships among milestones in the project that can be used for monitoring progress and completion
Show the interrelationships of activities in different parts of the work breakdown structure (WBS) hierarchy
Establish a vehicle for scheduling activities
Help reduce uncertainty in the project by breaking it into many small phases that have been analysed and sequenced in advance of starting the work
5 Steps to create a network diagram
List the activities using the WBS
Establish the interrelationships between activities
Identify the milestones that you want to specify
Lay out the activities and milestones as a network
Review the logic of the network
Are the activities properly sequenced?
Is all necessary precedence identified?
Is there any precedence that isn’t really required?
Are all of the activities really necessary?
Are any activities missing?
Does the completion of the activities in the network represent the accomplishment of everything necessary to meet the project goals that have been specified?
Network diagram of our project
Notes
Project manager and project team works 7 days a week (including Saturdays and Sundays)
Project team also work on public holidays.
The early start time (EST) of a new project is always 0-hours/days or months into the project
In our project the plumbing and electrical work will take place at the same time – simultaneously
This slide show complements the Learner Guide NCV 4 more
This slide show complements the Learner Guide NCV 4 Project Management Hands-On Training by Bert Eksteen, published by Future Managers. For more information visit our website www.futuremanagers.net less