SlideShare a Scribd company logo
1 of 16
County of Fairfax, Virginia
Improving Project Delivery
Status Report
Board of Supervisors
Transportation Committee
February 4, 2014
Department of Transportation
County of Fairfax, Virginia
Background
• Revenues for transportation have significantly increased:
– HB 2313
– Tysons Transportation Funding Plan
– Secondary Road Program (funding increase beginning in 2017)
• Other funding sources anticipated to continue:
– C & I
– Transportation Bonds
• Six-year transportation project priorities approved by the Board on
January 28, 2014.
• Increased workload requires ongoing evaluation of ways to increase
efficiency and expedite delivery of new projects.
Department of Transportation
2
County of Fairfax, Virginia
Background – Continued
• VDOT staff resources limited due
to expanded VDOT funding and
legislative limits on number of
VDOT personnel.
• Project delivery will require
expanded County role for both
secondary and primary roadway,
transit, bicycle, and pedestrian
projects.
• The County has been successfully
delivering transportation projects.
However, there are opportunities
to improve the efficiency of project
delivery.
Department of Transportation
3
County of Fairfax, Virginia
Background – Continued
• FCDOT staff have been meeting
since June 2013 to discuss ways to
improve project delivery. Meetings
have included other agencies, such
as VDOT and DPWES.
• Many ideas were suggested by staff.
Some can likely be addressed in the
short-term, and some are already
underway.
• Others require longer-term
coordination, particularly those
involving outside agencies such as
VDOT and DPWES.
Department of Transportation
4
County of Fairfax, Virginia
Anticipated Timeframe
 Suggested ideas were broken into the following timeframes:
• Actions Underway, and Short-term Recommendations:
– Could be implemented within 12 months.
• Mid-Term Recommendations:
– Could be implemented over next 2 to 3 years. Changes involve
staff efforts, policy decisions, and outside agency cooperation.
• Longer-Term Recommendations:
– Could be implemented over next 3 to 5. Changes involve staff,
policy decisions, legislative changes, and outside agency
cooperation.
Department of Transportation
5
County of Fairfax, Virginia
Major Themes
 In addition, suggested ideas were divided into the following categories:
• Improve project budgeting and scheduling process.
• Identify project issues early.
• Improve communication.
• Expand staff capabilities.
Department of Transportation
6
County of Fairfax, Virginia
Improve Budgeting and Scheduling
 Project budgets and estimates must occasionally be modified due to
unforeseen issues and project complexities which can be time
consuming.
Actions Recommended: Programming
• Clarify and formalize staff procedures and responsibilities for
appropriating funds.
• Prioritize and program individual projects within anticipated 6-year
funding stream. Recognize funding source and associated
requirements.
– FY 2014-2020 Cash Flow program in development.
• Investigate ways to reduce steps in the approval process.
Department of Transportation
7
County of Fairfax, Virginia
Improve Budgeting and Scheduling - Continued
Actions Recommended: Project Level
• Improve accuracy of project cost estimates and develop realistic
schedules.
− Fully scope and analyze benefits and impacts of projects prior to
proceeding with project adoption/selection and implementation.
• Work with outside agencies, such as VDOT to expedite plan review
time for internal and external agencies.
• Expand countywide permit tools with VDOT.
• Streamline agreements with external agencies.
– Funding agreement with NVTA approved by the Board on January
28, 2014.
– Development of ‘annual’ Request to Administer (RTA) agreements
with VDOT is underway.
Department of Transportation
8
County of Fairfax, Virginia
Identify Project Issues Early
 Unforeseen issues can delay projects.
Actions Recommended:
• Develop conceptual plans sufficient to ensure the project:
– Addresses utility, right-of-way, and environmental issues.
– Project scope is acceptable to the community.
Actions Underway:
• Improve project scoping and field review process.
• Identify utilities, right-of-way, and environmental issues earlier through a
more detailed and expanded scoping process.
• Coordinate with VDOT and other agencies earlier.
• Create Project Checklists.
• Create GIS layer for pending projects.
Department of Transportation
9
County of Fairfax, Virginia
Identify Project Issues Early – Continued
Other Recommendations (mid-term):
• Identify legislative changes that would enhance project delivery.
Department of Transportation
10
County of Fairfax, Virginia
Expand Staff Capabilities
 Project implementation technics and methods are complex and
continue to evolve.
Actions Underway and Short-Term Recommendations:
• Provide Additional Training on:
– Project Implementation and Scheduling
– Contracting/Procurement
– Technical Software
– Environmental Issues/Regulations
– Right-of-Way Impacts and Acquisition
– Proffer Research and Allocation
• Formally document consistent implementation procedures from
procurement to construction.
Department of Transportation
11
County of Fairfax, Virginia
Expand Staff Capabilities – Continued
• Expand availability of technical and project management software.
• Strengthen design-build capabilities with new position approved by the
Board in FY 2014.
• Inventory of in-house expertise was completed.
Other Recommendations (mid-term):
• Formalize mentoring program for junior engineers to assist senior staff
on complex projects to build their professional experience.
• Develop standardized procedural documentation to provide consistent
training and project delivery.
• Hire project managers with areas of special technical expertise.
• Better align right-of-way and construction management efforts with
programming and design activities.
Department of Transportation
12
County of Fairfax, Virginia
Improve Communication
 Effective communication between multiple disciplines, divisions, and
outside agencies is critical to efficient project delivery.
Actions Underway and Short-Term Recommendations:
• Expand project specific scoping meetings, and the participating
agencies.
• Formalize project delivery teams.
• Improve productivity of meetings by:
– Formalizing team meetings at appropriate plan review stages.
– Ensure that staff represented at meetings have authority to make
decisions, and ensure follow up on action items.
Department of Transportation
13
County of Fairfax, Virginia
Improve Communication
Other Recommendations (mid-term)
• Continue to work with VDOT and DPWES to resolve project delivery
issues.
• Create integrated system on GIS layer for data, such as traffic counts,
proffers, VDOT permits, and environmental issues.
Department of Transportation
14
County of Fairfax, Virginia
Other Alternative Delivery Methods
• Investigation of other alternative project delivery methods could include:
– Use of specialized or imbedded consultants.
– Work with VDOT to reinstall the ‘state construction forces.’
– Use of land developers to implement certain projects.
– Public-private partnerships.
– Investigate other out-of-the box solutions.
Department of Transportation
15
County of Fairfax, Virginia
Monitoring and Reporting
 Establish a baseline for monitoring
and reporting on the improved
efficiency of project delivery.
Actions Identified:
• Develop measures to assess
efficiency of project delivery, e.g.,
percent on-time, within budget, etc.
• Provide periodic progress updates
to the Board Transportation
Committee.
Department of Transportation
16

More Related Content

What's hot

Transportation Alternatives Program Workshop and Public Comment
Transportation Alternatives Program Workshop and Public CommentTransportation Alternatives Program Workshop and Public Comment
Transportation Alternatives Program Workshop and Public CommentFairfax County
 
Fairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor StudyFairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor StudyFairfax County
 
Reston Bike Share Feasibility Study: Public Open House
Reston Bike Share Feasibility Study: Public Open HouseReston Bike Share Feasibility Study: Public Open House
Reston Bike Share Feasibility Study: Public Open HouseFairfax County
 
Fairfax County Capital Bikeshare
Fairfax County Capital BikeshareFairfax County Capital Bikeshare
Fairfax County Capital BikeshareFairfax County
 
Reston Network Analysis - Community Kick-Off: Feb. 1, 2016
Reston Network Analysis - Community Kick-Off: Feb. 1, 2016Reston Network Analysis - Community Kick-Off: Feb. 1, 2016
Reston Network Analysis - Community Kick-Off: Feb. 1, 2016Fairfax County
 
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016Fairfax County
 
Reston Transportation Funding Plan: Updates and Recommendation-Community Meet...
Reston Transportation Funding Plan: Updates and Recommendation-Community Meet...Reston Transportation Funding Plan: Updates and Recommendation-Community Meet...
Reston Transportation Funding Plan: Updates and Recommendation-Community Meet...Fairfax County
 
Transportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesTransportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesFairfax County
 
Countywide Transit Network Study: Public Meeting July 10, 2013
Countywide Transit Network Study: Public Meeting July 10, 2013Countywide Transit Network Study: Public Meeting July 10, 2013
Countywide Transit Network Study: Public Meeting July 10, 2013Fairfax County
 
Proposed Bicycle Facilities: VDOT Summer 2015 Repaving-Franconia Road
Proposed Bicycle Facilities: VDOT Summer 2015 Repaving-Franconia RoadProposed Bicycle Facilities: VDOT Summer 2015 Repaving-Franconia Road
Proposed Bicycle Facilities: VDOT Summer 2015 Repaving-Franconia RoadFairfax County
 
Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016
Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016
Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016Fairfax County
 
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...Fairfax County
 
Reston Transportation Funding Plan: Community Meeting June 27, 2016
Reston Transportation Funding Plan: Community Meeting June 27, 2016Reston Transportation Funding Plan: Community Meeting June 27, 2016
Reston Transportation Funding Plan: Community Meeting June 27, 2016Fairfax County
 
Continuation of Countywide Dialogue on Transportation
Continuation of Countywide Dialogue on TransportationContinuation of Countywide Dialogue on Transportation
Continuation of Countywide Dialogue on TransportationFairfax County
 
Countywide Transit Network Study: Introductory Public Meeting
Countywide Transit Network Study: Introductory Public MeetingCountywide Transit Network Study: Introductory Public Meeting
Countywide Transit Network Study: Introductory Public MeetingFairfax County
 
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...Fairfax County
 
Dulles Corridor Air Rights Study Investigation
Dulles Corridor Air Rights Study InvestigationDulles Corridor Air Rights Study Investigation
Dulles Corridor Air Rights Study InvestigationFairfax County
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...Fairfax County
 
I-66 Inside the Beltway Initial Traffic Analysis and Framework Agreement
I-66 Inside the Beltway Initial Traffic Analysis and Framework AgreementI-66 Inside the Beltway Initial Traffic Analysis and Framework Agreement
I-66 Inside the Beltway Initial Traffic Analysis and Framework AgreementFairfax County
 

What's hot (20)

Transportation Alternatives Program Workshop and Public Comment
Transportation Alternatives Program Workshop and Public CommentTransportation Alternatives Program Workshop and Public Comment
Transportation Alternatives Program Workshop and Public Comment
 
Fairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor StudyFairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor Study
 
Reston Bike Share Feasibility Study: Public Open House
Reston Bike Share Feasibility Study: Public Open HouseReston Bike Share Feasibility Study: Public Open House
Reston Bike Share Feasibility Study: Public Open House
 
Fairfax County Capital Bikeshare
Fairfax County Capital BikeshareFairfax County Capital Bikeshare
Fairfax County Capital Bikeshare
 
Reston Network Analysis - Community Kick-Off: Feb. 1, 2016
Reston Network Analysis - Community Kick-Off: Feb. 1, 2016Reston Network Analysis - Community Kick-Off: Feb. 1, 2016
Reston Network Analysis - Community Kick-Off: Feb. 1, 2016
 
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
 
Reston Transportation Funding Plan: Updates and Recommendation-Community Meet...
Reston Transportation Funding Plan: Updates and Recommendation-Community Meet...Reston Transportation Funding Plan: Updates and Recommendation-Community Meet...
Reston Transportation Funding Plan: Updates and Recommendation-Community Meet...
 
Reston Funding Plan
Reston Funding PlanReston Funding Plan
Reston Funding Plan
 
Transportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesTransportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future Updates
 
Countywide Transit Network Study: Public Meeting July 10, 2013
Countywide Transit Network Study: Public Meeting July 10, 2013Countywide Transit Network Study: Public Meeting July 10, 2013
Countywide Transit Network Study: Public Meeting July 10, 2013
 
Proposed Bicycle Facilities: VDOT Summer 2015 Repaving-Franconia Road
Proposed Bicycle Facilities: VDOT Summer 2015 Repaving-Franconia RoadProposed Bicycle Facilities: VDOT Summer 2015 Repaving-Franconia Road
Proposed Bicycle Facilities: VDOT Summer 2015 Repaving-Franconia Road
 
Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016
Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016
Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016
 
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
 
Reston Transportation Funding Plan: Community Meeting June 27, 2016
Reston Transportation Funding Plan: Community Meeting June 27, 2016Reston Transportation Funding Plan: Community Meeting June 27, 2016
Reston Transportation Funding Plan: Community Meeting June 27, 2016
 
Continuation of Countywide Dialogue on Transportation
Continuation of Countywide Dialogue on TransportationContinuation of Countywide Dialogue on Transportation
Continuation of Countywide Dialogue on Transportation
 
Countywide Transit Network Study: Introductory Public Meeting
Countywide Transit Network Study: Introductory Public MeetingCountywide Transit Network Study: Introductory Public Meeting
Countywide Transit Network Study: Introductory Public Meeting
 
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
 
Dulles Corridor Air Rights Study Investigation
Dulles Corridor Air Rights Study InvestigationDulles Corridor Air Rights Study Investigation
Dulles Corridor Air Rights Study Investigation
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
 
I-66 Inside the Beltway Initial Traffic Analysis and Framework Agreement
I-66 Inside the Beltway Initial Traffic Analysis and Framework AgreementI-66 Inside the Beltway Initial Traffic Analysis and Framework Agreement
I-66 Inside the Beltway Initial Traffic Analysis and Framework Agreement
 

Similar to Improving Project Delivery Status Report

NVBIA NAIOP GOAL 3 Update
NVBIA NAIOP GOAL 3 UpdateNVBIA NAIOP GOAL 3 Update
NVBIA NAIOP GOAL 3 UpdateFairfax County
 
Jim Proce - 2018 Capital Improvement Planning Process CPM Class
Jim Proce - 2018 Capital Improvement Planning Process CPM ClassJim Proce - 2018 Capital Improvement Planning Process CPM Class
Jim Proce - 2018 Capital Improvement Planning Process CPM ClassJim Proce
 
NVBIA-NAIOP Presentation
NVBIA-NAIOP Presentation NVBIA-NAIOP Presentation
NVBIA-NAIOP Presentation Fairfax County
 
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumTransportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumFairfax County
 
Transportation Alternatives Program (TAP): The Regional Role in Project Selec...
Transportation Alternatives Program (TAP): The Regional Role in Project Selec...Transportation Alternatives Program (TAP): The Regional Role in Project Selec...
Transportation Alternatives Program (TAP): The Regional Role in Project Selec...RPO America
 
Johnson gilmer presentation
Johnson gilmer presentationJohnson gilmer presentation
Johnson gilmer presentationRPO America
 
Publilc sector productivity - Johannes Wolff, United Kingdom
Publilc sector productivity - Johannes Wolff, United KingdomPublilc sector productivity - Johannes Wolff, United Kingdom
Publilc sector productivity - Johannes Wolff, United KingdomOECD Governance
 
Zlotchenko ncdot presentation
Zlotchenko ncdot presentationZlotchenko ncdot presentation
Zlotchenko ncdot presentationRPO America
 
7 board pri update 2-23-15 3 pm
7 board pri update 2-23-15   3 pm7 board pri update 2-23-15   3 pm
7 board pri update 2-23-15 3 pmRon Garrison
 
Comprehensive Plan Amendment Work Program Process (March 22, 2017)
Comprehensive Plan Amendment Work Program Process (March 22, 2017)Comprehensive Plan Amendment Work Program Process (March 22, 2017)
Comprehensive Plan Amendment Work Program Process (March 22, 2017)Fairfax County
 
Plan Making Reforms Implementation Consultation Presentation Aug 2023
	Plan Making Reforms Implementation Consultation Presentation Aug 2023	Plan Making Reforms Implementation Consultation Presentation Aug 2023
Plan Making Reforms Implementation Consultation Presentation Aug 2023mhutttch
 
Artba Map 21 Re-authorization VS Grow Act
Artba Map 21 Re-authorization VS Grow ActArtba Map 21 Re-authorization VS Grow Act
Artba Map 21 Re-authorization VS Grow Actartba
 
CGIAR Site Integration: Site Integration Plans – next steps
CGIAR Site Integration: Site Integration Plans – next stepsCGIAR Site Integration: Site Integration Plans – next steps
CGIAR Site Integration: Site Integration Plans – next stepsCGIAR
 
Plan Making Reforms Consultation - September 2023 Event Series - Publish.pdf
Plan Making Reforms Consultation - September 2023 Event Series - Publish.pdfPlan Making Reforms Consultation - September 2023 Event Series - Publish.pdf
Plan Making Reforms Consultation - September 2023 Event Series - Publish.pdfmhutttch
 
Concept to-completion-presentation
Concept to-completion-presentationConcept to-completion-presentation
Concept to-completion-presentationbunthy sros
 
NCAPA LYNX BLE Blue Print for Change
NCAPA LYNX BLE Blue Print for ChangeNCAPA LYNX BLE Blue Print for Change
NCAPA LYNX BLE Blue Print for ChangeMeghan Makoid
 
Enhancement Projects: Improving Successful Implementation in Minnesota
Enhancement Projects: Improving Successful Implementation in MinnesotaEnhancement Projects: Improving Successful Implementation in Minnesota
Enhancement Projects: Improving Successful Implementation in MinnesotaRPO America
 

Similar to Improving Project Delivery Status Report (20)

NVBIA NAIOP GOAL 3 Update
NVBIA NAIOP GOAL 3 UpdateNVBIA NAIOP GOAL 3 Update
NVBIA NAIOP GOAL 3 Update
 
Jim Proce - 2018 Capital Improvement Planning Process CPM Class
Jim Proce - 2018 Capital Improvement Planning Process CPM ClassJim Proce - 2018 Capital Improvement Planning Process CPM Class
Jim Proce - 2018 Capital Improvement Planning Process CPM Class
 
NVBIA-NAIOP Presentation
NVBIA-NAIOP Presentation NVBIA-NAIOP Presentation
NVBIA-NAIOP Presentation
 
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumTransportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
 
Transportation Alternatives Program (TAP): The Regional Role in Project Selec...
Transportation Alternatives Program (TAP): The Regional Role in Project Selec...Transportation Alternatives Program (TAP): The Regional Role in Project Selec...
Transportation Alternatives Program (TAP): The Regional Role in Project Selec...
 
Johnson gilmer presentation
Johnson gilmer presentationJohnson gilmer presentation
Johnson gilmer presentation
 
Publilc sector productivity - Johannes Wolff, United Kingdom
Publilc sector productivity - Johannes Wolff, United KingdomPublilc sector productivity - Johannes Wolff, United Kingdom
Publilc sector productivity - Johannes Wolff, United Kingdom
 
Zlotchenko ncdot presentation
Zlotchenko ncdot presentationZlotchenko ncdot presentation
Zlotchenko ncdot presentation
 
7 board pri update 2-23-15 3 pm
7 board pri update 2-23-15   3 pm7 board pri update 2-23-15   3 pm
7 board pri update 2-23-15 3 pm
 
Comprehensive Plan Amendment Work Program Process (March 22, 2017)
Comprehensive Plan Amendment Work Program Process (March 22, 2017)Comprehensive Plan Amendment Work Program Process (March 22, 2017)
Comprehensive Plan Amendment Work Program Process (March 22, 2017)
 
Plan Making Reforms Implementation Consultation Presentation Aug 2023
	Plan Making Reforms Implementation Consultation Presentation Aug 2023	Plan Making Reforms Implementation Consultation Presentation Aug 2023
Plan Making Reforms Implementation Consultation Presentation Aug 2023
 
Federal transportation funding and innovations
Federal transportation funding and innovationsFederal transportation funding and innovations
Federal transportation funding and innovations
 
Artba Map 21 Re-authorization VS Grow Act
Artba Map 21 Re-authorization VS Grow ActArtba Map 21 Re-authorization VS Grow Act
Artba Map 21 Re-authorization VS Grow Act
 
CGIAR Site Integration: Site Integration Plans – next steps
CGIAR Site Integration: Site Integration Plans – next stepsCGIAR Site Integration: Site Integration Plans – next steps
CGIAR Site Integration: Site Integration Plans – next steps
 
Plan Making Reforms Consultation - September 2023 Event Series - Publish.pdf
Plan Making Reforms Consultation - September 2023 Event Series - Publish.pdfPlan Making Reforms Consultation - September 2023 Event Series - Publish.pdf
Plan Making Reforms Consultation - September 2023 Event Series - Publish.pdf
 
Concept to-completion-presentation
Concept to-completion-presentationConcept to-completion-presentation
Concept to-completion-presentation
 
Not Your Grandfather's DOT: The FDOT District 5 and PennDOT Experiences--Bria...
Not Your Grandfather's DOT: The FDOT District 5 and PennDOT Experiences--Bria...Not Your Grandfather's DOT: The FDOT District 5 and PennDOT Experiences--Bria...
Not Your Grandfather's DOT: The FDOT District 5 and PennDOT Experiences--Bria...
 
NCAPA LYNX BLE Blue Print for Change
NCAPA LYNX BLE Blue Print for ChangeNCAPA LYNX BLE Blue Print for Change
NCAPA LYNX BLE Blue Print for Change
 
Enhancement Projects: Improving Successful Implementation in Minnesota
Enhancement Projects: Improving Successful Implementation in MinnesotaEnhancement Projects: Improving Successful Implementation in Minnesota
Enhancement Projects: Improving Successful Implementation in Minnesota
 
February 10, 2021 FTAC Virtual Workshop
February 10, 2021 FTAC Virtual WorkshopFebruary 10, 2021 FTAC Virtual Workshop
February 10, 2021 FTAC Virtual Workshop
 

More from Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 

More from Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Recently uploaded

12042024_First India Newspaper Jaipur.pdf
12042024_First India Newspaper Jaipur.pdf12042024_First India Newspaper Jaipur.pdf
12042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
13042024_First India Newspaper Jaipur.pdf
13042024_First India Newspaper Jaipur.pdf13042024_First India Newspaper Jaipur.pdf
13042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
lok sabha Elections in india- 2024 .pptx
lok sabha Elections in india- 2024 .pptxlok sabha Elections in india- 2024 .pptx
lok sabha Elections in india- 2024 .pptxdigiyvbmrkt
 
Emerging issues in migration policies.ppt
Emerging issues in migration policies.pptEmerging issues in migration policies.ppt
Emerging issues in migration policies.pptNandinituteja1
 
Political-Ideologies-and-The-Movements.pptx
Political-Ideologies-and-The-Movements.pptxPolitical-Ideologies-and-The-Movements.pptx
Political-Ideologies-and-The-Movements.pptxSasikiranMarri
 
Mitochondrial Fusion Vital for Adult Brain Function and Disease Understanding...
Mitochondrial Fusion Vital for Adult Brain Function and Disease Understanding...Mitochondrial Fusion Vital for Adult Brain Function and Disease Understanding...
Mitochondrial Fusion Vital for Adult Brain Function and Disease Understanding...The Lifesciences Magazine
 
14042024_First India Newspaper Jaipur.pdf
14042024_First India Newspaper Jaipur.pdf14042024_First India Newspaper Jaipur.pdf
14042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Geostrategic significance of South Asian countries.ppt
Geostrategic significance of South Asian countries.pptGeostrategic significance of South Asian countries.ppt
Geostrategic significance of South Asian countries.pptUsmanKaran
 
11042024_First India Newspaper Jaipur.pdf
11042024_First India Newspaper Jaipur.pdf11042024_First India Newspaper Jaipur.pdf
11042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Foreign Relation of Pakistan with Neighboring Countries.pptx
Foreign Relation of Pakistan with Neighboring Countries.pptxForeign Relation of Pakistan with Neighboring Countries.pptx
Foreign Relation of Pakistan with Neighboring Countries.pptxunark75
 
Power in International Relations (Pol 5)
Power in International Relations (Pol 5)Power in International Relations (Pol 5)
Power in International Relations (Pol 5)ssuser583c35
 
16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Transforming Andhra Pradesh: TDP's Legacy in Road Connectivity
Transforming Andhra Pradesh: TDP's Legacy in Road ConnectivityTransforming Andhra Pradesh: TDP's Legacy in Road Connectivity
Transforming Andhra Pradesh: TDP's Legacy in Road Connectivitynarsireddynannuri1
 

Recently uploaded (14)

12042024_First India Newspaper Jaipur.pdf
12042024_First India Newspaper Jaipur.pdf12042024_First India Newspaper Jaipur.pdf
12042024_First India Newspaper Jaipur.pdf
 
13042024_First India Newspaper Jaipur.pdf
13042024_First India Newspaper Jaipur.pdf13042024_First India Newspaper Jaipur.pdf
13042024_First India Newspaper Jaipur.pdf
 
15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf
 
lok sabha Elections in india- 2024 .pptx
lok sabha Elections in india- 2024 .pptxlok sabha Elections in india- 2024 .pptx
lok sabha Elections in india- 2024 .pptx
 
Emerging issues in migration policies.ppt
Emerging issues in migration policies.pptEmerging issues in migration policies.ppt
Emerging issues in migration policies.ppt
 
Political-Ideologies-and-The-Movements.pptx
Political-Ideologies-and-The-Movements.pptxPolitical-Ideologies-and-The-Movements.pptx
Political-Ideologies-and-The-Movements.pptx
 
Mitochondrial Fusion Vital for Adult Brain Function and Disease Understanding...
Mitochondrial Fusion Vital for Adult Brain Function and Disease Understanding...Mitochondrial Fusion Vital for Adult Brain Function and Disease Understanding...
Mitochondrial Fusion Vital for Adult Brain Function and Disease Understanding...
 
14042024_First India Newspaper Jaipur.pdf
14042024_First India Newspaper Jaipur.pdf14042024_First India Newspaper Jaipur.pdf
14042024_First India Newspaper Jaipur.pdf
 
Geostrategic significance of South Asian countries.ppt
Geostrategic significance of South Asian countries.pptGeostrategic significance of South Asian countries.ppt
Geostrategic significance of South Asian countries.ppt
 
11042024_First India Newspaper Jaipur.pdf
11042024_First India Newspaper Jaipur.pdf11042024_First India Newspaper Jaipur.pdf
11042024_First India Newspaper Jaipur.pdf
 
Foreign Relation of Pakistan with Neighboring Countries.pptx
Foreign Relation of Pakistan with Neighboring Countries.pptxForeign Relation of Pakistan with Neighboring Countries.pptx
Foreign Relation of Pakistan with Neighboring Countries.pptx
 
Power in International Relations (Pol 5)
Power in International Relations (Pol 5)Power in International Relations (Pol 5)
Power in International Relations (Pol 5)
 
16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf
 
Transforming Andhra Pradesh: TDP's Legacy in Road Connectivity
Transforming Andhra Pradesh: TDP's Legacy in Road ConnectivityTransforming Andhra Pradesh: TDP's Legacy in Road Connectivity
Transforming Andhra Pradesh: TDP's Legacy in Road Connectivity
 

Improving Project Delivery Status Report

  • 1. County of Fairfax, Virginia Improving Project Delivery Status Report Board of Supervisors Transportation Committee February 4, 2014 Department of Transportation
  • 2. County of Fairfax, Virginia Background • Revenues for transportation have significantly increased: – HB 2313 – Tysons Transportation Funding Plan – Secondary Road Program (funding increase beginning in 2017) • Other funding sources anticipated to continue: – C & I – Transportation Bonds • Six-year transportation project priorities approved by the Board on January 28, 2014. • Increased workload requires ongoing evaluation of ways to increase efficiency and expedite delivery of new projects. Department of Transportation 2
  • 3. County of Fairfax, Virginia Background – Continued • VDOT staff resources limited due to expanded VDOT funding and legislative limits on number of VDOT personnel. • Project delivery will require expanded County role for both secondary and primary roadway, transit, bicycle, and pedestrian projects. • The County has been successfully delivering transportation projects. However, there are opportunities to improve the efficiency of project delivery. Department of Transportation 3
  • 4. County of Fairfax, Virginia Background – Continued • FCDOT staff have been meeting since June 2013 to discuss ways to improve project delivery. Meetings have included other agencies, such as VDOT and DPWES. • Many ideas were suggested by staff. Some can likely be addressed in the short-term, and some are already underway. • Others require longer-term coordination, particularly those involving outside agencies such as VDOT and DPWES. Department of Transportation 4
  • 5. County of Fairfax, Virginia Anticipated Timeframe  Suggested ideas were broken into the following timeframes: • Actions Underway, and Short-term Recommendations: – Could be implemented within 12 months. • Mid-Term Recommendations: – Could be implemented over next 2 to 3 years. Changes involve staff efforts, policy decisions, and outside agency cooperation. • Longer-Term Recommendations: – Could be implemented over next 3 to 5. Changes involve staff, policy decisions, legislative changes, and outside agency cooperation. Department of Transportation 5
  • 6. County of Fairfax, Virginia Major Themes  In addition, suggested ideas were divided into the following categories: • Improve project budgeting and scheduling process. • Identify project issues early. • Improve communication. • Expand staff capabilities. Department of Transportation 6
  • 7. County of Fairfax, Virginia Improve Budgeting and Scheduling  Project budgets and estimates must occasionally be modified due to unforeseen issues and project complexities which can be time consuming. Actions Recommended: Programming • Clarify and formalize staff procedures and responsibilities for appropriating funds. • Prioritize and program individual projects within anticipated 6-year funding stream. Recognize funding source and associated requirements. – FY 2014-2020 Cash Flow program in development. • Investigate ways to reduce steps in the approval process. Department of Transportation 7
  • 8. County of Fairfax, Virginia Improve Budgeting and Scheduling - Continued Actions Recommended: Project Level • Improve accuracy of project cost estimates and develop realistic schedules. − Fully scope and analyze benefits and impacts of projects prior to proceeding with project adoption/selection and implementation. • Work with outside agencies, such as VDOT to expedite plan review time for internal and external agencies. • Expand countywide permit tools with VDOT. • Streamline agreements with external agencies. – Funding agreement with NVTA approved by the Board on January 28, 2014. – Development of ‘annual’ Request to Administer (RTA) agreements with VDOT is underway. Department of Transportation 8
  • 9. County of Fairfax, Virginia Identify Project Issues Early  Unforeseen issues can delay projects. Actions Recommended: • Develop conceptual plans sufficient to ensure the project: – Addresses utility, right-of-way, and environmental issues. – Project scope is acceptable to the community. Actions Underway: • Improve project scoping and field review process. • Identify utilities, right-of-way, and environmental issues earlier through a more detailed and expanded scoping process. • Coordinate with VDOT and other agencies earlier. • Create Project Checklists. • Create GIS layer for pending projects. Department of Transportation 9
  • 10. County of Fairfax, Virginia Identify Project Issues Early – Continued Other Recommendations (mid-term): • Identify legislative changes that would enhance project delivery. Department of Transportation 10
  • 11. County of Fairfax, Virginia Expand Staff Capabilities  Project implementation technics and methods are complex and continue to evolve. Actions Underway and Short-Term Recommendations: • Provide Additional Training on: – Project Implementation and Scheduling – Contracting/Procurement – Technical Software – Environmental Issues/Regulations – Right-of-Way Impacts and Acquisition – Proffer Research and Allocation • Formally document consistent implementation procedures from procurement to construction. Department of Transportation 11
  • 12. County of Fairfax, Virginia Expand Staff Capabilities – Continued • Expand availability of technical and project management software. • Strengthen design-build capabilities with new position approved by the Board in FY 2014. • Inventory of in-house expertise was completed. Other Recommendations (mid-term): • Formalize mentoring program for junior engineers to assist senior staff on complex projects to build their professional experience. • Develop standardized procedural documentation to provide consistent training and project delivery. • Hire project managers with areas of special technical expertise. • Better align right-of-way and construction management efforts with programming and design activities. Department of Transportation 12
  • 13. County of Fairfax, Virginia Improve Communication  Effective communication between multiple disciplines, divisions, and outside agencies is critical to efficient project delivery. Actions Underway and Short-Term Recommendations: • Expand project specific scoping meetings, and the participating agencies. • Formalize project delivery teams. • Improve productivity of meetings by: – Formalizing team meetings at appropriate plan review stages. – Ensure that staff represented at meetings have authority to make decisions, and ensure follow up on action items. Department of Transportation 13
  • 14. County of Fairfax, Virginia Improve Communication Other Recommendations (mid-term) • Continue to work with VDOT and DPWES to resolve project delivery issues. • Create integrated system on GIS layer for data, such as traffic counts, proffers, VDOT permits, and environmental issues. Department of Transportation 14
  • 15. County of Fairfax, Virginia Other Alternative Delivery Methods • Investigation of other alternative project delivery methods could include: – Use of specialized or imbedded consultants. – Work with VDOT to reinstall the ‘state construction forces.’ – Use of land developers to implement certain projects. – Public-private partnerships. – Investigate other out-of-the box solutions. Department of Transportation 15
  • 16. County of Fairfax, Virginia Monitoring and Reporting  Establish a baseline for monitoring and reporting on the improved efficiency of project delivery. Actions Identified: • Develop measures to assess efficiency of project delivery, e.g., percent on-time, within budget, etc. • Provide periodic progress updates to the Board Transportation Committee. Department of Transportation 16