SlideShare a Scribd company logo
1 of 5
Download to read offline
International Journal of Engineering Inventions
ISSN: 2278-7461, www.ijeijournal.com
Volume 1, Issue 6 (October2012) PP: 01-05


        Analysis of Casting Defects and Identification of Remedial
                     Measures – A Diagnostic Study
                      Dr D.N. Shivappa1, Mr Rohit2, Mr. Abhijit Bhattacharya3
1
    Professor, Mechanical Engineering Department, Sir MV Institute of Technology, Bangalore Karnataka India.
     2
       M Tech Student, Mechanical Engineering Department, Sir MV Institute of Technology, Bangalore India
                   3
                     Head Operations, Dakshin Foundry Pvt. Ltd, Bangalore Karnataka India.


Abstract––Paper presents analysis of casting defects and identification of remedial measures carried out at Dakshin
Foundry Ltd, Bangalore, India. Diagnostic study carried out on Trunion Support Bracket (TSB) Castings revealed that
the contribution of the four prominent defects in casting rejections are sand drop, blow hole, mismatch, and oversize. It
was noticed that these defects are frequently occurring at particular locations. Systematic analyses were carried out to
understand the reasons for defects occurrence and suitable remedial measures were identified. Outcome of the validation
trials showed substantial reduction in rejection of castings. Company has accepted the remedial measures and
incorporated them in the standard operating procedure.

                                             I.          INTRODUCTION
           Dakshin Foundry is facing casting rejections due to some chronic defects, after observing six months’ data of the
company the most frequently rejected castings identified were TSB, Converter Housing, and Gear Housing. Out of these
three castings TSB casting was identified as most severely affected casting, hence it was considered for detail investigation.
The work on Quality Improvement of castings was carried out in following steps.
          Identification of defects in the TSB casting and analysis
          Selection of most chronic defects which frequently occurred and carried out the analysis.
          Identification of root causes and finding the remedial measures.
          Production trials in the company with the remedial measures and validation.

            II.           IDENTIFICATION OF CASTING DEFECTS AND ANALYSIS
          The frequently rejected castings identified at Dakshin Foundry are Trunion Support Bracket (TSB), Converter
Housing, Gear Housing etc. TSB casting comprises 15-20 percent of total production of the company. The number of
castings produced in the month of June 2010 and their weight, quantity and cost per kg are given in Table 1. As the
production of TSB is maximum and its cost of rejection is highest this casting was considered for detail study. TSB casting is
having defects such as sand drop, blow hole, shrinkage, mismatch, sand fusion, core shift, parting line leak, oversize, flash,
mould not filled, cold shut etc. The data observation of defects in TSB for six months period from June 2010 to Dec 2010 is
plotted as Pareto Chart shown in Figure 1. It may be noticed that the most occurring casting defects are Sand drop, Blow
holes, Mismatch, and Oversize hence they were picked up for diagnostic study. To understand the reason for causes of these
four defects a detail study was carried out in foundry.

                       III.          PRODUCTION PROCESS OF TSB CASTING
         Photograph of the TSB casting is shown in Figure 2. Details of sand systems used for mould and core making are
explained hereunder [1], [2].

Sand System used for Mould making:
Sand: Silica sand 98.5 %
Binder: Urea Furan Resin 1% of sand
Catalyst: 0.5% of resin
Silica sand comprises 85% reclaimed sand and 15% new sand with AFS number 45 to 55, clay content 0.27% (max), and
moisture 0.5% (max). Mixing of sand and binder along with catalyst is done in 20 tonne mixer for 3 to 4 minutes.

Sand System used for Core making:
Four cores are used in TSB casting, these are central core, breaker core, U cut core, flat core.
Sand system used for central core, U cut core, breaker core are;
Sand: Silica sand 98.5 %
Binder: Urea Furan Resin 1% of sand
Catalyst: 0.5% of resin
Sand system used for flat core are;
Sand: Silica sand 96.5 %
Binder: Sodium silicate 3.5 %


                                                                                                                            1
Analysis of Casting Defects and Identification of Remedial Measures...

           For all the cores fresh silica sand is used, in case of resin bonded core the sand system is prepared as explained
above for moulding sand system. And for sodium silicate – Co2 sand system mixing of fresh silica sand and sodium silica is
done in mixer for 3 minutes. Soon after the mixing core sand mix is taken to core box and adequately rammed, after the
ramming Co2 gas is passed into core box for 60 seconds. After the moulds and cores are cured, and securing them properly
the molten metal is poured and allowed to solidify. After 8 hours of pouring shakeout of casting is done and processed
further. Inspection of casting is done at different stages as per the requirement [2].
Chemical constituents of TSB casting are: Fe 92-94%, C 3.20-3.60%, Si 2.20-2.60%, Mn 0.60%, P 0.05%, S0.015%, Mg
0.025-0.050%, etc.

         IV.           CASTING DEFECTS ANALYSIS AND REMEDIAL MEASURES
           Analysis for causes of most frequently occurring four defects of TSB casting are carried out. The reason for
occurrence of these defects and their remedial measure are briefly given in Table 2. Due to nature of defects they were
analysed by observation in the shop-floor for quite a long period and assessed. Wisdom of the experts in the company and
long experience of the authors in the field of foundry technology has helped in identifying the nature of causes. Repeated
trials were carried out in the foundry to arrive at appropriate remedial measures.

                       V.           VALIDATION WITH PRODUCTION TRIALS
           Production trials on TSB casting were carried out in the company after incorporating the remedial measures
identified and reported in section 4 above. There is a substantial improvement in quality resulting in reduction in rejection
levels of castings, details are given in Table 3. For the purpose of comparison four months data of TSB Casting before
implementation of remedial is compared with four months data after implementation of remedial measure, details of
validation trials are presented here below. And it is noted that number of TSB castings produced during these four months
period are; 2657 and 2730 respectively of the years 2010 and 2011. Since difference in production quantity is only about
2.7% it is considered as same for the purpose of comparisons of rejection quantity before and after implementation of
remedial measure.

(i) Remedial measure trial for sand drop defect
          As reported Table 2 loose sand at chill and moulds interface left un-cleaned at long member that was resulting in
sand drop in this location. This was happening due to carelessness of operators. Strict instructions were given to the
operators for ensuring the proper cleaning of moulds before closing and not cleaning the mould when two moulds are near.
That suggestion is also revised in mould making checklist. By proper monitoring of cleaning moulds before closing, it was
observed that before remedial measure 52 castings were rejected due to sand drop found around long member but after
implementation of remedial measure only 18 castings were rejected during four months period. The reduction in castings
rejection was observed as 65.4%.

The second reason for rejection of TSB casting due to sand drop found around square pad area. Due to sleeve top hole, the
sand enters through sleeves and gets collected around the bottom of surface of top and bottom pad. Here also improper
cleaning of sleeve hole was reason for rejection due to sand drop. The remedial measure taken was to cover the sleeve top
hole by paper and clean the hole by air blowing and remove the paper before pouring. After implementation of this small
correction, castings rejection reduced by 75.6%, details are given in Table 3.

Core oversize and core end broken were also found responsible for rejections of TSB casting, due to these reason sand drop
observed around cross member. To overcome the problem loose piece design modified in core box, and also two pads were
provided at the bottom face of core. The remedial measure implemented and observed the rejections data for last four month
which showed 84.6% reduction in rejections.

(ii) Remedial measure trial for blow-hole defect
          To overcome the TSB casting rejections due to blow holes observed at chill interface area the position of flow offs
in gating design was modified. The placement of flow offs at the right position in gating system was very difficult but after
taking 3 to 4 trials and observation, it was found that the correct position of flow offs on the top surface of long member
only. This change brought down the rejection level by 67%.

(iii) Remedial measure trial for mismatch defect
          The inadequate numbers of locators were found to be responsible for mismatch of TSB casting. Initially only three
metallic locators were placed to locate bottom and top mould, but in order to resist mould or core movement some more
locators were required. At the time of trials the mounting of extra number of locators was found difficult. During first trial
only two locators were mounted in diagonally opposite direction, but this concept didn’t show much improvement. Then in
second trial three locators were placed in a triangular manner, the two locators were placed on a single line and third
opposite side of the line. There are three cavities provided at the pattern and three self sand mould locators build for the
cavity. Now the six locators (metallic and self sand) are used to overcome the problem of mismatch. The four month
rejection data shows that before remedial measure the rejections were 43 castings due to mismatch but after remedial
measures only 7 castings rejected, which show 83.7% improvement in mismatch.

(iv) Remedial measure trial for oversize problem


                                                                                                                            2
Analysis of Casting Defects and Identification of Remedial Measures...

          Oversize of casting was another reasons for rejection of TSB casting. Due to mould bulging and mould lift
oversize of castings used to take place. This was happening due to improper clamping of moulds. Initially in the first trial
only c- channel clamp was provided at sideways. But it was found that this measure was not suitable to control mould
bulging at centre. Then in the second trial along with sideways channels an intermediate c- channel clamp was provided.
This measure reduced the casting rejection by 77%.

After confirming with four months results by adopting remedial measures and noticing the substantial quality improvement,
company accepted the measures suggested in the work. Standard operating procedures of the company were revised by
incorporating the suggested measures.

                                           VI.           CONCLUSION
          Diagnostic study carried out on TSB Castings revealed that the contribution of the four prominent defects in
casting rejections are Sand drop, Blow hole, Mismatch, and Oversize. It was noticed that these defects are frequently
occurring at particular locations. Systematic analyses were carried out to understand the reasons for defects occurrence and
the reasons identified are;
         The causes of sand drop were found due to improper cleaning of mould in the areas around chills and mould
          interface, sleeve, and breaker core.
         Blow holes occurrence around long member is due to failure to connect flow off in the gating design.
         The mismatch of castings is due to lack of locators and improper setting of cores.
         Casting oversize is due to mould lift and mould bulging.

Remedial measures identified to overcome the above defects are;
  (i)     Sand Drop: Proper cleaning of the mould before closing, ensure that sand don’t enter into the sleeve, replace no-
          bake core with shell core, provide pads at bottom face, and modified the loose piece design to avoid core crushing.
  (i)     Blow Hole: Modification of gating system; flow offs are to be directly connected on top surface of long member.
  (ii)    Mismatch: Provided six locators for proper setting of cores - three are of metallic and three are self locators.
  (iii) Oversize: Clamp the moulds properly to withstand the pouring pressure – Clamp centre channel with C-Clamps
          during metal pouring.
Production trials were carried out in the foundry for four months period by incorporating the above remedial measures and
validated. Outcome of the results showed substantial reduction in rejection of castings. Company has accepted and adopted
the remedial measures suggested in the production methods, also suitably modified the standard operating procedure.

                                                    REFERENCES
 1.      British Cast Iron Research Association, ‘BCIRA broadsheets’, BCIRA, 1986.
 2.      Apex Company (Dhakshin Foundry) Manual.
 3.      American Foundry Men’s Society, ‘Analysis of casting defects’, American Foundry Men’s Society, USA, 1974.

Acknowledgement: Authors sincerely express their gratitude to the Management and Employees of Dakshin Foundry Ltd,
Bangalore, India for their help, support, and assistance.



                            Weight                         Rejection       Cost (Rs) per      Cost of Rejection,
             Casting         (Kg)        Produc-tion       Quantity             Kg                    Rs
              Name                        Quantity
                               (A)                            (B)               (C )               (A×B×C)




          TSB                  83            748               40                99                328,680




          Converter
                              250             70               5                95.5               119,375
          Housing

         Gear
                              202             23               5                349                 96,455
         Housing
         Rs: Indian Rupe
                                     Table 1 Details of Rejected Castings in June 2010




                                                                                                                           3
Analysis of Casting Defects and Identification of Remedial Measures...



SI.                                                                                      Remedial Measure
       Defect Name      Defect Location                 Causes
No.                                                                                           (RM)


                                                                               Before closing the mould, ensure the
                                              Chill and mould interface
                      Long member                                              cleaning of mould, chill and mould
                                              not cleaned properly
                                                                               interface.

                                                                               Close the sleeve top hole by covering
                      Square pad area:        Sleeve inside loose sand not
                                                                               paper before mould closing and remove
                      Top & Bottom 40         cleaned up
                                                                               at the time of pouring.
                      mm area
1      Sand Drop      Around Breaker          Loose sand around the
                      Core                    breaker core is due to           Replace No-Bake core with Shell core
                                              improper sand ramming

                                              Core crushing while core
                                                                               Loose piece design modified
                                              setting.
                      Cross member
                                              Core end broken and fallen
                                                                               Two pads provided at the bottom face
                                              inside mould

                          Around chill        Failure to connect Flow
2       Blow Hole                                                              Flow off provided on the casting face
                         interface area       Offs

                                              Lack of locators in pattern
                                                                               Provide six locators three are metallic
3       Mismatch        Around the Bore       and improper setting of
                                                                               and three are self locator
                                              cores
                                           Improper clamping of
                                                                     Centre clamping with C-clamps
4       Oversize                           moulds, mould lift and
                                           mould bulging
                       Table 2 Major Sand Drop Location, Causes & Remedial Measure


                                                   Rejection* Before         Rejection** After
 SI.                                                                                                  Reduction in
           Defects          Defect Location               RM                        RM
 No.                                                                                               Rejection (percent)
                                                      (Quantity)                (Quantity)


                         Long member                        52                      18                     65.4


 1.     Sand Drop        Square pad area                    41                      10                     75.6


                         Cross member                       26                       4                     84.6


 2.     Blow Holes       Around chill area                  36                      12                     67.0


 3.     Mismatch         Around bore                        43                       7                     83.7

 4.     Oversize                    -                       48                      11                     77.0
                     RM: Remedial Measure, * During March – June 2010, ** During March – June2011
                            Table 3 Rejection Control after Remedial Measure




                                                                                                                         4
Analysis of Casting Defects and Identification of Remedial Measures...


                          120.0
                                                                                             97.7            100
Percentage of Rejection




                          100.0                                                 89.1
                                                               80.1
                           80.0
                                                 58.8
                           60.0

                           40.0     32.6
                                                 26.2
                                                               21.3
                           20.0                                                  9           8.6
                                                                                                              2.3
                            0.0
                                  Sand drop   Blow holes    Mismatch        Over size      Core Lift       Shrinkage
                                                                      Defects

                                              Percentage Rejection      Percentage Cummulative Rejection

                                    Figure 1 Pareto Diagram of Defects                                                 Figure 2 Photograph of TSB Casting
                                    in TSB Casting




                                                                                                                                                            5

More Related Content

What's hot

Minimization of the Casting Defects Using Taguchi’s Method
Minimization of the Casting Defects Using Taguchi’s MethodMinimization of the Casting Defects Using Taguchi’s Method
Minimization of the Casting Defects Using Taguchi’s Methodinventionjournals
 
Testing/Manufacture/Closed and open cells content
Testing/Manufacture/Closed and open cells contentTesting/Manufacture/Closed and open cells content
Testing/Manufacture/Closed and open cells contentfec2020
 
Testing/Manufacture/closed and open cells content
Testing/Manufacture/closed and open cells contentTesting/Manufacture/closed and open cells content
Testing/Manufacture/closed and open cells contentfec2020
 
Building Materials Testing - Exclusive Services for Infrastructure / Civil Se...
Building Materials Testing - Exclusive Services for Infrastructure / Civil Se...Building Materials Testing - Exclusive Services for Infrastructure / Civil Se...
Building Materials Testing - Exclusive Services for Infrastructure / Civil Se...Spectro Group of Companies
 
Manufacture of Adhesive from CIC Polymerizing Paint Waste
Manufacture of Adhesive from CIC Polymerizing Paint WasteManufacture of Adhesive from CIC Polymerizing Paint Waste
Manufacture of Adhesive from CIC Polymerizing Paint WasteIRJET Journal
 
Geos Laboratories Company Presentation
Geos Laboratories Company PresentationGeos Laboratories Company Presentation
Geos Laboratories Company PresentationIvan Seymus
 

What's hot (12)

Minimization of the Casting Defects Using Taguchi’s Method
Minimization of the Casting Defects Using Taguchi’s MethodMinimization of the Casting Defects Using Taguchi’s Method
Minimization of the Casting Defects Using Taguchi’s Method
 
Testing/Manufacture/Closed and open cells content
Testing/Manufacture/Closed and open cells contentTesting/Manufacture/Closed and open cells content
Testing/Manufacture/Closed and open cells content
 
Testing/Manufacture/closed and open cells content
Testing/Manufacture/closed and open cells contentTesting/Manufacture/closed and open cells content
Testing/Manufacture/closed and open cells content
 
Building Materials Testing - Exclusive Services for Infrastructure / Civil Se...
Building Materials Testing - Exclusive Services for Infrastructure / Civil Se...Building Materials Testing - Exclusive Services for Infrastructure / Civil Se...
Building Materials Testing - Exclusive Services for Infrastructure / Civil Se...
 
Aade 04-df-ho-21
Aade 04-df-ho-21Aade 04-df-ho-21
Aade 04-df-ho-21
 
Main report
Main reportMain report
Main report
 
Manufacture of Adhesive from CIC Polymerizing Paint Waste
Manufacture of Adhesive from CIC Polymerizing Paint WasteManufacture of Adhesive from CIC Polymerizing Paint Waste
Manufacture of Adhesive from CIC Polymerizing Paint Waste
 
Auckland Scope
Auckland ScopeAuckland Scope
Auckland Scope
 
China inspection-china quality control report
China inspection-china quality control reportChina inspection-china quality control report
China inspection-china quality control report
 
KENNY CV
KENNY CVKENNY CV
KENNY CV
 
Gypsum Products
Gypsum ProductsGypsum Products
Gypsum Products
 
Geos Laboratories Company Presentation
Geos Laboratories Company PresentationGeos Laboratories Company Presentation
Geos Laboratories Company Presentation
 

Similar to International Journal of Engineering Inventions (IJEI)

Drilling efficiency optimization at hassai site
Drilling efficiency optimization at hassai siteDrilling efficiency optimization at hassai site
Drilling efficiency optimization at hassai siteAhmad Elsir
 
IRJET- Reduction of Man Power, Cost and Power Consumption in Grits Plant
IRJET- Reduction of Man Power, Cost and Power Consumption in Grits PlantIRJET- Reduction of Man Power, Cost and Power Consumption in Grits Plant
IRJET- Reduction of Man Power, Cost and Power Consumption in Grits PlantIRJET Journal
 
Final project ppt
Final project pptFinal project ppt
Final project pptAkhil Vas
 
IRJET - Experimental Investigation of Rheological Properties of Drilling Flui...
IRJET - Experimental Investigation of Rheological Properties of Drilling Flui...IRJET - Experimental Investigation of Rheological Properties of Drilling Flui...
IRJET - Experimental Investigation of Rheological Properties of Drilling Flui...IRJET Journal
 
IRJET - Barite Sagging: Polymer Integrated Drilling Mud Design Analysis
IRJET - Barite Sagging: Polymer Integrated Drilling Mud Design AnalysisIRJET - Barite Sagging: Polymer Integrated Drilling Mud Design Analysis
IRJET - Barite Sagging: Polymer Integrated Drilling Mud Design AnalysisIRJET Journal
 
IRJET- Minimization of Casting Defects of Double Beat Valve (Bonnet)
IRJET- Minimization of Casting Defects of Double Beat Valve (Bonnet)IRJET- Minimization of Casting Defects of Double Beat Valve (Bonnet)
IRJET- Minimization of Casting Defects of Double Beat Valve (Bonnet)IRJET Journal
 
CASTING DEFECTS ANALYSIS OF SWASH PLATE (PVB10 YOKE) USING SIMULATION
CASTING DEFECTS ANALYSIS OF SWASH PLATE (PVB10 YOKE) USING SIMULATIONCASTING DEFECTS ANALYSIS OF SWASH PLATE (PVB10 YOKE) USING SIMULATION
CASTING DEFECTS ANALYSIS OF SWASH PLATE (PVB10 YOKE) USING SIMULATIONIRJET Journal
 
A Study on Cement Stabilized Conventional Waste and Marginal Material for Pav...
A Study on Cement Stabilized Conventional Waste and Marginal Material for Pav...A Study on Cement Stabilized Conventional Waste and Marginal Material for Pav...
A Study on Cement Stabilized Conventional Waste and Marginal Material for Pav...IRJET Journal
 
IRJET- Defect Analysis for Sand Casting Process (Case Study in Foundry of Kom...
IRJET- Defect Analysis for Sand Casting Process (Case Study in Foundry of Kom...IRJET- Defect Analysis for Sand Casting Process (Case Study in Foundry of Kom...
IRJET- Defect Analysis for Sand Casting Process (Case Study in Foundry of Kom...IRJET Journal
 
Application of taugchi method for optimization of dry sliding wear process pa...
Application of taugchi method for optimization of dry sliding wear process pa...Application of taugchi method for optimization of dry sliding wear process pa...
Application of taugchi method for optimization of dry sliding wear process pa...IJARIIT
 
IRJET- Self-Compacting Concrete - Procedure and Mix Design
IRJET-  	  Self-Compacting Concrete - Procedure and Mix DesignIRJET-  	  Self-Compacting Concrete - Procedure and Mix Design
IRJET- Self-Compacting Concrete - Procedure and Mix DesignIRJET Journal
 
Design and Analysis of fluid flow in AISI 1008 Steel reduction gear box
Design and Analysis of fluid flow in AISI 1008 Steel reduction gear boxDesign and Analysis of fluid flow in AISI 1008 Steel reduction gear box
Design and Analysis of fluid flow in AISI 1008 Steel reduction gear boxIRJET Journal
 
Image segmentation, Rough set Theory, Game Theory, Image processing
Image segmentation, Rough set Theory, Game Theory, Image processingImage segmentation, Rough set Theory, Game Theory, Image processing
Image segmentation, Rough set Theory, Game Theory, Image processingijsrd.com
 
Analyses of Water Contaminants Lubricated Deep Groove Ball Bearing through Vi...
Analyses of Water Contaminants Lubricated Deep Groove Ball Bearing through Vi...Analyses of Water Contaminants Lubricated Deep Groove Ball Bearing through Vi...
Analyses of Water Contaminants Lubricated Deep Groove Ball Bearing through Vi...IRJET Journal
 
Casting Defects & Remedies - A Review
Casting Defects & Remedies - A ReviewCasting Defects & Remedies - A Review
Casting Defects & Remedies - A ReviewIRJET Journal
 
Tensile and Wear Property Analysis of Friction Stir processed Metal Matrix Co...
Tensile and Wear Property Analysis of Friction Stir processed Metal Matrix Co...Tensile and Wear Property Analysis of Friction Stir processed Metal Matrix Co...
Tensile and Wear Property Analysis of Friction Stir processed Metal Matrix Co...IRJET Journal
 
The influence of Rolling process on the porosity and wear behavior of Spray-f...
The influence of Rolling process on the porosity and wear behavior of Spray-f...The influence of Rolling process on the porosity and wear behavior of Spray-f...
The influence of Rolling process on the porosity and wear behavior of Spray-f...IOSR Journals
 

Similar to International Journal of Engineering Inventions (IJEI) (20)

De4301615618
De4301615618De4301615618
De4301615618
 
Drilling efficiency optimization at hassai site
Drilling efficiency optimization at hassai siteDrilling efficiency optimization at hassai site
Drilling efficiency optimization at hassai site
 
IRJET- Reduction of Man Power, Cost and Power Consumption in Grits Plant
IRJET- Reduction of Man Power, Cost and Power Consumption in Grits PlantIRJET- Reduction of Man Power, Cost and Power Consumption in Grits Plant
IRJET- Reduction of Man Power, Cost and Power Consumption in Grits Plant
 
Final project ppt
Final project pptFinal project ppt
Final project ppt
 
IRJET - Experimental Investigation of Rheological Properties of Drilling Flui...
IRJET - Experimental Investigation of Rheological Properties of Drilling Flui...IRJET - Experimental Investigation of Rheological Properties of Drilling Flui...
IRJET - Experimental Investigation of Rheological Properties of Drilling Flui...
 
IRJET - Barite Sagging: Polymer Integrated Drilling Mud Design Analysis
IRJET - Barite Sagging: Polymer Integrated Drilling Mud Design AnalysisIRJET - Barite Sagging: Polymer Integrated Drilling Mud Design Analysis
IRJET - Barite Sagging: Polymer Integrated Drilling Mud Design Analysis
 
IRJET- Minimization of Casting Defects of Double Beat Valve (Bonnet)
IRJET- Minimization of Casting Defects of Double Beat Valve (Bonnet)IRJET- Minimization of Casting Defects of Double Beat Valve (Bonnet)
IRJET- Minimization of Casting Defects of Double Beat Valve (Bonnet)
 
DURUM WHEAT DEBRANNING - BY OCRIM
DURUM WHEAT DEBRANNING - BY OCRIMDURUM WHEAT DEBRANNING - BY OCRIM
DURUM WHEAT DEBRANNING - BY OCRIM
 
CASTING DEFECTS ANALYSIS OF SWASH PLATE (PVB10 YOKE) USING SIMULATION
CASTING DEFECTS ANALYSIS OF SWASH PLATE (PVB10 YOKE) USING SIMULATIONCASTING DEFECTS ANALYSIS OF SWASH PLATE (PVB10 YOKE) USING SIMULATION
CASTING DEFECTS ANALYSIS OF SWASH PLATE (PVB10 YOKE) USING SIMULATION
 
A Study on Cement Stabilized Conventional Waste and Marginal Material for Pav...
A Study on Cement Stabilized Conventional Waste and Marginal Material for Pav...A Study on Cement Stabilized Conventional Waste and Marginal Material for Pav...
A Study on Cement Stabilized Conventional Waste and Marginal Material for Pav...
 
IRJET- Defect Analysis for Sand Casting Process (Case Study in Foundry of Kom...
IRJET- Defect Analysis for Sand Casting Process (Case Study in Foundry of Kom...IRJET- Defect Analysis for Sand Casting Process (Case Study in Foundry of Kom...
IRJET- Defect Analysis for Sand Casting Process (Case Study in Foundry of Kom...
 
Application of taugchi method for optimization of dry sliding wear process pa...
Application of taugchi method for optimization of dry sliding wear process pa...Application of taugchi method for optimization of dry sliding wear process pa...
Application of taugchi method for optimization of dry sliding wear process pa...
 
IRJET- Self-Compacting Concrete - Procedure and Mix Design
IRJET-  	  Self-Compacting Concrete - Procedure and Mix DesignIRJET-  	  Self-Compacting Concrete - Procedure and Mix Design
IRJET- Self-Compacting Concrete - Procedure and Mix Design
 
Design and Analysis of fluid flow in AISI 1008 Steel reduction gear box
Design and Analysis of fluid flow in AISI 1008 Steel reduction gear boxDesign and Analysis of fluid flow in AISI 1008 Steel reduction gear box
Design and Analysis of fluid flow in AISI 1008 Steel reduction gear box
 
Image segmentation, Rough set Theory, Game Theory, Image processing
Image segmentation, Rough set Theory, Game Theory, Image processingImage segmentation, Rough set Theory, Game Theory, Image processing
Image segmentation, Rough set Theory, Game Theory, Image processing
 
Analyses of Water Contaminants Lubricated Deep Groove Ball Bearing through Vi...
Analyses of Water Contaminants Lubricated Deep Groove Ball Bearing through Vi...Analyses of Water Contaminants Lubricated Deep Groove Ball Bearing through Vi...
Analyses of Water Contaminants Lubricated Deep Groove Ball Bearing through Vi...
 
SPE 147856
SPE 147856SPE 147856
SPE 147856
 
Casting Defects & Remedies - A Review
Casting Defects & Remedies - A ReviewCasting Defects & Remedies - A Review
Casting Defects & Remedies - A Review
 
Tensile and Wear Property Analysis of Friction Stir processed Metal Matrix Co...
Tensile and Wear Property Analysis of Friction Stir processed Metal Matrix Co...Tensile and Wear Property Analysis of Friction Stir processed Metal Matrix Co...
Tensile and Wear Property Analysis of Friction Stir processed Metal Matrix Co...
 
The influence of Rolling process on the porosity and wear behavior of Spray-f...
The influence of Rolling process on the porosity and wear behavior of Spray-f...The influence of Rolling process on the porosity and wear behavior of Spray-f...
The influence of Rolling process on the porosity and wear behavior of Spray-f...
 

More from International Journal of Engineering Inventions www.ijeijournal.com

More from International Journal of Engineering Inventions www.ijeijournal.com (20)

H04124548
H04124548H04124548
H04124548
 
G04123844
G04123844G04123844
G04123844
 
F04123137
F04123137F04123137
F04123137
 
E04122330
E04122330E04122330
E04122330
 
C04121115
C04121115C04121115
C04121115
 
B04120610
B04120610B04120610
B04120610
 
A04120105
A04120105A04120105
A04120105
 
F04113640
F04113640F04113640
F04113640
 
E04112135
E04112135E04112135
E04112135
 
D04111520
D04111520D04111520
D04111520
 
C04111114
C04111114C04111114
C04111114
 
B04110710
B04110710B04110710
B04110710
 
A04110106
A04110106A04110106
A04110106
 
I04105358
I04105358I04105358
I04105358
 
H04104952
H04104952H04104952
H04104952
 
G04103948
G04103948G04103948
G04103948
 
F04103138
F04103138F04103138
F04103138
 
E04102330
E04102330E04102330
E04102330
 
D04101822
D04101822D04101822
D04101822
 
C04101217
C04101217C04101217
C04101217
 

International Journal of Engineering Inventions (IJEI)

  • 1. International Journal of Engineering Inventions ISSN: 2278-7461, www.ijeijournal.com Volume 1, Issue 6 (October2012) PP: 01-05 Analysis of Casting Defects and Identification of Remedial Measures – A Diagnostic Study Dr D.N. Shivappa1, Mr Rohit2, Mr. Abhijit Bhattacharya3 1 Professor, Mechanical Engineering Department, Sir MV Institute of Technology, Bangalore Karnataka India. 2 M Tech Student, Mechanical Engineering Department, Sir MV Institute of Technology, Bangalore India 3 Head Operations, Dakshin Foundry Pvt. Ltd, Bangalore Karnataka India. Abstract––Paper presents analysis of casting defects and identification of remedial measures carried out at Dakshin Foundry Ltd, Bangalore, India. Diagnostic study carried out on Trunion Support Bracket (TSB) Castings revealed that the contribution of the four prominent defects in casting rejections are sand drop, blow hole, mismatch, and oversize. It was noticed that these defects are frequently occurring at particular locations. Systematic analyses were carried out to understand the reasons for defects occurrence and suitable remedial measures were identified. Outcome of the validation trials showed substantial reduction in rejection of castings. Company has accepted the remedial measures and incorporated them in the standard operating procedure. I. INTRODUCTION Dakshin Foundry is facing casting rejections due to some chronic defects, after observing six months’ data of the company the most frequently rejected castings identified were TSB, Converter Housing, and Gear Housing. Out of these three castings TSB casting was identified as most severely affected casting, hence it was considered for detail investigation. The work on Quality Improvement of castings was carried out in following steps.  Identification of defects in the TSB casting and analysis  Selection of most chronic defects which frequently occurred and carried out the analysis.  Identification of root causes and finding the remedial measures.  Production trials in the company with the remedial measures and validation. II. IDENTIFICATION OF CASTING DEFECTS AND ANALYSIS The frequently rejected castings identified at Dakshin Foundry are Trunion Support Bracket (TSB), Converter Housing, Gear Housing etc. TSB casting comprises 15-20 percent of total production of the company. The number of castings produced in the month of June 2010 and their weight, quantity and cost per kg are given in Table 1. As the production of TSB is maximum and its cost of rejection is highest this casting was considered for detail study. TSB casting is having defects such as sand drop, blow hole, shrinkage, mismatch, sand fusion, core shift, parting line leak, oversize, flash, mould not filled, cold shut etc. The data observation of defects in TSB for six months period from June 2010 to Dec 2010 is plotted as Pareto Chart shown in Figure 1. It may be noticed that the most occurring casting defects are Sand drop, Blow holes, Mismatch, and Oversize hence they were picked up for diagnostic study. To understand the reason for causes of these four defects a detail study was carried out in foundry. III. PRODUCTION PROCESS OF TSB CASTING Photograph of the TSB casting is shown in Figure 2. Details of sand systems used for mould and core making are explained hereunder [1], [2]. Sand System used for Mould making: Sand: Silica sand 98.5 % Binder: Urea Furan Resin 1% of sand Catalyst: 0.5% of resin Silica sand comprises 85% reclaimed sand and 15% new sand with AFS number 45 to 55, clay content 0.27% (max), and moisture 0.5% (max). Mixing of sand and binder along with catalyst is done in 20 tonne mixer for 3 to 4 minutes. Sand System used for Core making: Four cores are used in TSB casting, these are central core, breaker core, U cut core, flat core. Sand system used for central core, U cut core, breaker core are; Sand: Silica sand 98.5 % Binder: Urea Furan Resin 1% of sand Catalyst: 0.5% of resin Sand system used for flat core are; Sand: Silica sand 96.5 % Binder: Sodium silicate 3.5 % 1
  • 2. Analysis of Casting Defects and Identification of Remedial Measures... For all the cores fresh silica sand is used, in case of resin bonded core the sand system is prepared as explained above for moulding sand system. And for sodium silicate – Co2 sand system mixing of fresh silica sand and sodium silica is done in mixer for 3 minutes. Soon after the mixing core sand mix is taken to core box and adequately rammed, after the ramming Co2 gas is passed into core box for 60 seconds. After the moulds and cores are cured, and securing them properly the molten metal is poured and allowed to solidify. After 8 hours of pouring shakeout of casting is done and processed further. Inspection of casting is done at different stages as per the requirement [2]. Chemical constituents of TSB casting are: Fe 92-94%, C 3.20-3.60%, Si 2.20-2.60%, Mn 0.60%, P 0.05%, S0.015%, Mg 0.025-0.050%, etc. IV. CASTING DEFECTS ANALYSIS AND REMEDIAL MEASURES Analysis for causes of most frequently occurring four defects of TSB casting are carried out. The reason for occurrence of these defects and their remedial measure are briefly given in Table 2. Due to nature of defects they were analysed by observation in the shop-floor for quite a long period and assessed. Wisdom of the experts in the company and long experience of the authors in the field of foundry technology has helped in identifying the nature of causes. Repeated trials were carried out in the foundry to arrive at appropriate remedial measures. V. VALIDATION WITH PRODUCTION TRIALS Production trials on TSB casting were carried out in the company after incorporating the remedial measures identified and reported in section 4 above. There is a substantial improvement in quality resulting in reduction in rejection levels of castings, details are given in Table 3. For the purpose of comparison four months data of TSB Casting before implementation of remedial is compared with four months data after implementation of remedial measure, details of validation trials are presented here below. And it is noted that number of TSB castings produced during these four months period are; 2657 and 2730 respectively of the years 2010 and 2011. Since difference in production quantity is only about 2.7% it is considered as same for the purpose of comparisons of rejection quantity before and after implementation of remedial measure. (i) Remedial measure trial for sand drop defect As reported Table 2 loose sand at chill and moulds interface left un-cleaned at long member that was resulting in sand drop in this location. This was happening due to carelessness of operators. Strict instructions were given to the operators for ensuring the proper cleaning of moulds before closing and not cleaning the mould when two moulds are near. That suggestion is also revised in mould making checklist. By proper monitoring of cleaning moulds before closing, it was observed that before remedial measure 52 castings were rejected due to sand drop found around long member but after implementation of remedial measure only 18 castings were rejected during four months period. The reduction in castings rejection was observed as 65.4%. The second reason for rejection of TSB casting due to sand drop found around square pad area. Due to sleeve top hole, the sand enters through sleeves and gets collected around the bottom of surface of top and bottom pad. Here also improper cleaning of sleeve hole was reason for rejection due to sand drop. The remedial measure taken was to cover the sleeve top hole by paper and clean the hole by air blowing and remove the paper before pouring. After implementation of this small correction, castings rejection reduced by 75.6%, details are given in Table 3. Core oversize and core end broken were also found responsible for rejections of TSB casting, due to these reason sand drop observed around cross member. To overcome the problem loose piece design modified in core box, and also two pads were provided at the bottom face of core. The remedial measure implemented and observed the rejections data for last four month which showed 84.6% reduction in rejections. (ii) Remedial measure trial for blow-hole defect To overcome the TSB casting rejections due to blow holes observed at chill interface area the position of flow offs in gating design was modified. The placement of flow offs at the right position in gating system was very difficult but after taking 3 to 4 trials and observation, it was found that the correct position of flow offs on the top surface of long member only. This change brought down the rejection level by 67%. (iii) Remedial measure trial for mismatch defect The inadequate numbers of locators were found to be responsible for mismatch of TSB casting. Initially only three metallic locators were placed to locate bottom and top mould, but in order to resist mould or core movement some more locators were required. At the time of trials the mounting of extra number of locators was found difficult. During first trial only two locators were mounted in diagonally opposite direction, but this concept didn’t show much improvement. Then in second trial three locators were placed in a triangular manner, the two locators were placed on a single line and third opposite side of the line. There are three cavities provided at the pattern and three self sand mould locators build for the cavity. Now the six locators (metallic and self sand) are used to overcome the problem of mismatch. The four month rejection data shows that before remedial measure the rejections were 43 castings due to mismatch but after remedial measures only 7 castings rejected, which show 83.7% improvement in mismatch. (iv) Remedial measure trial for oversize problem 2
  • 3. Analysis of Casting Defects and Identification of Remedial Measures... Oversize of casting was another reasons for rejection of TSB casting. Due to mould bulging and mould lift oversize of castings used to take place. This was happening due to improper clamping of moulds. Initially in the first trial only c- channel clamp was provided at sideways. But it was found that this measure was not suitable to control mould bulging at centre. Then in the second trial along with sideways channels an intermediate c- channel clamp was provided. This measure reduced the casting rejection by 77%. After confirming with four months results by adopting remedial measures and noticing the substantial quality improvement, company accepted the measures suggested in the work. Standard operating procedures of the company were revised by incorporating the suggested measures. VI. CONCLUSION Diagnostic study carried out on TSB Castings revealed that the contribution of the four prominent defects in casting rejections are Sand drop, Blow hole, Mismatch, and Oversize. It was noticed that these defects are frequently occurring at particular locations. Systematic analyses were carried out to understand the reasons for defects occurrence and the reasons identified are;  The causes of sand drop were found due to improper cleaning of mould in the areas around chills and mould interface, sleeve, and breaker core.  Blow holes occurrence around long member is due to failure to connect flow off in the gating design.  The mismatch of castings is due to lack of locators and improper setting of cores.  Casting oversize is due to mould lift and mould bulging. Remedial measures identified to overcome the above defects are; (i) Sand Drop: Proper cleaning of the mould before closing, ensure that sand don’t enter into the sleeve, replace no- bake core with shell core, provide pads at bottom face, and modified the loose piece design to avoid core crushing. (i) Blow Hole: Modification of gating system; flow offs are to be directly connected on top surface of long member. (ii) Mismatch: Provided six locators for proper setting of cores - three are of metallic and three are self locators. (iii) Oversize: Clamp the moulds properly to withstand the pouring pressure – Clamp centre channel with C-Clamps during metal pouring. Production trials were carried out in the foundry for four months period by incorporating the above remedial measures and validated. Outcome of the results showed substantial reduction in rejection of castings. Company has accepted and adopted the remedial measures suggested in the production methods, also suitably modified the standard operating procedure. REFERENCES 1. British Cast Iron Research Association, ‘BCIRA broadsheets’, BCIRA, 1986. 2. Apex Company (Dhakshin Foundry) Manual. 3. American Foundry Men’s Society, ‘Analysis of casting defects’, American Foundry Men’s Society, USA, 1974. Acknowledgement: Authors sincerely express their gratitude to the Management and Employees of Dakshin Foundry Ltd, Bangalore, India for their help, support, and assistance. Weight Rejection Cost (Rs) per Cost of Rejection, Casting (Kg) Produc-tion Quantity Kg Rs Name Quantity (A) (B) (C ) (A×B×C) TSB 83 748 40 99 328,680 Converter 250 70 5 95.5 119,375 Housing Gear 202 23 5 349 96,455 Housing Rs: Indian Rupe Table 1 Details of Rejected Castings in June 2010 3
  • 4. Analysis of Casting Defects and Identification of Remedial Measures... SI. Remedial Measure Defect Name Defect Location Causes No. (RM) Before closing the mould, ensure the Chill and mould interface Long member cleaning of mould, chill and mould not cleaned properly interface. Close the sleeve top hole by covering Square pad area: Sleeve inside loose sand not paper before mould closing and remove Top & Bottom 40 cleaned up at the time of pouring. mm area 1 Sand Drop Around Breaker Loose sand around the Core breaker core is due to Replace No-Bake core with Shell core improper sand ramming Core crushing while core Loose piece design modified setting. Cross member Core end broken and fallen Two pads provided at the bottom face inside mould Around chill Failure to connect Flow 2 Blow Hole Flow off provided on the casting face interface area Offs Lack of locators in pattern Provide six locators three are metallic 3 Mismatch Around the Bore and improper setting of and three are self locator cores Improper clamping of Centre clamping with C-clamps 4 Oversize moulds, mould lift and mould bulging Table 2 Major Sand Drop Location, Causes & Remedial Measure Rejection* Before Rejection** After SI. Reduction in Defects Defect Location RM RM No. Rejection (percent) (Quantity) (Quantity) Long member 52 18 65.4 1. Sand Drop Square pad area 41 10 75.6 Cross member 26 4 84.6 2. Blow Holes Around chill area 36 12 67.0 3. Mismatch Around bore 43 7 83.7 4. Oversize - 48 11 77.0 RM: Remedial Measure, * During March – June 2010, ** During March – June2011 Table 3 Rejection Control after Remedial Measure 4
  • 5. Analysis of Casting Defects and Identification of Remedial Measures... 120.0 97.7 100 Percentage of Rejection 100.0 89.1 80.1 80.0 58.8 60.0 40.0 32.6 26.2 21.3 20.0 9 8.6 2.3 0.0 Sand drop Blow holes Mismatch Over size Core Lift Shrinkage Defects Percentage Rejection Percentage Cummulative Rejection Figure 1 Pareto Diagram of Defects Figure 2 Photograph of TSB Casting in TSB Casting 5