EU rep5 project(support to the energy sector in 5 pacific island states)<br />
EU REP5 Project<br />Project overview<br /><ul><li>Initiative supported by Pacific Islands Forum Secretariat (PIFS)
Focused on renewable energy and demand-side energy efficiency activities
Funded by the 9th European Development Fund (EDF9)
Total Fund : 12.38 M€
Upcoming SlideShare
Loading in...5
×

EU REP5 Project

629

Published on

Published in: News & Politics
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
629
On Slideshare
0
From Embeds
0
Number of Embeds
0
Actions
Shares
0
Downloads
5
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

EU REP5 Project

  1. 1. EU rep5 project(support to the energy sector in 5 pacific island states)<br />
  2. 2. EU REP5 Project<br />Project overview<br /><ul><li>Initiative supported by Pacific Islands Forum Secretariat (PIFS)
  3. 3. Focused on renewable energy and demand-side energy efficiency activities
  4. 4. Funded by the 9th European Development Fund (EDF9)
  5. 5. Total Fund : 12.38 M€
  6. 6. Five island nations participated:
  7. 7. RMI and FSM (four states): focused on outer islands
  8. 8. Palau, Nauru and Niue: overall efficiency improvement
  9. 9. Four year project started in January, 2006
  10. 10. Project completion delayed into May, 2010
  11. 11. Programme Management Unit (PMU) to oversee overall projects
  12. 12. Main office in Suva and sub-office in Pohnpei</li></li></ul><li>Projects in FSM<br /><ul><li>Total 173kWp PV systems installed
  13. 13. Off-grid solar PV (121kWp) installed in 11 outer islands (Yap, Chuuk, and Pohnpei)
  14. 14. 5 grid-connected solar PV (52kWp) installed in Kosrae
  15. 15. Energy efficiency awareness improved
  16. 16. PV system training implemented
  17. 17. Energy efficiency awareness campaign carried out
  18. 18. Energy policy and action plans development underway
  19. 19. Project Hand-over and O&M delayed
  20. 20. Installation completed but final acceptance delayed to mid-2010
  21. 21. O&M contract scheme yet to be agreed</li></ul>EU REP5 Project<br />
  22. 22. Project Details in FSM<br />EU REP5 Project<br />Total FSM: 173.4 kWp<br />
  23. 23. High Priority Follow-up actions<br />Completion of building wiring for PV installations in Chuuk<br />Safety/performance inspection for all PV installations in Chuuk<br />Contractual arrangement on O&M and fee-payment for outer-island PV systems in Pohnpei<br />Hand-over of PV systems from Federal to State government<br />Replacement of faulty inverter – Kosrae Airport<br />Inspection and final acceptance of PV systems by KUA – due in October, 2010<br />Confirmation of solar lantern shipment<br />Hiring a consultant to assist for completion of energy policy and action plans<br />Start of implementation of coordinated energy efficiency actions<br />Self-sustained/professional training programs for inverters and controllers <br />EU REP5 Project<br />