OPS Forum SMA Validation PtII 15.08.2008

Loading...

Flash Player 9 (or above) is needed to view presentations.
We have detected that you do not have it on your computer. To install it, go here.

0 comments

Post a comment

    Post a comment
    Embed Video
    Edit your comment Cancel

    Favorites, Groups & Events

    OPS Forum SMA Validation PtII 15.08.2008 - Presentation Transcript

    1. The new ESTRACK Santa Maria Ground station for support of Ariane 5 launch of ATV. Head of Systems and Project Support Section
    2. The Santa Maria Station is presented by:
      • Part 1 Boris Smeds OPS-GSY
      • Overview of requirements and technical implementation
      • Specific differences compared to a conventional satellite ground station
      • Lessons learned, unexpected problems and how they were solved
      • Part 2 Gerhard Billig OPS-ONV
      • Test and validation
      • Operational concept, preparations and launch operation
    3. Requirements
      • Receive telemetry data from Ariane 5 during the launch of ATV and send to Kourou in real time.
      • Cover the passes over the Atlantic region.
      Santa Maria Azores
    4. Time scale of actual implementation.
      • April 2006: Site Inspection
      • June 2006: SoW for antenna and related equipment. ITT
      • September 2006: PDR for antenna, TM system and power plant
      • November 2006: CDR for antenna and TM system
      • March 2007: Start of Factory Acceptance Tests
      • April 2007: Shelter and TM equipment installation at Santa Maria
      • July 2007: Commissioning of Powerplant
      • October 2007: Start of antenna commissioning at Santa Maria
      • December 2007 / January 2008: Antenna fully validated for AR5
    5. Station system overview
    6. X-band option
      • To allow reception of Earth observation satellites in the 8025-8400 MHz band the antenna is equipped with a dual feed and dichroic sub-reflector.
    7. Major differences compared to satellite RF-links
      • Dual frequency transmission. One antenna on each side of the spinning launcher
      • Telemetry modulation: frequency shift (not CCSDS) , no remnant carrier. 1 Mbps
      • No Kepler orbit during launcher propulsion phase. Continuous position updates that may have large errors.
      • High angular velocity due to close distance ( 180 km , 7 km/s)
      • Communication using HDLC protocol
      • ISDN and Inmarsat satellite link to Kourou
    8. Existing concrete platform
    9. Equipment shelter and Telemetry kit
      • Reuse existing design of TM-kit developed for Ariane tracking network by Carlo Gavazzi Space
    10. Calibration tower
      • Guests on existing tower at Pico Alto
    11. Antenna supplied by Indra Espacio. Assembly at factory.
      • Partly new design. 5.5 m dish, Carbon fibre
    12. Antenna installed at Santa Maria
      • X-Y mount (no singularity at zenith)
      Inmarsat antenna Radio link to calibration tower
    13. Murphy’s law
      • If anything can go wrong, it will.
    14. Filters required to reject UMTS ( mobile phone )
      • Filters supplied from US company.
      • Delayed delivery due to ITAR
      Receive band
    15. Unexpected problems, wrong paint.
      • Glossy paint was used on the reflector. Feed cover burnt when pointing to the sun during G/T tests.
      • Repainting of reflector required
    16. Unexpected problems, autotrack patterns
      • Error in computer simulation of antenna pattern for the autotrack feed. Actual pattern gave larger angular offset than expected.
      Original feed design
    17. Unexpected problems, autotrack patterns
      • Computer simulation
    18. Antenna tracking pattern measured Error signal
    19. New feed
      • New feed design solved the issue.
      • 4 lateral dipoles closer together. Sum signal generated by combining signals from the lateral dipoles.
    20. Antenna tracking pattern new feed Error signal
    21. Unexpected problems, bad cables
      • RF cables after Low noise amplifier with 60 dB gain with damaged screen. ( Cut through at manufacturing and covered so not visible )
      • Caused the receive system to self oscillate at 2.2 GHz.
      Leaking cable
    22. Unexpected problems. RFI from microwave link
      • Microwave links at Azores used the same frequencies as foreseen for Ariane 5.
      • Local coordination possible. Microwave links could move to other frequencies.
    23. Unexpected problems. Broken RF cables.
      • Cables from antenna are passing over a cable chain that is bent up to 180 degree each pass.
      • Selected coax cables had solid centre conductor not suitable for repeated bending.
      • Cables replaced , first temporary with RG223 available on site.
      • After AR5 support replaced to RG214 High Flex cables.
    24. Servo system not optimised
      • Large pointing errors when tracking moving targets.
      • Servo system software corrected
    25. Rough climate conditions.
      • Rust
      • Replace bolts with better quality, and repaint
    26. Useful tool for maintenance
    SlideShare Zeitgeist 2009

    + ESA/ESOC & OPS TeamESA/ESOC & OPS Team Nominate

    custom

    161 views, 0 favs, 0 embeds more stats

    This seminar will provide an overview of the new ES more

    More info about this document

    © All Rights Reserved

    Go to text version

    • Total Views 161
      • 161 on SlideShare
      • 0 from embeds
    • Comments 0
    • Favorites 0
    • Downloads 1
    Most viewed embeds

    more

    All embeds

    less

    Flagged as inappropriate Flag as inappropriate
    Flag as inappropriate

    Select your reason for flagging this presentation as inappropriate. If needed, use the feedback form to let us know more details.

    Cancel
    File a copyright complaint
    Having problems? Go to our helpdesk?

    Categories