Your SlideShare is downloading. ×
Setting Default Percent Types in Primavera P6 Version 8.2
Upcoming SlideShare
Loading in...5
×

Thanks for flagging this SlideShare!

Oops! An error has occurred.

×
Saving this for later? Get the SlideShare app to save on your phone or tablet. Read anywhere, anytime – even offline.
Text the download link to your phone
Standard text messaging rates apply

Setting Default Percent Types in Primavera P6 Version 8.2

1,273

Published on

Find out how to set up default percent types in Primavera P6 Version 8.2.

Find out how to set up default percent types in Primavera P6 Version 8.2.

Published in: Business, Technology
0 Comments
2 Likes
Statistics
Notes
  • Be the first to comment

No Downloads
Views
Total Views
1,273
On Slideshare
0
From Embeds
0
Number of Embeds
0
Actions
Shares
0
Downloads
162
Comments
0
Likes
2
Embeds 0
No embeds

Report content
Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
No notes for slide

Transcript

  • 1. Setting Default Percent Types in Primavera P6 Version 8.2
  • 2. Default Percent Complete Type The Default Percent Complete Type for each new activity in each project is assigned in the Defaults tab of the Details form in the Project Window:
  • 3. A new activity Percent Complete Type is set to the Default Percent Complete when created and may be changed at any time.
  • 4. Percent Complete Types Physical % Complete – This field enables the user to enter the percent complete of an activity and this value is independent of the activity durations. This is similar to the way P3 and SureTrak calculates the % Complete when the Link Remaining Duration and Percent Complete option is NOT selected.
  • 5. Duration % Complete – This field is calculated from the proportion of the Original Duration and the Remaining Duration and they are linked. A change to one value will change the other. When the Remaining Duration is set to greater than the Original Duration this percent complete is always zero. This is similar to the way Primavera P3 and SureTrak calculates the % Complete when the Link Remaining Duration and Percent Complete option is selected
  • 6. Units % Complete – This is where the percent complete is calculated from the resources’ Actual and Remaining Units. A change to one value will change the other and when more than one resource is assigned then all the Actual Units for all resources will be changed proportionally. This will be covered further in the Updating Resources chapter. This is similar to the Microsoft Project % Work Complete.
  • 7. Activity % Complete The Activity % Complete field is linked to the % Complete Type field assigned to an activity in the General tab of the Details form in the Activities Window or the % Complete Type column:
  • 8. The Activity % Complete is also linked the % Complete Bar and this value is represented on the% Complete Bar.
  • 9. Eastwood Harris Supplies Project Management Training Manuals, Project Management Training Presentations and Consulting on Primavera P6 and Microsoft Project 2010across Australia. Buy the Book Now - Project Planning & Control Using Primavera P6

×