Setting New Activities in
Primavera 8.2 – Duration Type
and Percent Complete
New Activity Defaults
After creating a new project and before adding
activities it is important to set the defaults such
a...
These defaults are set in the Defaults tab of the Project
Details form:
Duration Type
None of the Duration Type options affects how the
schedule calculates until one or more resources is
assigne...
If you do not plan to add resources to Activities, then
you do not need to assign a Duration Type and it may
be left as th...
Percent Complete Type
The Percent Complete type should be understood if it
is intended to be used to update (status or pro...
Activity % Complete, which may be linked to one
only of the three following % Complete fields and is
always linked to the ...
There are three percent complete options; each new
activity is assigned the project default Percent
Complete Type and then...
Therefore, for example, when the option of Physical %
Complete is selected for an activity then the Activity
% Complete an...
Eastwood Harris Supplies Project Management
Training Manuals, Project Management Training
Presentations and Consulting on ...
Upcoming SlideShare
Loading in …5
×

Setting New Activities in Primavera 8.2 – Duration Type and Percent Complete

3,712 views
3,325 views

Published on

Find out how to set up new activities in Primavera 8.2.

Published in: Business, Technology
0 Comments
1 Like
Statistics
Notes
  • Be the first to comment

No Downloads
Views
Total views
3,712
On SlideShare
0
From Embeds
0
Number of Embeds
2
Actions
Shares
0
Downloads
122
Comments
0
Likes
1
Embeds 0
No embeds

No notes for slide

Setting New Activities in Primavera 8.2 – Duration Type and Percent Complete

  1. 1. Setting New Activities in Primavera 8.2 – Duration Type and Percent Complete
  2. 2. New Activity Defaults After creating a new project and before adding activities it is important to set the defaults such as the Activity ID Numbers and Calendars. By setting them correctly before adding activities you will save a significant amount of time because you will not have to change a number of attributes against all activities at a later date.
  3. 3. These defaults are set in the Defaults tab of the Project Details form:
  4. 4. Duration Type None of the Duration Type options affects how the schedule calculates until one or more resources is assigned to an Activity. The following options are available:  Fixed Units  Fixed Duration & Units/Time  Fixed Units/Time  Fixed Duration & Units
  5. 5. If you do not plan to add resources to Activities, then you do not need to assign a Duration Type and it may be left as the default. This topic will be covered in detail in the Assigning Roles and Resources Expenses chapter.
  6. 6. Percent Complete Type The Percent Complete type should be understood if it is intended to be used to update (status or progress) the schedule. This option may be set for each activity individually in Primavera and the default for new activities is set in the Percent Complete Type drop down box. Primavera has many Activity Percent Complete fields that may be displayed in columns and we will discuss four of them now:
  7. 7. Activity % Complete, which may be linked to one only of the three following % Complete fields and is always linked to the % Complete displayed on the Gantt Chart bars:  Physical % Complete, which is independent of activity resources and durations,  Duration % Complete, which is linked to activity durations, and  Units % Complete, which is linked to resource units.
  8. 8. There are three percent complete options; each new activity is assigned the project default Percent Complete Type and then this may be edited for each activity as required.
  9. 9. Therefore, for example, when the option of Physical % Complete is selected for an activity then the Activity % Complete and the Physical % Complete are linked and a change to one will change the other and this value would be displayed on the Gantt Chart.
  10. 10. Eastwood Harris Supplies Project Management Training Manuals, Project Management Training Presentations and Consulting on Primavera P6 and Microsoft Project 2010 across Australia.

×