• Share
  • Email
  • Embed
  • Like
  • Save
  • Private Content
2.4 dam made disaster
 

2.4 dam made disaster

on

  • 903 views

 

Statistics

Views

Total Views
903
Views on SlideShare
903
Embed Views
0

Actions

Likes
0
Downloads
9
Comments
0

0 Embeds 0

No embeds

Accessibility

Categories

Upload Details

Uploaded via as Microsoft PowerPoint

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

    2.4 dam made disaster 2.4 dam made disaster Presentation Transcript

    • Dam builders blind to geo-hydrological risksCT.Lakshmanan
    •  Indias monsoons are legendary. Very heavy rains can come in concentrated periods, making the runoff particularly hard to manage with traditional engineered solutions. This has not prevented the Indian government from trying to use big dams, embankments, floodwalls and the like to control floodwaters. When these efforts fail, they can fail catastrophically.
    • UKAI DAM, NEAR SURAT - GUJARAT This is a story of few of those failures. Near the end of July 2006, the annual 3-4 month long monsoon had been pummeling the South Gujarat region for about a month. The first seasonal increase in the water level at the huge Ukai Dam was noticed on July 2. The dam, located about 80 km upstream from the city of Surat, was designed with adequate storage capacity (7.092 billion cubic meters when it was completed in 1972) and a comfortable flood cushion (1.332 billion cubic meters, or almost 20% of the reservoir, was intended to remain unfilled until the end of monsoon). Residents of Surat – a thriving city known for diamonds, silk textiles and interesting cuisine – should have had little to fear.
    •  But just a week into August, the most disastrous flood in the citys history hit like a runaway train. By the evening of August 8, the dam was releasing over twice the amount of water that the river downstream could carry. That carrying capacity is further reduced on high tide days, as was the case on that fateful August day. High releases continued for over four days. By the time the floods subsided, at least 120 people were dead, hundreds of others missing, over 4,000 cattle dead and more missing, and economic losses estimated at US$49 billion.
    •  What went wrong? The dams mismanagement was as wide as it was deep. First, they allowed the reservoir to fill past the allotted "flood storage" point, then waited too long to begin releasing water. Second, critical information on the carrying capacity of the Tapi River did not seem to be part of the equation of the dams water releases. And third, siltation in the reservoir had reduced the dams storage capacity. Add to this dangerous mix the fact that 21% of the live storage capacity of the reservoir was full even before the monsoon started.
    •  When we compared the Ukai reservoir levels just before the monsoon to previous years, we found that they were at their highest levels in four years. In the days before the flood, dam managers knew that especially high rains had hit the basin in recent days. They could have restored an adequate flood cushion by beginning much higher water releases on August 1. Yet releases even just two days before the flood were shockingly low. On top of all this, the authorities knew the flood cushion had shrunk from siltation, and had recommended a review of its operation. This likely would have resulted in an even greater flood cushion requirement. This was not done. The Ukai Dam story was repeated in many river basins across India in 2006, including the Mahi, Sabarmati, Chambal, Narmada, Krishna, Godavari and Mahanadi basins. Everywhere, sudden high releases of water from dams (many of them having high pre-monsoon storages) were the prime reason for most of the flood damages in these basins. And in most cases, the floods occurred less than half way through the monsoon.
    • Teesta Low dam Project (III & IV),Jalpaiguri district in North Bengal On July 27, torrential rains in Jalpaiguri district in North Bengal damaged two under construction dams (Teesta Low dam Project (TLDP) III and IV on Teesta River being built by National Hydroelectric Power Corp (NHPC). The incident has once again put the utterly poor track record of NHPC in terms of taking care of geological & hydrological risks under scanner.
    •  Earlier on July 17, a minor breach in embankment at nearby Kalijhora had swept away machineries, and should have alerted NHPC. Last year on June 25, a temporary Bailey bridge had collapsed at TLDP III HEP site near Rambhi. Seven workers had died and 17 were feared dead due to that accident.
    •  An environmental organisation North East Society for Protection Of Nature (NESPON) from Siliguri carried out a fact finding at both the sites – TLDP III near Rambhi in Kalimpong sub division and TLDP IV near Kalijhora – on July 29, and found that NHPC had failed to address geological concernsand had not carried out any slope protectivemeasures along the reservoir rim.
    •  Soumitra Ghosh of NESPON says, “Construction was started by NHPC at TLDP III near Rambhi since 2004, and at TLDP IV near Kalijhora since 2006 and all through out we witnessed rampant use of dynamite, fast denudation of existing vegetation cover at slopes on both the banks of river, while no protection activity was undertaken along the reservoir rim or potential slide zones. When a large part of NH 31 road side caved in during August 2006,opening a new slide just above TLDP III site, NHPC responded byshoddily erecting a guard wall at that particular site. Although, the environment clearance granted to the projects isbased on Environmental Impact Assessment and EnvironmentalManagement Plan that talk about giving priority to catchmentprotection work given the high siltation, NHPC has just concentratedon dam construction while nothing has been done for catchmentprotection.” CT.Lakshmanan
    •  Just one day before on July 4, 2005, a reporter working with Business Standard filed a news story on the trouble in the underground shaft tunnel of NHPC’s 280 MW Dhauliganga hydropower project, situated near Pithoragarh in Uttaranchal. Built at Rs 1500 crores, the project was scheduled for commissioning on March 31, 2005; but due to some unexplained technical reasons NHPC has postponed its commissioning several times. The trouble began when NHPC authorities released water inside 5.5 km long underground shaft tunnel to test the turbines during June. Within minutes of the trial run, Ailagarh village, situated at the higher reaches of the project got flooded, creating panic in the area due to the excessive releases of water through shaft holes.
    •  An enquiry committee set up to investigate the tunnel collapse had observed; a) Geologists had specifically brought out the necessity for taking surface protectionmeasures in the slopes where tunnel was on low cover. Possibility of the over crown beingwashed away from overburden movements over the years was foreseen. This aspect did notappear to have been taken note of by the project designers till the accident. b) The Commissioning of the project in April 1983 was preceded by a Technical AdvisoryCommittee’s meeting to finalise the filling schedule and other connected matters. There washowever, no discussion among designers, geologists and the project team on the aspect ofdesign and construction of tunnel lining in the low cover zone and no rock reaches.
    •  The hydropower industry in India seems to have become habitual in its complacency and remains unwilling to learn any lessons from the past blunders. So is there a hope to imagine a disaster free dam operations in India? Have our structural engineers internalized a lesson or two on the need of “defensive engineering” during the pre-feasibility, planning and design stage for dam projects? Explaining the term, US Dam safety expert Robert Jansen says, “dams require defensive engineering, which means listing every imaginable force that might be imposed, examination of every possible set of circumstances, and incorporation of protective elements to cope with each and every condition.”
    •  Dams in India chronically suffer from tendency to “cut corners” to make them appear cost effective and it is high time some thought is given to geological risks and hazards they pose. It is also necessary to put under the lenses the role of the central regulatory agencies like the Central Water Commission and the Central Electricity Authority that have refused to take any action against the dangerous negligence of the developers. It seems this is nobody’s baby, unlike in US, where the Federal Electricity Regularly Commission also regulates the safety of operations of the dams.