Production Tracking For Construction Contractors
Upcoming SlideShare
Loading in...5
×
 

Production Tracking For Construction Contractors

on

  • 3,741 views

Slides from production tracking for construction contractors training module.

Slides from production tracking for construction contractors training module.

Statistics

Views

Total Views
3,741
Views on SlideShare
3,733
Embed Views
8

Actions

Likes
0
Downloads
0
Comments
0

4 Embeds 8

http://www.dbrownonline.com 3
http://www.slideshare.net 3
http://museuvirtualfeb.blogspot.com.br 1
https://www.linkedin.com 1

Accessibility

Categories

Upload Details

Uploaded via as Microsoft PowerPoint

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

Production Tracking For Construction Contractors Production Tracking For Construction Contractors Presentation Transcript

  •  
  • 4 Pillars Of Productivity www.dbrownmanagement.com © 2004 by D. Brown Management /56 Factors You Typically Control
  • The Foreman’s Job – Maximize Production
    • Know what your production goal is
    • Pencil out “What-If” scenarios
    • Lay out the work clearly
    • Set short-term rewards (1-3 days)
      • “ I’ll pay you for 11 hours today if you get 160’ completed”
    • Mark-out hourly production targets on ground / plans
    • Buy some Gatorade and snacks throughout the day
    • Act in the capacity of “Head Cheerleader”
    • Save $1,000 on this task in 3 days!
    • Go back to step 1 for the next task
    www.dbrownmanagement.com © 2004 by D. Brown Management /56 9 Steps
  • Creating A Shift In Language
    • TYPICAL LANGUAGE
    • Today was really hot
    • It was a long day
    • We worked really hard today
    • Those plumbers are really getting in our way
    • The job superintendent is disorganized and skipping us all over the project
    • PRODUCTION LANGUAGE
    • We kicked ass today – it was hot as hell and a long day but we got that trench completely done and beat production by $2.15 per foot!
    • The plumbers are behind and have impacted our production in all bathrooms. It will cost us about $550 in productivity.
    • We are being moved all over the jobsite – our branch productivity dropped by $0.27 per foot.
    www.dbrownmanagement.com © 2004 by D. Brown Management /56 Common Language
  • Production Tracking The Clear Path To Profitability
  • Slides Taken From “Profit Happens Here!” Training Module Production Tracking For More Information [email_address] (916) 716-1696 www.dbrownmanagement.com © 2004 by D. Brown Management /56