Deltek Insight 2012: wInsight Schedule Analysis & Reporting Features

  • 459 views
Published

With the recent and upcoming focus on schedule data, this presentation discusses wInsight’s schedule analysis capabilities with C/S Glue Viewer and DCMA Tripwire metrics as well as OMB and Format 6 …

With the recent and upcoming focus on schedule data, this presentation discusses wInsight’s schedule analysis capabilities with C/S Glue Viewer and DCMA Tripwire metrics as well as OMB and Format 6 reporting featues. Beginner Level.

Published in Technology
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Be the first to comment
    Be the first to like this
No Downloads

Views

Total Views
459
On SlideShare
0
From Embeds
0
Number of Embeds
1

Actions

Shares
Downloads
6
Comments
0
Likes
0

Embeds 0

No embeds

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
    No notes for slide

Transcript

  • 1. wInsight Schedule Analysis &Reporting FeaturesWayne Erwin, Sr. Principal Customer Care Analyst, DeltekGC-452
  • 2. Motivation for this PresentationNew customers unfamiliar with  wInsight applications  Schedule analysis and reporting capabilities that are availableRecent emphasis on schedule side of earned value reportingand analysis  Format 6 schedules  DCMA Tripwires  OMB FY11 Table IIA Report2 ©2012 Deltek, Inc. All Rights Reserved
  • 3. Scheduling Analysis & ReportingC/S Glue Viewer  View schedule data  Link schedule data to earned value data in wInsightDefense Contract Management Agency (DCMA) TripwireMetrics  BEI (Baseline Execution Index)  CPLI (Critical Path Length Index)  Start and Completion metricsOMB FY11 Table IIA Report3 ©2012 Deltek, Inc. All Rights Reserved
  • 4. C/S Glue Viewer
  • 5. C/S Glue Viewer OverviewCustomized application to  Analyze schedules  Link cost & schedule  Filter activitiesAnalyze schedule data using the Analysis Gantt ChartLink many schedule activities to one WBS elementFilter thresholds for management by exception5 ©2012 Deltek, Inc. All Rights Reserved
  • 6. Analyzing SchedulesAnalysis Gantt Chart displays schedule data related to WBSelement  Baseline  Current plan  Drop-dead dates  Consecutive slips (last 3 months projected completion date)6 ©2012 Deltek, Inc. All Rights Reserved
  • 7. Analysis Gantt Chart Baseline Current Schedule Schedule Consecutive Slips Drop-Dead Date7 ©2012 Deltek, Inc. All Rights Reserved
  • 8. Analysis Gantt Chart Legend INFORMATION SYMBOL COLOR Current Schedule (Top Bar) Critical Path Task Red Non-Critical Task Blue Summary Task Green Progress Black Baseline Schedule (Bottom Bar) Green Milestone Black, Filled-In Rolled Up Milestone Black, Hollow Drop-Dead Date (Total Slack) Red Previous Completion Dates 3 Months Ago (first slip) Green 2 Months Ago (second slip) Yellow 1 Month Ago (third slip) Red8 ©2012 Deltek, Inc. All Rights Reserved
  • 9. Linking Cost & Schedule DataAuto Sync button works as a toggleC/S Glue Viewer automatically updated when a new elementis chosen in wInsightLinking based on WBS numberFilter button must also be used9 ©2012 Deltek, Inc. All Rights Reserved
  • 10. C/S Glue Viewer FiltersFilter buttons narrow down the activities that are displayed inthe scheduleFilters only displays activities  Whose WBS number matches that of the active wInsight WBS element  That meet the threshold conditions  That are not complete10 ©2012 Deltek, Inc. All Rights Reserved
  • 11. C/S Glue Viewer FiltersDefault filter thresholdsDevelop your own management thresholds Displays Activities That Meet Any Condition Filter Slips in Past Completion Slip Float Button 4 Months Past Baseline -6 days or Red 3 31 days or more worse Yellow 2 15 to 30 days -1 to -5 days Green 1 or less 14 or less days 0 or more White Displays All Activities for the Active Element11 ©2012 Deltek, Inc. All Rights Reserved
  • 12. Schedule ProcessingExport schedule data using provided utility  Open Plan  MS Project  Primavera  Identify field containing WBS numbers that match WBS numbers in wInsightImport schedule data using C/S Glue Viewer  Identify matching wInsight contract and reporting period  Multiple schedules can be combined!Run processing functions  Update Prior Finish Dates to capture previous completion dates  Set Filter Flags to determine the Red, Yellow, and Green filters12 ©2012 Deltek, Inc. All Rights Reserved
  • 13. C/S Glue Viewer Demonstration13 ©2012 Deltek, Inc. All Rights Reserved
  • 14. DCMA Tripwire Metrics
  • 15. DCMA Schedule Tripwire Data and MetricsTripwire Data  CumActualCompl, CurPlannedStarts, Critical Path Length, Number of days of float, etc.  They are the values used in Tripwire Metrics  They are stored in the database  Most in the BEI table  Top level data is also stored in the CPR Header spreadsheet in wInsight Administrator  Can be displayed in wInsight Sort windowTripwire Metrics  Baseline Execution Index (BEI), Monthly % Hit, and Critical Path Length Index (CPLI)  They are calculations/formulas  They are not stored in the database  They are calculated at the time a chart or a report is displayed  BEIs can be displayed in wInsight Sort windowAvailability  BEI, Monthly % Hit, and related data at all levels  CPLI and related data only at level 1/total contract15 ©2012 Deltek, Inc. All Rights Reserved
  • 16. DCMA Schedule Tripwire Data CriteriaIn determining Tripwire Data totals, wInsight ignores thefollowing schedule items:  All zero (0) duration tasks, even those that are not marked as milestones  Milestones  Summary tasks  LOE tasks (level-of-effort tasks)  Tasks without a baseline  Tasks that are not mapped to WBS (i.e., no WBS# in LinkVal field in C/S Glue Viewer)16 ©2012 Deltek, Inc. All Rights Reserved
  • 17. Baseline Execution Index (BEI) Defined # of Baseline Tasks Actually Finished BEI = # of Baseline Tasks Scheduled to be FinishedIn calculating BEI data  It does not matter if tasks finish on or ahead of their baseline schedule  If a task has finished (early, on time, or late), wInsight counts itBEI can be > 1.017 ©2012 Deltek, Inc. All Rights Reserved
  • 18. Monthly % Hit Defined Monthly # of THIS month’s tasks finished on or ahead of their baseline schedule = % Hit # of THIS month’s tasks to be finished in the baseline scheduleMore stringent criteria than for the BEIMonthly % Hit cannot be > 1.018 ©2012 Deltek, Inc. All Rights Reserved
  • 19. Critical Path Length Index (CPLI) Defined Critical Path Duration + Float CPLI = Critical Path DurationSchedule Float – the difference between the amount of timeavailable for performing a program or a milestone and the timerequired to complete the program or milestonewInsight always assumes a 5-day work week in calculatingCPLICPLI of less than 1.00 indicates that the program is not likelyto achieve its baseline completion date without correctiveaction19 ©2012 Deltek, Inc. All Rights Reserved
  • 20. Program Tripwires Summary ReportIndicates whether the program is going well or poorly againstbaseline estimates20 ©2012 Deltek, Inc. All Rights Reserved
  • 21. Program Tripwires Summary Report ThresholdsSetting Tripwire Thresholds  wInsight Administrator 6.5 provides the capability to customize the secondary tripwire thresholds  wInsight Administrator > Data Input > Contracts Setup > Contracts21 ©2012 Deltek, Inc. All Rights Reserved
  • 22. BEI and Monthly % Hit ChartCompletions and Starts version of this chart  Lines = CUM Data, BEI criteria  Bars = CUR Data, Monthly % Hit criteria22 ©2012 Deltek, Inc. All Rights Reserved
  • 23. CPLI Milestone ReportIf the ProgramOrMilestone column is NULL, or says "TotalProgram" or "Milestone,“ report does not display a recordOtherwise  The milestone name, critical path length, and schedule float for the report come from the corresponding columns in the CPR Header  The UID, Start, and End dates come from imported schedule data for the milestone23 ©2012 Deltek, Inc. All Rights Reserved
  • 24. Automation of Tripwire DataDeriving Tripwire data is a 3 step process  Export schedule data using provided utility and identify LOE tasks  Import schedule data using C/S Glue Viewer  Recalculate the contract in wInsight Administrator using the Derive Tripwire Metrics option24 ©2012 Deltek, Inc. All Rights Reserved
  • 25. Recalculate & Derive Tripwire DataUse wInsight Administrator to recalculate the contract andDerive Tripwire Metrics (data)25 ©2012 Deltek, Inc. All Rights Reserved
  • 26. OMB FY11 Table IIA Report
  • 27. OMB FY 11 Exhibit 300 Table IIA ReportData was previously posted yearly, now required monthly3 Key Features  Report based on imported EVM & schedule data and a WBSOMB milestone mapping completed by the end-user  Ability to export data as a .CSV file or an .XML file from wInsight only  OMB Milestone Changes Report27 ©2012 Deltek, Inc. All Rights Reserved
  • 28. OMB FY 11 Report – Structure MappingIn wInsight Administrator  Create OMB structure and OMB elements  Use the WBS Mapper to map WBS elements to OMB elements  Load and recalculate WBS earned value data as usual  OMB Report data generated at time report is run28 ©2012 Deltek, Inc. All Rights Reserved
  • 29. OMB FY 11 Report – Example of Mapping 1000 OMB Report 3000 MS 1 MS 2 MS 33200 3400 360029 ©2012 Deltek, Inc. All Rights Reserved
  • 30. OMB FY 11 Report – Sample Change Report A blue highlighted field represents a changed value A blue highlighted row represents a new Investment30 ©2012 Deltek, Inc. All Rights Reserved
  • 31. OMB FY 11 Report – Exporting DataExporting OMB FY 11 Report data  Right-click on report  Select Export OBM Table IIA Data…  Select either  CSV  XML31 ©2012 Deltek, Inc. All Rights Reserved
  • 32. The Future
  • 33. wInsight EnhancementsNew Integrated Program Management (IPMR) requirements  CPR Format 1  Minor changes in report header  Data in XML in whole units (no decimals). Applies to Formats 1-4 and 7.  CPR Format 2  Subcontractor and Material reported separately from OBS  CPR Format 3  Time-phasing of changes between BOP and EOP  CPR Format 6  Integrated Master Schedule (IMS)  CPR Format 7  Time-phased historical & forecasted costsAvailable Q4 201233 ©2012 Deltek, Inc. All Rights Reserved
  • 34. CPR Format 6Report containing the Integrated Master Schedule (IMS)Two electronic formats required  Schedule application’s native file format (ex., .MPP file)  UN/CEFACT XML transfer file generated by schedule application  Open Plan (Deltek – Available Q4 2012)  MS Project (Steelray – Available now)  Primavera (Oracle committed to adding)C/S Glue Viewer  Updated to import Format 6 UN/CEFACT files  Database not expanded with additional fields (ex., Best/Worse duration)34 ©2012 Deltek, Inc. All Rights Reserved
  • 35. Questions?
  • 36. Thank You!