Snecked rubble step by step

  1. 1. Snecked Rubble WallingA step-by-step guide for stonemasons Stonemasonry Department 2013
  2. 2. The aim of this presentation is to introduce you to the method of building snecked rubble walling against a block backing. By the end of the lesson you should have developed anunderstanding of the bonding arrangement and process for constructing this type of walling.
  3. 3. The first course is built using a repeating pattern of one riser followed by three levellers. Youshould see that at the stop end of each of the returns the pattern is stopped but if the wall was longer this pattern could repeat indefinately.
  4. 4. The second course consists of arrangements built between the risers of the first course. Thisarrangement will continue throughout the remainder of the wall. Between each riser there is a sneck, then a riser, then two levellers. Remember the minimum overlap is 100mm.
  5. 5. The third course is similar to the second. A sneck is followed by a riser and two levellers. Youmay find that more cuts are required on this course as you need to ensure that the bonding requirements are followed. Remember there are a maximum of three heads to a joint.
  6. 6. As you progress higher up the wall you should see that the pattern continues; sneck, riser,leveller, leveller. By this stage of the construction you should be becoming more familiar with the bonding arrangements and able to plan each course with the next course in mind.
  7. 7. The main challenge in maintaining a regular bonding arrangement is making sure the bond ismaintained at the returns. The external return in particular requires careful consideration as the external arris must always be plumbed and minimum overlap adhered to.
  8. 8. As you approach the top of the wall you should see a pattern emerging where the position ofthe risers form elongated diamond shapes. You should also notice that the courses alternate between 1/3 height stones and 2/3 height stones.
  9. 9. On the second-to-last course the risers are levelled to finished building height. Have younoticed that the risers have been arranged to form the external return? This is the simplest way of forming the return as the stones are larger and easier to keep in alignment.
  10. 10. The top course is completed entirely of snecks (or levellers). These are intended to represent the sneck, riser, leveller, leveller pattern as though they had been built and then cut to form the finished building height. Once complete you should level the top course and point the wall.
  11. 11. Developed by The Stonemasonry Department City of Glasgow College 2013

×