SlideShare a Scribd company logo
1 of 2
Status
• Phase 1
• Punchlist – VDOT, WMATA, and Fairfax County
• Ongoing
• Fairfax County 274 items, 81 closed
• Project Closeout
• Ongoing
• Contingency Remaining - $12.8M
• Not all claims finalized
• Wiehle Garage – 85% parking utilization
• Phase 2
• Design Build Status
• Overall Project – 14%
• Design – 69%
• Construction – 1%
• Highlights
• Aerial guideway under construction
• 60 drilled shafts installed
• 42 columns installed
• 26 caps installed
• Enabling work on Innovation Center Station
began
• Enabling work on Herndon and Reston
Town Center 1st and 2nd quarter 2015
• 1,300 linear feet of existing utilities
relocated
County Activities
• Phase 2 Design Reviews
• County Coordination
• Town of Herndon
• Adjacent Land Owners
• Project Partners (MWAA, VDOT, DRPT, WMATA,
Loudoun County)
• Fairfax Connector
• Phase 1 Close Out and Punchlist
• Coordination with MWAA and adjacent land owners on
land use applications (SE, 2232)
1
January 20, 2015
County Activities
• Herndon & Innovation Center Station garages - DPWES lead for design/construction
• Innovation Center Station Garage ($57M)
• Rezoning was approved July 2014
• Schematic Design Received January 2015 – under review
• Design development to be completed in March 2015 and start of
construction expected March 2016
• Gordon and HGA Architects have been selected as part of the project
team
• Herndon Garage ($58.7M)
• 2232 application was approved June 2014
• Schematic Design Received January 2015 – under review
• Design development to be completed in March 2015 and start of
construction expected March 2016
• Gordon and HGA Architects have been selected as part of the project
team
• TIFIA
• Fairfax County Closed a $ 403.3M TIFIA Loan
• 2nd lowest interest rate in the history of the TIFIA loan program -
2.73%
• Only Maryland received a lower rate for the Inter-county
Connector in 2009 – 2.56%
• Fairfax County earned the lowest rate among the Silver Line funding
partners
• MWAA - $1.3B loan at 3.21%
• Loudoun County - $195M at 2.87%
• Loan will cover about 45% of the county’s total estimated cost of
$915M
2
January 20, 2015

More Related Content

What's hot

Transportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumTransportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumFairfax County
 
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadPublic Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadFairfax County
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...Fairfax County
 
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...Fairfax County
 
Reston Network Analysis: Community Meeting Tier 1 & Tier 2
Reston Network Analysis: Community Meeting Tier 1 & Tier 2Reston Network Analysis: Community Meeting Tier 1 & Tier 2
Reston Network Analysis: Community Meeting Tier 1 & Tier 2Fairfax County
 
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...Fairfax County
 
Fairfax County Capital Bikeshare
Fairfax County Capital BikeshareFairfax County Capital Bikeshare
Fairfax County Capital BikeshareFairfax County
 
Reston Transportation Funding Plan: Community Meeting June 27, 2016
Reston Transportation Funding Plan: Community Meeting June 27, 2016Reston Transportation Funding Plan: Community Meeting June 27, 2016
Reston Transportation Funding Plan: Community Meeting June 27, 2016Fairfax County
 
Fairfax County Countywide Transit Network Study: Sept. 17, 2013
Fairfax County Countywide Transit Network Study: Sept. 17, 2013Fairfax County Countywide Transit Network Study: Sept. 17, 2013
Fairfax County Countywide Transit Network Study: Sept. 17, 2013Fairfax County
 
Continuation of Countywide Dialogue on Transportation
Continuation of Countywide Dialogue on TransportationContinuation of Countywide Dialogue on Transportation
Continuation of Countywide Dialogue on TransportationFairfax County
 
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...Fairfax County
 
Reston Network Analysis: Mid-Buildout Results and Roadway Classifications- Ap...
Reston Network Analysis: Mid-Buildout Results and Roadway Classifications- Ap...Reston Network Analysis: Mid-Buildout Results and Roadway Classifications- Ap...
Reston Network Analysis: Mid-Buildout Results and Roadway Classifications- Ap...Fairfax County
 
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield District
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield DistrictProposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield District
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield DistrictFairfax County
 
Fairfax County and the NVTA TransAction Update
Fairfax County and the NVTA TransAction UpdateFairfax County and the NVTA TransAction Update
Fairfax County and the NVTA TransAction UpdateFairfax County
 
Richmond Highway Transit Center Feasibility Study: Public Information Meeting
Richmond Highway Transit Center Feasibility Study: Public Information MeetingRichmond Highway Transit Center Feasibility Study: Public Information Meeting
Richmond Highway Transit Center Feasibility Study: Public Information MeetingFairfax County
 
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next StepsVDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next StepsFairfax County
 
I-66 Beltway to Haymarket - VDOT
 I-66 Beltway to Haymarket - VDOT I-66 Beltway to Haymarket - VDOT
I-66 Beltway to Haymarket - VDOTFairfax County
 
Little River Turnpike Bicycle Corridor Study: Public Meeting #2: Sept. 26, 2016
Little River Turnpike Bicycle Corridor Study: Public Meeting #2: Sept. 26, 2016Little River Turnpike Bicycle Corridor Study: Public Meeting #2: Sept. 26, 2016
Little River Turnpike Bicycle Corridor Study: Public Meeting #2: Sept. 26, 2016Fairfax County
 
Snow Removal on Sidewalks
Snow Removal on SidewalksSnow Removal on Sidewalks
Snow Removal on SidewalksFairfax County
 
I-66 Multimodal Improvements Inside the Beltway
I-66 Multimodal Improvements Inside the BeltwayI-66 Multimodal Improvements Inside the Beltway
I-66 Multimodal Improvements Inside the BeltwayFairfax County
 

What's hot (20)

Transportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumTransportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
 
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadPublic Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
 
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
 
Reston Network Analysis: Community Meeting Tier 1 & Tier 2
Reston Network Analysis: Community Meeting Tier 1 & Tier 2Reston Network Analysis: Community Meeting Tier 1 & Tier 2
Reston Network Analysis: Community Meeting Tier 1 & Tier 2
 
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...
 
Fairfax County Capital Bikeshare
Fairfax County Capital BikeshareFairfax County Capital Bikeshare
Fairfax County Capital Bikeshare
 
Reston Transportation Funding Plan: Community Meeting June 27, 2016
Reston Transportation Funding Plan: Community Meeting June 27, 2016Reston Transportation Funding Plan: Community Meeting June 27, 2016
Reston Transportation Funding Plan: Community Meeting June 27, 2016
 
Fairfax County Countywide Transit Network Study: Sept. 17, 2013
Fairfax County Countywide Transit Network Study: Sept. 17, 2013Fairfax County Countywide Transit Network Study: Sept. 17, 2013
Fairfax County Countywide Transit Network Study: Sept. 17, 2013
 
Continuation of Countywide Dialogue on Transportation
Continuation of Countywide Dialogue on TransportationContinuation of Countywide Dialogue on Transportation
Continuation of Countywide Dialogue on Transportation
 
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
 
Reston Network Analysis: Mid-Buildout Results and Roadway Classifications- Ap...
Reston Network Analysis: Mid-Buildout Results and Roadway Classifications- Ap...Reston Network Analysis: Mid-Buildout Results and Roadway Classifications- Ap...
Reston Network Analysis: Mid-Buildout Results and Roadway Classifications- Ap...
 
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield District
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield DistrictProposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield District
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield District
 
Fairfax County and the NVTA TransAction Update
Fairfax County and the NVTA TransAction UpdateFairfax County and the NVTA TransAction Update
Fairfax County and the NVTA TransAction Update
 
Richmond Highway Transit Center Feasibility Study: Public Information Meeting
Richmond Highway Transit Center Feasibility Study: Public Information MeetingRichmond Highway Transit Center Feasibility Study: Public Information Meeting
Richmond Highway Transit Center Feasibility Study: Public Information Meeting
 
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next StepsVDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps
 
I-66 Beltway to Haymarket - VDOT
 I-66 Beltway to Haymarket - VDOT I-66 Beltway to Haymarket - VDOT
I-66 Beltway to Haymarket - VDOT
 
Little River Turnpike Bicycle Corridor Study: Public Meeting #2: Sept. 26, 2016
Little River Turnpike Bicycle Corridor Study: Public Meeting #2: Sept. 26, 2016Little River Turnpike Bicycle Corridor Study: Public Meeting #2: Sept. 26, 2016
Little River Turnpike Bicycle Corridor Study: Public Meeting #2: Sept. 26, 2016
 
Snow Removal on Sidewalks
Snow Removal on SidewalksSnow Removal on Sidewalks
Snow Removal on Sidewalks
 
I-66 Multimodal Improvements Inside the Beltway
I-66 Multimodal Improvements Inside the BeltwayI-66 Multimodal Improvements Inside the Beltway
I-66 Multimodal Improvements Inside the Beltway
 

Viewers also liked

Metrorail SafeTrack Overview and Mitigation
Metrorail SafeTrack Overview and MitigationMetrorail SafeTrack Overview and Mitigation
Metrorail SafeTrack Overview and MitigationFairfax County
 
Board Transportation Committee Update: March 17, 2015
Board Transportation Committee Update: March 17, 2015Board Transportation Committee Update: March 17, 2015
Board Transportation Committee Update: March 17, 2015Fairfax County
 
Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Fairfax County
 
Fairfax Connector Silver Line Bus Service
Fairfax Connector Silver Line Bus ServiceFairfax Connector Silver Line Bus Service
Fairfax Connector Silver Line Bus ServiceFairfax County
 
Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013Fairfax County
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Fairfax County
 
Mobile Food Vending within VDOT Right-of-Way: Board Transportation Committee ...
Mobile Food Vending within VDOT Right-of-Way: Board Transportation Committee ...Mobile Food Vending within VDOT Right-of-Way: Board Transportation Committee ...
Mobile Food Vending within VDOT Right-of-Way: Board Transportation Committee ...Fairfax County
 
Requirements for Pedestrian Improvements on Road Projects in the Board's Six ...
Requirements for Pedestrian Improvements on Road Projects in the Board's Six ...Requirements for Pedestrian Improvements on Road Projects in the Board's Six ...
Requirements for Pedestrian Improvements on Road Projects in the Board's Six ...Fairfax County
 
Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013Fairfax County
 
Student Free Fare Program Update and Recommendations: Board Transportation Co...
Student Free Fare Program Update and Recommendations: Board Transportation Co...Student Free Fare Program Update and Recommendations: Board Transportation Co...
Student Free Fare Program Update and Recommendations: Board Transportation Co...Fairfax County
 
Fairfax County and the NVTA TransAction Update
Fairfax County and the NVTA TransAction UpdateFairfax County and the NVTA TransAction Update
Fairfax County and the NVTA TransAction UpdateFairfax County
 
Board of Supervisors Transportation Committee: Proposed High Quality Transit ...
Board of Supervisors Transportation Committee: Proposed High Quality Transit ...Board of Supervisors Transportation Committee: Proposed High Quality Transit ...
Board of Supervisors Transportation Committee: Proposed High Quality Transit ...Fairfax County
 
Dulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and FundingDulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and FundingFairfax County
 
Fairfax Commercial and Industrial Property Tax for Transportation
Fairfax Commercial and Industrial Property Tax for TransportationFairfax Commercial and Industrial Property Tax for Transportation
Fairfax Commercial and Industrial Property Tax for TransportationFairfax County
 
Transform 66 Outside the Beltway: Multimodal Solutions- 495 to Haymarket
Transform 66 Outside the Beltway: Multimodal Solutions- 495 to HaymarketTransform 66 Outside the Beltway: Multimodal Solutions- 495 to Haymarket
Transform 66 Outside the Beltway: Multimodal Solutions- 495 to HaymarketFairfax County
 
Herndon Metrorail Stations Access Management Study (HMSAMS)
Herndon Metrorail Stations Access Management Study (HMSAMS)Herndon Metrorail Stations Access Management Study (HMSAMS)
Herndon Metrorail Stations Access Management Study (HMSAMS)Fairfax County
 
Update on Route 1 Multimodal Alternatives Analysis
Update on Route 1 Multimodal Alternatives AnalysisUpdate on Route 1 Multimodal Alternatives Analysis
Update on Route 1 Multimodal Alternatives AnalysisFairfax County
 
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Fairfax County
 
Fairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor StudyFairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor StudyFairfax County
 
Board of Supervisors Transportation Committee: Next Steps for Urban Street St...
Board of Supervisors Transportation Committee: Next Steps for Urban Street St...Board of Supervisors Transportation Committee: Next Steps for Urban Street St...
Board of Supervisors Transportation Committee: Next Steps for Urban Street St...Fairfax County
 

Viewers also liked (20)

Metrorail SafeTrack Overview and Mitigation
Metrorail SafeTrack Overview and MitigationMetrorail SafeTrack Overview and Mitigation
Metrorail SafeTrack Overview and Mitigation
 
Board Transportation Committee Update: March 17, 2015
Board Transportation Committee Update: March 17, 2015Board Transportation Committee Update: March 17, 2015
Board Transportation Committee Update: March 17, 2015
 
Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016
 
Fairfax Connector Silver Line Bus Service
Fairfax Connector Silver Line Bus ServiceFairfax Connector Silver Line Bus Service
Fairfax Connector Silver Line Bus Service
 
Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
 
Mobile Food Vending within VDOT Right-of-Way: Board Transportation Committee ...
Mobile Food Vending within VDOT Right-of-Way: Board Transportation Committee ...Mobile Food Vending within VDOT Right-of-Way: Board Transportation Committee ...
Mobile Food Vending within VDOT Right-of-Way: Board Transportation Committee ...
 
Requirements for Pedestrian Improvements on Road Projects in the Board's Six ...
Requirements for Pedestrian Improvements on Road Projects in the Board's Six ...Requirements for Pedestrian Improvements on Road Projects in the Board's Six ...
Requirements for Pedestrian Improvements on Road Projects in the Board's Six ...
 
Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013
 
Student Free Fare Program Update and Recommendations: Board Transportation Co...
Student Free Fare Program Update and Recommendations: Board Transportation Co...Student Free Fare Program Update and Recommendations: Board Transportation Co...
Student Free Fare Program Update and Recommendations: Board Transportation Co...
 
Fairfax County and the NVTA TransAction Update
Fairfax County and the NVTA TransAction UpdateFairfax County and the NVTA TransAction Update
Fairfax County and the NVTA TransAction Update
 
Board of Supervisors Transportation Committee: Proposed High Quality Transit ...
Board of Supervisors Transportation Committee: Proposed High Quality Transit ...Board of Supervisors Transportation Committee: Proposed High Quality Transit ...
Board of Supervisors Transportation Committee: Proposed High Quality Transit ...
 
Dulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and FundingDulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and Funding
 
Fairfax Commercial and Industrial Property Tax for Transportation
Fairfax Commercial and Industrial Property Tax for TransportationFairfax Commercial and Industrial Property Tax for Transportation
Fairfax Commercial and Industrial Property Tax for Transportation
 
Transform 66 Outside the Beltway: Multimodal Solutions- 495 to Haymarket
Transform 66 Outside the Beltway: Multimodal Solutions- 495 to HaymarketTransform 66 Outside the Beltway: Multimodal Solutions- 495 to Haymarket
Transform 66 Outside the Beltway: Multimodal Solutions- 495 to Haymarket
 
Herndon Metrorail Stations Access Management Study (HMSAMS)
Herndon Metrorail Stations Access Management Study (HMSAMS)Herndon Metrorail Stations Access Management Study (HMSAMS)
Herndon Metrorail Stations Access Management Study (HMSAMS)
 
Update on Route 1 Multimodal Alternatives Analysis
Update on Route 1 Multimodal Alternatives AnalysisUpdate on Route 1 Multimodal Alternatives Analysis
Update on Route 1 Multimodal Alternatives Analysis
 
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
 
Fairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor StudyFairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor Study
 
Board of Supervisors Transportation Committee: Next Steps for Urban Street St...
Board of Supervisors Transportation Committee: Next Steps for Urban Street St...Board of Supervisors Transportation Committee: Next Steps for Urban Street St...
Board of Supervisors Transportation Committee: Next Steps for Urban Street St...
 

Similar to Dulles Metrorail Silver Line Phase 2 Update

Silver Line Update: December 1, 2015
Silver Line Update: December 1, 2015Silver Line Update: December 1, 2015
Silver Line Update: December 1, 2015Fairfax County
 
Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015Fairfax County
 
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateDulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateFairfax County
 
Silver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportSilver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportFairfax County
 
Silver Line Phase 1-Status Report
Silver Line Phase 1-Status ReportSilver Line Phase 1-Status Report
Silver Line Phase 1-Status ReportFairfax County
 
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Fairfax County
 
Silver Line Update - Feb. 12, 2016
Silver Line Update - Feb. 12, 2016Silver Line Update - Feb. 12, 2016
Silver Line Update - Feb. 12, 2016Fairfax County
 
Transportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesTransportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesFairfax County
 
Transportation Priorities Plan Future Updates
Transportation Priorities Plan Future UpdatesTransportation Priorities Plan Future Updates
Transportation Priorities Plan Future UpdatesFairfax County
 
Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014Fairfax County
 
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...Fairfax County
 
Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014Fairfax County
 
Update on Reston Development and Transportation Projects
Update on Reston Development and Transportation ProjectsUpdate on Reston Development and Transportation Projects
Update on Reston Development and Transportation ProjectsFairfax County
 
Kirby Road Sidewalk - Citizens Information Meeting: Dec. 11, 2018
Kirby Road Sidewalk - Citizens Information Meeting: Dec. 11, 2018Kirby Road Sidewalk - Citizens Information Meeting: Dec. 11, 2018
Kirby Road Sidewalk - Citizens Information Meeting: Dec. 11, 2018Fairfax County
 
Kirby Road Sidewalk Presentation
Kirby Road Sidewalk PresentationKirby Road Sidewalk Presentation
Kirby Road Sidewalk PresentationFairfax County
 
Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014Fairfax County
 
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...Fairfax County
 
Dulles Rail Silver Line Phase 2 Status and Funding
Dulles Rail Silver Line Phase 2 Status and FundingDulles Rail Silver Line Phase 2 Status and Funding
Dulles Rail Silver Line Phase 2 Status and FundingFairfax County
 
Clean Water Facility Update
Clean Water Facility UpdateClean Water Facility Update
Clean Water Facility UpdateJackie Dagger
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects UpdateTownofAddison
 

Similar to Dulles Metrorail Silver Line Phase 2 Update (20)

Silver Line Update: December 1, 2015
Silver Line Update: December 1, 2015Silver Line Update: December 1, 2015
Silver Line Update: December 1, 2015
 
Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015
 
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateDulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
 
Silver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportSilver Line Phase 1 Status Report
Silver Line Phase 1 Status Report
 
Silver Line Phase 1-Status Report
Silver Line Phase 1-Status ReportSilver Line Phase 1-Status Report
Silver Line Phase 1-Status Report
 
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
 
Silver Line Update - Feb. 12, 2016
Silver Line Update - Feb. 12, 2016Silver Line Update - Feb. 12, 2016
Silver Line Update - Feb. 12, 2016
 
Transportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesTransportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future Updates
 
Transportation Priorities Plan Future Updates
Transportation Priorities Plan Future UpdatesTransportation Priorities Plan Future Updates
Transportation Priorities Plan Future Updates
 
Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014
 
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
 
Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014
 
Update on Reston Development and Transportation Projects
Update on Reston Development and Transportation ProjectsUpdate on Reston Development and Transportation Projects
Update on Reston Development and Transportation Projects
 
Kirby Road Sidewalk - Citizens Information Meeting: Dec. 11, 2018
Kirby Road Sidewalk - Citizens Information Meeting: Dec. 11, 2018Kirby Road Sidewalk - Citizens Information Meeting: Dec. 11, 2018
Kirby Road Sidewalk - Citizens Information Meeting: Dec. 11, 2018
 
Kirby Road Sidewalk Presentation
Kirby Road Sidewalk PresentationKirby Road Sidewalk Presentation
Kirby Road Sidewalk Presentation
 
Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014
 
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
 
Dulles Rail Silver Line Phase 2 Status and Funding
Dulles Rail Silver Line Phase 2 Status and FundingDulles Rail Silver Line Phase 2 Status and Funding
Dulles Rail Silver Line Phase 2 Status and Funding
 
Clean Water Facility Update
Clean Water Facility UpdateClean Water Facility Update
Clean Water Facility Update
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects Update
 

More from Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 

More from Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Recently uploaded

Rohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeRohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeAbdulGhani778830
 
Experience the Future of the Web3 Gaming Trend
Experience the Future of the Web3 Gaming TrendExperience the Future of the Web3 Gaming Trend
Experience the Future of the Web3 Gaming TrendFabwelt
 
16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkcomplaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkbhavenpr
 
IndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest2
 
15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.NaveedKhaskheli1
 
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdfGerald Furnkranz
 

Recently uploaded (8)

Rohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeRohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for Justice
 
Experience the Future of the Web3 Gaming Trend
Experience the Future of the Web3 Gaming TrendExperience the Future of the Web3 Gaming Trend
Experience the Future of the Web3 Gaming Trend
 
16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf
 
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkcomplaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
 
IndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global News
 
15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf
 
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.
 
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf
 

Dulles Metrorail Silver Line Phase 2 Update

  • 1. Status • Phase 1 • Punchlist – VDOT, WMATA, and Fairfax County • Ongoing • Fairfax County 274 items, 81 closed • Project Closeout • Ongoing • Contingency Remaining - $12.8M • Not all claims finalized • Wiehle Garage – 85% parking utilization • Phase 2 • Design Build Status • Overall Project – 14% • Design – 69% • Construction – 1% • Highlights • Aerial guideway under construction • 60 drilled shafts installed • 42 columns installed • 26 caps installed • Enabling work on Innovation Center Station began • Enabling work on Herndon and Reston Town Center 1st and 2nd quarter 2015 • 1,300 linear feet of existing utilities relocated County Activities • Phase 2 Design Reviews • County Coordination • Town of Herndon • Adjacent Land Owners • Project Partners (MWAA, VDOT, DRPT, WMATA, Loudoun County) • Fairfax Connector • Phase 1 Close Out and Punchlist • Coordination with MWAA and adjacent land owners on land use applications (SE, 2232) 1 January 20, 2015
  • 2. County Activities • Herndon & Innovation Center Station garages - DPWES lead for design/construction • Innovation Center Station Garage ($57M) • Rezoning was approved July 2014 • Schematic Design Received January 2015 – under review • Design development to be completed in March 2015 and start of construction expected March 2016 • Gordon and HGA Architects have been selected as part of the project team • Herndon Garage ($58.7M) • 2232 application was approved June 2014 • Schematic Design Received January 2015 – under review • Design development to be completed in March 2015 and start of construction expected March 2016 • Gordon and HGA Architects have been selected as part of the project team • TIFIA • Fairfax County Closed a $ 403.3M TIFIA Loan • 2nd lowest interest rate in the history of the TIFIA loan program - 2.73% • Only Maryland received a lower rate for the Inter-county Connector in 2009 – 2.56% • Fairfax County earned the lowest rate among the Silver Line funding partners • MWAA - $1.3B loan at 3.21% • Loudoun County - $195M at 2.87% • Loan will cover about 45% of the county’s total estimated cost of $915M 2 January 20, 2015