A Presentation on the Regulatory Regime for Renewable Energy Projects in Andhra Pradesh - Presentation Transcript
A Presentation on Regulatory Regime for Renewable Energy Projects in Andhra Pradesh
In respect of NCE:
Role of the State Commissions
National Electricity Policy
Tariff Policy notified by GoI
State Government Policy
Promotional measures taken by APERC
Salient features of NCE Tariff Order Dt. 20-03-2004
In this Presentation
Section 86(1)(e) of the Electricity Act, 2003 mandates the Commission to promote Generation and Co-generation of electricity from Renewable sources –
by providing suitable measures for connectivity with the grid, and
sale of electricity to any person, and also
specify a percentage of the total consumption of electricity in the area of a distribution licensee.
Role of the State Commissions in respect of NCE under Electricity Act 2003
Role of the State Commissions in respect of NCE under Electricity Act 2003 (contd..)
While specifying Terms and Conditions for determination of tariff under Section 61 of the Act, the Commission shall inter-alia be guided, by the requirements of promotion of co-generation and generation of electricity from renewable sources of energy
Feasible potential to be exploited fully (5.2.20)
Encourage private sector participation (5.2.20)
Efforts need to be made to reduce the capital cost of NCE projects (5.12.1)
Promotional measures to be taken for development of technologies (5.12.1)
Share of NCE to be increased progressively (5.12.2)
Purchase of NCE by DISCOMS shall be through competitive bidding process (5.12.2)
Commission may determine appropriate differential in prices to promote NCE technologies
National Electricity Policy
Minimum percentage of NCE purchase U/S 86 (1) (e) of the Act to be fixed taking into account.
availability of such resources in the region.
impact on retail tariffs.
Specified percentage for NCE purchase to be made applicable for the tariff to be determined by the State Commissions effective from April, 2006 onwards.
Preferential tariffs to be determined by the SERCs till NCE technologies can compete with conventional sources.
Tariff Policy
Future procurement through competitive bidding process (U/S 63) within same type of NCEs.
Central Commission to lay down guidelines within three months for pricing of non-firm power when purchased not through competitive bidding.
Tariff Policy (Contd..)
State Government policy on NCE [ G.O.Ms.No.93 dated 18-11-1997] (Valid for 3 years)
Power Purchase Price Rs.2.25 with 5% annual escalation with 1997-1998 as the Base year (Base year changed to 1994-95 by the Commission in its Order dated 20-06-2001)
Wheeling Charges 2% (sub-judice)
3 rd Party Sales Allowed at a tariff not lower than HT Tariff of APSEB
Banking Allowed up to 12 months
Banking Charges 2%
Re-use of banked energy
(a) Captive Consumers Throughout the year
(b) Third Party Sales August – March
Renewable Power Purchase Obligation (RPPO) order dated 27-09-2005 issued by the Commission U/s 86(1)(e) of Electricity Act, 2003.
Certain Incentives / reliefs were permitted by the Commission in the matter of Open Access phasing, Cross-subsidy Surcharge etc., for NCE Developers.
Tariff rationalization has been done to achieve overall efficiency in the NCE generation and usage.
Promotional measures undertaken by APERC
Highlights of RPPO Order Dated 27-09-2005
This obligation applied to all - Distribution licensees, Captive Power users (set aside; under re-examination), Open Access Consumers
Percentage specified : 5% for three years viz., 2005-06 to 2007-08
0.5% out of the above reserved for wind based energy.
Mandatory purchase from all the NCEs with PPAs consented by the Commission as on 27-09-2005 to confer regulatory certainty even if consequently the minimum percentage specified increases.
Provision to purchase from other distribution licensee(s), at weighted average cost of the purchase provided, thus sending a right signal to site generation where it is optimally feasible.
Highlights of RPPO Order Dated 27-09-2005
The tariffs determined in the Commission’s order dated 20-03-2004 as amended shall be the ceiling tariffs.
Failure to comply with this obligation attracts penal provisions of Section 142 of the Act.
Money secured through penalization to be used for promotion of co-generation and renewables besides conservation of electricity.
Must-run status conferred on NCE projects
Consumers availing of power from NCE projects are allowed open access without being subjected to phasing as per the contracted capacity applicable for conventional energy.
Relief of 50% on cross-subsidy surcharge to those availing open access from NCE projects.
Other Incentives provided by the Commission
Banking facility for Mini-Hydel and Wind-based projects:
1. Banking allowed during all the 12 months.
2. Drawals are subject to the following:
(a). The banking year shall be from January to December.
(b). The banking charges shall be in kind @2% of the energy delivered at the point of injection.
(c). Drawals shall be permitted only during the 6 month period, from July to December.The banked energy remaining unutilized as on 31 st December shall be treated as lapsed.
(d). Drawal of banked energy during the peak hours i.e 06:00 to 09:00 hours and 18:00 hours to 21:00 hours shall not be permitted.
Other Incentives provided by the Commission
Rationalization of NCE tariffs through cost-reflective tariffs with due regard for the promotion by allowing suitable incentives.
Tariff determination for qua-class against project- wise tariffs
Two-tier tariff as against single-part tariff except for wind power and municipal waste projects.
Threshold PLF for full fixed cost recovery :
Biomass power plants - 80%
Bagasse based co-gen - 55%
Mini Hydel - 35%
Salient features of NCE Tariff Order Dated 20-03-2004
Incentive of 25 paise / unit after threshold PLF.
Variable cost determined based on market rates for fuel with escalation thereon.
Debt-equity ratio of 70:30.
Return on equity at 16% is provided in spite of decling interest rates to provide promotional impetus.
Accelerated depreciation allowed to facilitate loan repayments.
Exemption from Merit Order requirements.
Salient features of NCE Tariff Order Dated 20-03-2004 (contd..)
Tariff determination for Biomass Plants FIXED COST
Explanation in respect of Depreciation : From the date of commissioning till the depreciation accumulates to 70% of the project cost. The balance depreciation of 20% of the project cost will be allowed every year equally for the balance period of the PPA so that the total depreciation allowed for the project does not exceed 90% of the project cost
VARIABLE COST Note :- This tariff is also applicable to Industrial Water Based Projects
Tariff determination for Bagasse Based Co-generation Plants FIXED COST
Explanation in respect of Depreciation :- From the date of Commissioning till the depreciation accumulates to 70% of the project cost. The balance depreciation of 20% of the project cost will be allowed every year equally for the balance period of the PPA so that the total depreciation allowed for the project does not exceed 90% of the project cost.
Tariff fixation for Mini-Hydel Projects
* To match the loan repayment profile for the first ten years; the balance depreciation is spread over for the life of the project.
** As revised in the Order dated 07.07.2004 on R.P.No.5/2004 and R.P.No.12/2004.
(#) As per G.O.Ms.No.39 dated 02.04.2002 Royalty payable is a pass – through and to be paid to the Government directly by APTRANSCO and DISCOMs.
Tariff fixation for Mini-Hydel Projects (contd..)
* .
Tariff fixation for Municipal Waste based Projects and Wind Electricity Generating Plants: Base unit price of Rs.2.25 as on 01.04.1994 and a simple escalation of 5% per annum thereafter.
* .
INSTALLED CAPACITY OF NCES IN A.P (As on 31.03.2007):
0 comments
Post a comment