SlideShare a Scribd company logo
1 of 5
December 2013
Status
• Overall Phase 1 Construction – 99% complete
• All Station at 98% complete except Wiehle – Reston
East at 99% complete
• Systems work – 98% complete
• Primary Focus:
• Station Completion
• Testing
• Punch List
• Wiehle garage – Complete
• Punch list and site work ongoing
• Record of Decision roadway improvements – 99%
complete
• Anticipated completion Dec. 16, 2013
• Connector bus testing at Wiehle north - Ongoing
• West Falls Church rail yard:
• Completion – 93% (Jan. 2014)
• Sound Box Testing – Jan 2014
• Sound Box Test Plan – Under review
• Public Meeting early Jan 2014
• Two noise studies / reports will be prepared
– Condition 7 and 8 (SEA)
• First delivery of 7000-series rail cars – Feb. 2014 (WMATA
will use current fleet spare ratio to run Phase 1 service)
• WMATA will provide FCDOT 30 day notice prior to start of
revenue operations to allow for Connector service changes
• Phase 1 project remains on budget - $ 2.906B

Schedule
• Substantial completion/MWAA turn-over to WMATA:
• MWAA continues to work with DTP on SSCD
• System testing is ongoing
• Estimated passenger revenue service - date determined by
WMATA when testing, training, and safe operation is
achieved (WMATA has 90 days after SSCD for testing,
training, and acceptance)
• January 2014 Sound Box Testing WFCY

Current Milestones – Past 30 Days
• Regional coordination for bus service and marketing
outreach ongoing
• WMATA lead for Phase 1 marketing and outreach;
public website: www. silverlinemetro.com
• Connector conducting operation testing Wiehle Garage
• Fit out activities ongoing
• Phase 1 Maintenance & Land Conveyance process ongoing;
“walk down” field visits ongoing for property being turned
over to the county
• Punch List and Testing - Ongoing

1
December 2013
Status
• Phase 2 fully into the design stage
• 23 of the 43 60% design packages received
• Issued for Construction packets – Starting Spring
2014
• Coordination ongoing
• Town of Herndon
• Adjacent Land Owners
• Herndon and Innovation Center Station (south) garages
• Fairfax County has committed funding for design of
the parking garages. The county has entered into a
Real Estate Exchange Agreement with an adjacent
property owner at Innovation Center Station for an
improved transit oriented development and a real
estate agreement.
• At Herndon staff has developed a number of
concept designs
• Scheduled have been developed that track
completion of the garages to the completion of
Phase 2
• Town Center Parkway tunnel
• Final concept design received by consultant
November 2013
• FCDOT submits formal request to MWAA for
change order / pricing on Nov. 18, 2013

• Status of Phase 2 Bid Packages:
• Packet A - rail Line, station, and systems (includes
Innovation Center Station) - Awarded
• Maintenance Facility
• RFQI - Issued Nov. 12, 2013
• RFP – Jan. 2014 (est.)
• Award – 2nd Qtr. 2014
• NTP – July 2014
• Completion Summer 2018
• MWAA’s Dulles Rail office to relocate to Herndon – Moves
ongoing through Jan 17, 2014

Budget/Schedule
• Cost Estimate: $3.093B
• Cost Estimate with value engineering , Packet A savings,
and garages funding outside the project: $2.6B
• Cost to build garages in Fairfax County: $135M est.
• Substantial Completion: Summer 2018
• Revenue Operations: Late 2018

Current Milestones – Past 30 Days
• FTA oversight of Phase 2 under discussion - Ongoing
• TIFIA process – Ongoing
• Design - Ongoing

2
December 2013

Status
• Phase 2 Parking Garages (Herndon Station and Innovation Center Station) – Plan of
Finance
• Per MOA Counties to utilize “best efforts” to fund garages outside of project
• County will construct and own the garages upon completion
• Pledge parking revenue to cover financing costs:
• Revenue generated from the two parking garages
• Surcharge revenue from the County garages currently in the WMATA System
• County and WMATA working on a revised surcharge agreement
• Legal changes will require WMATA and Board of Supervisor approval
(Winter/Spring 2014)

3
December 2013

Greensboro Station - Looking east with Route 7 on the left; the sidewalk and curb & gutter construction is
complete and the balance of the site work is nearing completion. Photo courtesy Stephen Barna, DCMP.

4
December 2013

Wiehle-Reston East Station south pedestrian pavilion with completed Metro entrance pylon. Completed Wiehle
south bus lane/bays is to the right of the Metro pylon. Photo courtesy Stephen Barna, DCMP.

5

More Related Content

What's hot

Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)Fairfax County
 
Transportation Plan Map In County Comprehensive Plan-Completed Facilities
Transportation Plan Map In County Comprehensive Plan-Completed FacilitiesTransportation Plan Map In County Comprehensive Plan-Completed Facilities
Transportation Plan Map In County Comprehensive Plan-Completed FacilitiesFairfax County
 
Fairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor StudyFairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor StudyFairfax County
 
Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015Fairfax County
 
Board Transportation Committee Update: March 17, 2015
Board Transportation Committee Update: March 17, 2015Board Transportation Committee Update: March 17, 2015
Board Transportation Committee Update: March 17, 2015Fairfax County
 
Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014Fairfax County
 
Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Silver Line Update: Board Transportation Committee: Feb. 7, 2017Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Silver Line Update: Board Transportation Committee: Feb. 7, 2017Fairfax County
 
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumTransportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumFairfax County
 
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...Fairfax County
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Fairfax County
 
Reston Network Analysis: 2050 2nd Tier Mitigation Results
Reston Network Analysis: 2050 2nd Tier Mitigation ResultsReston Network Analysis: 2050 2nd Tier Mitigation Results
Reston Network Analysis: 2050 2nd Tier Mitigation ResultsFairfax County
 
Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Fairfax County
 
VDRPT Route 1 Multimodal Alternatives Analysis
VDRPT Route 1 Multimodal Alternatives AnalysisVDRPT Route 1 Multimodal Alternatives Analysis
VDRPT Route 1 Multimodal Alternatives AnalysisFairfax County
 
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateDulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateFairfax County
 
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Fairfax County
 
I-66 Beltway to Haymarket - VDOT
 I-66 Beltway to Haymarket - VDOT I-66 Beltway to Haymarket - VDOT
I-66 Beltway to Haymarket - VDOTFairfax County
 
Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013Fairfax County
 
Dulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and FundingDulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and FundingFairfax County
 
Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016Fairfax County
 
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield District
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield DistrictProposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield District
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield DistrictFairfax County
 

What's hot (20)

Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)
 
Transportation Plan Map In County Comprehensive Plan-Completed Facilities
Transportation Plan Map In County Comprehensive Plan-Completed FacilitiesTransportation Plan Map In County Comprehensive Plan-Completed Facilities
Transportation Plan Map In County Comprehensive Plan-Completed Facilities
 
Fairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor StudyFairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor Study
 
Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015
 
Board Transportation Committee Update: March 17, 2015
Board Transportation Committee Update: March 17, 2015Board Transportation Committee Update: March 17, 2015
Board Transportation Committee Update: March 17, 2015
 
Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014
 
Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Silver Line Update: Board Transportation Committee: Feb. 7, 2017Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Silver Line Update: Board Transportation Committee: Feb. 7, 2017
 
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumTransportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
 
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
 
Reston Network Analysis: 2050 2nd Tier Mitigation Results
Reston Network Analysis: 2050 2nd Tier Mitigation ResultsReston Network Analysis: 2050 2nd Tier Mitigation Results
Reston Network Analysis: 2050 2nd Tier Mitigation Results
 
Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016
 
VDRPT Route 1 Multimodal Alternatives Analysis
VDRPT Route 1 Multimodal Alternatives AnalysisVDRPT Route 1 Multimodal Alternatives Analysis
VDRPT Route 1 Multimodal Alternatives Analysis
 
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateDulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
 
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
 
I-66 Beltway to Haymarket - VDOT
 I-66 Beltway to Haymarket - VDOT I-66 Beltway to Haymarket - VDOT
I-66 Beltway to Haymarket - VDOT
 
Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013
 
Dulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and FundingDulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and Funding
 
Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016
 
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield District
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield DistrictProposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield District
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield District
 

Viewers also liked

Urban Street Standards Progress Report
Urban Street Standards Progress ReportUrban Street Standards Progress Report
Urban Street Standards Progress ReportFairfax County
 
Operational Analysis of Dulles Toll Road Ramps to Tysons
Operational Analysis of Dulles Toll Road Ramps to TysonsOperational Analysis of Dulles Toll Road Ramps to Tysons
Operational Analysis of Dulles Toll Road Ramps to TysonsFairfax County
 
Dulles Corridor Air Rights Study Investigation
Dulles Corridor Air Rights Study InvestigationDulles Corridor Air Rights Study Investigation
Dulles Corridor Air Rights Study InvestigationFairfax County
 
Fairfax County Bicycle Master Plan
Fairfax County Bicycle Master PlanFairfax County Bicycle Master Plan
Fairfax County Bicycle Master PlanFairfax County
 
Continuation of Countywide Dialogue on Transportation
Continuation of Countywide Dialogue on TransportationContinuation of Countywide Dialogue on Transportation
Continuation of Countywide Dialogue on TransportationFairfax County
 
Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013Fairfax County
 
Fairfax County Countywide Transit Network Study: Sept. 17, 2013
Fairfax County Countywide Transit Network Study: Sept. 17, 2013Fairfax County Countywide Transit Network Study: Sept. 17, 2013
Fairfax County Countywide Transit Network Study: Sept. 17, 2013Fairfax County
 
Potential Fairfax County Photo Red Light Program
Potential Fairfax County Photo Red Light ProgramPotential Fairfax County Photo Red Light Program
Potential Fairfax County Photo Red Light ProgramFairfax County
 
Board of Supervisors Transportation Committee-Next Steps for Urban Street Sta...
Board of Supervisors Transportation Committee-Next Steps for Urban Street Sta...Board of Supervisors Transportation Committee-Next Steps for Urban Street Sta...
Board of Supervisors Transportation Committee-Next Steps for Urban Street Sta...Fairfax County
 
Route 1 Multimodal Alternatives Analysis Status Update: Sept. 17, 2013
Route 1 Multimodal Alternatives Analysis Status Update: Sept. 17, 2013Route 1 Multimodal Alternatives Analysis Status Update: Sept. 17, 2013
Route 1 Multimodal Alternatives Analysis Status Update: Sept. 17, 2013Fairfax County
 
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Fairfax County
 
Interstate 66 Corridor Improvements
Interstate 66 Corridor ImprovementsInterstate 66 Corridor Improvements
Interstate 66 Corridor ImprovementsFairfax County
 
Policy on Level of Service in Activity Centers
Policy on Level of Service in Activity CentersPolicy on Level of Service in Activity Centers
Policy on Level of Service in Activity CentersFairfax County
 
Stormwater and Wastewater Consolidation
Stormwater and Wastewater Consolidation Stormwater and Wastewater Consolidation
Stormwater and Wastewater Consolidation Fairfax County
 

Viewers also liked (14)

Urban Street Standards Progress Report
Urban Street Standards Progress ReportUrban Street Standards Progress Report
Urban Street Standards Progress Report
 
Operational Analysis of Dulles Toll Road Ramps to Tysons
Operational Analysis of Dulles Toll Road Ramps to TysonsOperational Analysis of Dulles Toll Road Ramps to Tysons
Operational Analysis of Dulles Toll Road Ramps to Tysons
 
Dulles Corridor Air Rights Study Investigation
Dulles Corridor Air Rights Study InvestigationDulles Corridor Air Rights Study Investigation
Dulles Corridor Air Rights Study Investigation
 
Fairfax County Bicycle Master Plan
Fairfax County Bicycle Master PlanFairfax County Bicycle Master Plan
Fairfax County Bicycle Master Plan
 
Continuation of Countywide Dialogue on Transportation
Continuation of Countywide Dialogue on TransportationContinuation of Countywide Dialogue on Transportation
Continuation of Countywide Dialogue on Transportation
 
Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013
 
Fairfax County Countywide Transit Network Study: Sept. 17, 2013
Fairfax County Countywide Transit Network Study: Sept. 17, 2013Fairfax County Countywide Transit Network Study: Sept. 17, 2013
Fairfax County Countywide Transit Network Study: Sept. 17, 2013
 
Potential Fairfax County Photo Red Light Program
Potential Fairfax County Photo Red Light ProgramPotential Fairfax County Photo Red Light Program
Potential Fairfax County Photo Red Light Program
 
Board of Supervisors Transportation Committee-Next Steps for Urban Street Sta...
Board of Supervisors Transportation Committee-Next Steps for Urban Street Sta...Board of Supervisors Transportation Committee-Next Steps for Urban Street Sta...
Board of Supervisors Transportation Committee-Next Steps for Urban Street Sta...
 
Route 1 Multimodal Alternatives Analysis Status Update: Sept. 17, 2013
Route 1 Multimodal Alternatives Analysis Status Update: Sept. 17, 2013Route 1 Multimodal Alternatives Analysis Status Update: Sept. 17, 2013
Route 1 Multimodal Alternatives Analysis Status Update: Sept. 17, 2013
 
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
 
Interstate 66 Corridor Improvements
Interstate 66 Corridor ImprovementsInterstate 66 Corridor Improvements
Interstate 66 Corridor Improvements
 
Policy on Level of Service in Activity Centers
Policy on Level of Service in Activity CentersPolicy on Level of Service in Activity Centers
Policy on Level of Service in Activity Centers
 
Stormwater and Wastewater Consolidation
Stormwater and Wastewater Consolidation Stormwater and Wastewater Consolidation
Stormwater and Wastewater Consolidation
 

Similar to Silver Line Phase 1 Status Report

Dulles Metrorail Silver Line Phase 2 Update
Dulles Metrorail Silver Line Phase 2 UpdateDulles Metrorail Silver Line Phase 2 Update
Dulles Metrorail Silver Line Phase 2 UpdateFairfax County
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationFairfax County
 
Silver Line Update: December 1, 2015
Silver Line Update: December 1, 2015Silver Line Update: December 1, 2015
Silver Line Update: December 1, 2015Fairfax County
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...Fairfax County
 
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...Fairfax County
 
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...Fairfax County
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects UpdateTownofAddison
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Fairfax County
 
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018Fairfax County
 
Transportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesTransportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesFairfax County
 
Transportation Priorities Plan Future Updates
Transportation Priorities Plan Future UpdatesTransportation Priorities Plan Future Updates
Transportation Priorities Plan Future UpdatesFairfax County
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationFairfax County
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Fairfax County
 
Silver Line Update - Feb. 12, 2016
Silver Line Update - Feb. 12, 2016Silver Line Update - Feb. 12, 2016
Silver Line Update - Feb. 12, 2016Fairfax County
 
Update on Reston Development and Transportation Projects
Update on Reston Development and Transportation ProjectsUpdate on Reston Development and Transportation Projects
Update on Reston Development and Transportation ProjectsFairfax County
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project: Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project: Silver Line Phase 2 ImplementationFairfax County
 
Status Report on the Columbia Pike Streetcar and Preview of Upcoming Decisions
Status Report on the Columbia Pike Streetcar and Preview of Upcoming DecisionsStatus Report on the Columbia Pike Streetcar and Preview of Upcoming Decisions
Status Report on the Columbia Pike Streetcar and Preview of Upcoming DecisionsFairfax County
 
159197331 presentation-on-work-hour-exemptions
159197331 presentation-on-work-hour-exemptions159197331 presentation-on-work-hour-exemptions
159197331 presentation-on-work-hour-exemptionspeggydrouet
 
Burke Road Corridor Community Meeting : June 18, 2018
Burke Road Corridor Community Meeting : June 18, 2018Burke Road Corridor Community Meeting : June 18, 2018
Burke Road Corridor Community Meeting : June 18, 2018Fairfax County
 

Similar to Silver Line Phase 1 Status Report (20)

Dulles Metrorail Silver Line Phase 2 Update
Dulles Metrorail Silver Line Phase 2 UpdateDulles Metrorail Silver Line Phase 2 Update
Dulles Metrorail Silver Line Phase 2 Update
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
 
Silver Line Update: December 1, 2015
Silver Line Update: December 1, 2015Silver Line Update: December 1, 2015
Silver Line Update: December 1, 2015
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
 
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
 
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects Update
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
 
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
 
Transportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesTransportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future Updates
 
Transportation Priorities Plan Future Updates
Transportation Priorities Plan Future UpdatesTransportation Priorities Plan Future Updates
Transportation Priorities Plan Future Updates
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
 
Silver Line Update - Feb. 12, 2016
Silver Line Update - Feb. 12, 2016Silver Line Update - Feb. 12, 2016
Silver Line Update - Feb. 12, 2016
 
Update on Reston Development and Transportation Projects
Update on Reston Development and Transportation ProjectsUpdate on Reston Development and Transportation Projects
Update on Reston Development and Transportation Projects
 
State of the City of Norman
State of the City of NormanState of the City of Norman
State of the City of Norman
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project: Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
 
Status Report on the Columbia Pike Streetcar and Preview of Upcoming Decisions
Status Report on the Columbia Pike Streetcar and Preview of Upcoming DecisionsStatus Report on the Columbia Pike Streetcar and Preview of Upcoming Decisions
Status Report on the Columbia Pike Streetcar and Preview of Upcoming Decisions
 
159197331 presentation-on-work-hour-exemptions
159197331 presentation-on-work-hour-exemptions159197331 presentation-on-work-hour-exemptions
159197331 presentation-on-work-hour-exemptions
 
Burke Road Corridor Community Meeting : June 18, 2018
Burke Road Corridor Community Meeting : June 18, 2018Burke Road Corridor Community Meeting : June 18, 2018
Burke Road Corridor Community Meeting : June 18, 2018
 

More from Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 

More from Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Recently uploaded

Mitochondrial Fusion Vital for Adult Brain Function and Disease Understanding...
Mitochondrial Fusion Vital for Adult Brain Function and Disease Understanding...Mitochondrial Fusion Vital for Adult Brain Function and Disease Understanding...
Mitochondrial Fusion Vital for Adult Brain Function and Disease Understanding...The Lifesciences Magazine
 
14042024_First India Newspaper Jaipur.pdf
14042024_First India Newspaper Jaipur.pdf14042024_First India Newspaper Jaipur.pdf
14042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Emerging issues in migration policies.ppt
Emerging issues in migration policies.pptEmerging issues in migration policies.ppt
Emerging issues in migration policies.pptNandinituteja1
 
Power in International Relations (Pol 5)
Power in International Relations (Pol 5)Power in International Relations (Pol 5)
Power in International Relations (Pol 5)ssuser583c35
 
15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
11042024_First India Newspaper Jaipur.pdf
11042024_First India Newspaper Jaipur.pdf11042024_First India Newspaper Jaipur.pdf
11042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Geostrategic significance of South Asian countries.ppt
Geostrategic significance of South Asian countries.pptGeostrategic significance of South Asian countries.ppt
Geostrategic significance of South Asian countries.pptUsmanKaran
 
lok sabha Elections in india- 2024 .pptx
lok sabha Elections in india- 2024 .pptxlok sabha Elections in india- 2024 .pptx
lok sabha Elections in india- 2024 .pptxdigiyvbmrkt
 
13042024_First India Newspaper Jaipur.pdf
13042024_First India Newspaper Jaipur.pdf13042024_First India Newspaper Jaipur.pdf
13042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
12042024_First India Newspaper Jaipur.pdf
12042024_First India Newspaper Jaipur.pdf12042024_First India Newspaper Jaipur.pdf
12042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Transforming Andhra Pradesh: TDP's Legacy in Road Connectivity
Transforming Andhra Pradesh: TDP's Legacy in Road ConnectivityTransforming Andhra Pradesh: TDP's Legacy in Road Connectivity
Transforming Andhra Pradesh: TDP's Legacy in Road Connectivitynarsireddynannuri1
 
Foreign Relation of Pakistan with Neighboring Countries.pptx
Foreign Relation of Pakistan with Neighboring Countries.pptxForeign Relation of Pakistan with Neighboring Countries.pptx
Foreign Relation of Pakistan with Neighboring Countries.pptxunark75
 
Political-Ideologies-and-The-Movements.pptx
Political-Ideologies-and-The-Movements.pptxPolitical-Ideologies-and-The-Movements.pptx
Political-Ideologies-and-The-Movements.pptxSasikiranMarri
 
16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdfFIRST INDIA
 

Recently uploaded (14)

Mitochondrial Fusion Vital for Adult Brain Function and Disease Understanding...
Mitochondrial Fusion Vital for Adult Brain Function and Disease Understanding...Mitochondrial Fusion Vital for Adult Brain Function and Disease Understanding...
Mitochondrial Fusion Vital for Adult Brain Function and Disease Understanding...
 
14042024_First India Newspaper Jaipur.pdf
14042024_First India Newspaper Jaipur.pdf14042024_First India Newspaper Jaipur.pdf
14042024_First India Newspaper Jaipur.pdf
 
Emerging issues in migration policies.ppt
Emerging issues in migration policies.pptEmerging issues in migration policies.ppt
Emerging issues in migration policies.ppt
 
Power in International Relations (Pol 5)
Power in International Relations (Pol 5)Power in International Relations (Pol 5)
Power in International Relations (Pol 5)
 
15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf
 
11042024_First India Newspaper Jaipur.pdf
11042024_First India Newspaper Jaipur.pdf11042024_First India Newspaper Jaipur.pdf
11042024_First India Newspaper Jaipur.pdf
 
Geostrategic significance of South Asian countries.ppt
Geostrategic significance of South Asian countries.pptGeostrategic significance of South Asian countries.ppt
Geostrategic significance of South Asian countries.ppt
 
lok sabha Elections in india- 2024 .pptx
lok sabha Elections in india- 2024 .pptxlok sabha Elections in india- 2024 .pptx
lok sabha Elections in india- 2024 .pptx
 
13042024_First India Newspaper Jaipur.pdf
13042024_First India Newspaper Jaipur.pdf13042024_First India Newspaper Jaipur.pdf
13042024_First India Newspaper Jaipur.pdf
 
12042024_First India Newspaper Jaipur.pdf
12042024_First India Newspaper Jaipur.pdf12042024_First India Newspaper Jaipur.pdf
12042024_First India Newspaper Jaipur.pdf
 
Transforming Andhra Pradesh: TDP's Legacy in Road Connectivity
Transforming Andhra Pradesh: TDP's Legacy in Road ConnectivityTransforming Andhra Pradesh: TDP's Legacy in Road Connectivity
Transforming Andhra Pradesh: TDP's Legacy in Road Connectivity
 
Foreign Relation of Pakistan with Neighboring Countries.pptx
Foreign Relation of Pakistan with Neighboring Countries.pptxForeign Relation of Pakistan with Neighboring Countries.pptx
Foreign Relation of Pakistan with Neighboring Countries.pptx
 
Political-Ideologies-and-The-Movements.pptx
Political-Ideologies-and-The-Movements.pptxPolitical-Ideologies-and-The-Movements.pptx
Political-Ideologies-and-The-Movements.pptx
 
16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf
 

Silver Line Phase 1 Status Report

  • 1. December 2013 Status • Overall Phase 1 Construction – 99% complete • All Station at 98% complete except Wiehle – Reston East at 99% complete • Systems work – 98% complete • Primary Focus: • Station Completion • Testing • Punch List • Wiehle garage – Complete • Punch list and site work ongoing • Record of Decision roadway improvements – 99% complete • Anticipated completion Dec. 16, 2013 • Connector bus testing at Wiehle north - Ongoing • West Falls Church rail yard: • Completion – 93% (Jan. 2014) • Sound Box Testing – Jan 2014 • Sound Box Test Plan – Under review • Public Meeting early Jan 2014 • Two noise studies / reports will be prepared – Condition 7 and 8 (SEA) • First delivery of 7000-series rail cars – Feb. 2014 (WMATA will use current fleet spare ratio to run Phase 1 service) • WMATA will provide FCDOT 30 day notice prior to start of revenue operations to allow for Connector service changes • Phase 1 project remains on budget - $ 2.906B Schedule • Substantial completion/MWAA turn-over to WMATA: • MWAA continues to work with DTP on SSCD • System testing is ongoing • Estimated passenger revenue service - date determined by WMATA when testing, training, and safe operation is achieved (WMATA has 90 days after SSCD for testing, training, and acceptance) • January 2014 Sound Box Testing WFCY Current Milestones – Past 30 Days • Regional coordination for bus service and marketing outreach ongoing • WMATA lead for Phase 1 marketing and outreach; public website: www. silverlinemetro.com • Connector conducting operation testing Wiehle Garage • Fit out activities ongoing • Phase 1 Maintenance & Land Conveyance process ongoing; “walk down” field visits ongoing for property being turned over to the county • Punch List and Testing - Ongoing 1
  • 2. December 2013 Status • Phase 2 fully into the design stage • 23 of the 43 60% design packages received • Issued for Construction packets – Starting Spring 2014 • Coordination ongoing • Town of Herndon • Adjacent Land Owners • Herndon and Innovation Center Station (south) garages • Fairfax County has committed funding for design of the parking garages. The county has entered into a Real Estate Exchange Agreement with an adjacent property owner at Innovation Center Station for an improved transit oriented development and a real estate agreement. • At Herndon staff has developed a number of concept designs • Scheduled have been developed that track completion of the garages to the completion of Phase 2 • Town Center Parkway tunnel • Final concept design received by consultant November 2013 • FCDOT submits formal request to MWAA for change order / pricing on Nov. 18, 2013 • Status of Phase 2 Bid Packages: • Packet A - rail Line, station, and systems (includes Innovation Center Station) - Awarded • Maintenance Facility • RFQI - Issued Nov. 12, 2013 • RFP – Jan. 2014 (est.) • Award – 2nd Qtr. 2014 • NTP – July 2014 • Completion Summer 2018 • MWAA’s Dulles Rail office to relocate to Herndon – Moves ongoing through Jan 17, 2014 Budget/Schedule • Cost Estimate: $3.093B • Cost Estimate with value engineering , Packet A savings, and garages funding outside the project: $2.6B • Cost to build garages in Fairfax County: $135M est. • Substantial Completion: Summer 2018 • Revenue Operations: Late 2018 Current Milestones – Past 30 Days • FTA oversight of Phase 2 under discussion - Ongoing • TIFIA process – Ongoing • Design - Ongoing 2
  • 3. December 2013 Status • Phase 2 Parking Garages (Herndon Station and Innovation Center Station) – Plan of Finance • Per MOA Counties to utilize “best efforts” to fund garages outside of project • County will construct and own the garages upon completion • Pledge parking revenue to cover financing costs: • Revenue generated from the two parking garages • Surcharge revenue from the County garages currently in the WMATA System • County and WMATA working on a revised surcharge agreement • Legal changes will require WMATA and Board of Supervisor approval (Winter/Spring 2014) 3
  • 4. December 2013 Greensboro Station - Looking east with Route 7 on the left; the sidewalk and curb & gutter construction is complete and the balance of the site work is nearing completion. Photo courtesy Stephen Barna, DCMP. 4
  • 5. December 2013 Wiehle-Reston East Station south pedestrian pavilion with completed Metro entrance pylon. Completed Wiehle south bus lane/bays is to the right of the Metro pylon. Photo courtesy Stephen Barna, DCMP. 5