Silver Line Phase 1-Status Report: Feb. 4, 2014
Upcoming SlideShare
Loading in...5
×
 

Silver Line Phase 1-Status Report: Feb. 4, 2014

on

  • 236 views

Silver Line Phase 1-Status Report: Feb. 4, 2014

Silver Line Phase 1-Status Report: Feb. 4, 2014

Statistics

Views

Total Views
236
Views on SlideShare
188
Embed Views
48

Actions

Likes
0
Downloads
0
Comments
0

3 Embeds 48

http://www.fairfaxcounty.gov 38
http://ffxpwdevpgc01 9
http://ffxwcmasvm02 1

Accessibility

Categories

Upload Details

Uploaded via as Microsoft PowerPoint

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

    Silver Line Phase 1-Status Report: Feb. 4, 2014 Silver Line Phase 1-Status Report: Feb. 4, 2014 Presentation Transcript

    • Status • Overall Phase 1 Construction – 99% complete • Primary Focus: • Station Certificates of Occupancy • Testing • Punch List • Achieve Substantial Completion by Dulles Transit Partners • System Performance Demonstration Test Conducted – Jan 25-26 • Wiehle garage – Complete • Record of Decision roadway improvements – 99% complete (minor work remains) • Connector bus testing at Wiehle north - Ongoing • West Falls Church rail yard: • Completion – 95% • Community Meeting – Jan 29, 2014 • Sound Box Completion – Feb 2014 • Testing - Feb 2014 • Two noise studies / reports will be prepared – Condition 7 and 8 (SEA) • WMATA will provide FCDOT 30 day notice prior to start of revenue operations to allow for Connector service changes • Phase 1 project remains on budget - $ 2.906B Schedule • Substantial completion/MWAA turn-over to WMATA: • MWAA continues to work with DTP on Scheduled Substantial Completion Date (SSCD) • System testing is ongoing • Estimated passenger revenue service - date determined by WMATA when testing, training, and safe operation is achieved (WMATA has 90 days after SSCD for testing, training, and acceptance) • Tristate Oversight Committee Safety and Security process concurrent with WMATA testing • February 2014 Sound Box Testing WFCY • Tax District Advisory & Commission Meetings – March 2014 Current Milestones – Past 30 Days • Regional coordination for bus service and marketing outreach ongoing • WMATA lead for Phase 1 marketing and outreach; public website: www. silverlinemetro.com • Connector conducting operation testing Wiehle Garage • Fit out activities ongoing • Phase 1 Maintenance & Land Conveyance process ongoing; “walk down” field visits ongoing for property being turned over to the county • Punch List and Testing – Ongoing • Systems Performance Test Conducted 1 February 2013
    • Status • Phase 2 fully in design stage • 60% and some 90% design packages received • Issued for Construction packets – Starting Spring 2014 • Coordination ongoing • Town of Herndon • Adjacent Land Owners • Project Partners • Herndon and Innovation Center Station (south) garages • Fairfax County has committed to fund and construct parking garages - Design ongoing • Innovation Center Station Garage - Land use case ongoing (June 2014) • Herndon Garage - staff has developed a number of concept designs (2232) • Scheduled tracks completion of the garages to the completion of Phase 2 • Town Center Parkway tunnel • Final concept design received by consultant November 2013 • FCDOT submits formal request to MWAA for change order / pricing on Nov. 18, 2013 • Status of Phase 2 Bid Packages: • Packet A - rail Line, station, and systems (includes Innovation Center Station) - Awarded • Packet B - Maintenance Facility at Dulles Airport • Award – Summer 2014 • NTP – Summer 2014 • Completion Summer 2018 • MWAA’s Dulles Rail office to relocate to Herndon – Completed on Jan 17, 2014 Budget/Schedule • Cost Estimate: $3.093B • Cost Estimate with value engineering , Packet A savings, and garages funding outside the project: $2.6B • Substantial Completion: Summer 2018 • Revenue Operations: Late 2018 • Tax District Advisory & Commission Meetings – March 2014 Current Milestones – Past 30 Days • FTA oversight of Phase 2 similar to Phase 1 • TIFIA process – Ongoing • Design – Ongoing • Herndon Metrorail Station Access Management Study (HMSAMS) • Identify pedestrian, bicycle, bus transit and roadway improvements to and from Herndon and Innovation Center Station • Public Meetings – Spring 2014 2 February 2013