SolarWall® At Jaguar Land Rover Academy - Presentation Transcript
SolarWall®
@
The Jaguar Land Rover Technical
Academy
Jaguar Land Rover
John Vickers - Manager, Plant Engineering
Peter Phillipson – Project Engineer
Tony McGuire – Environmental Specialist
SolarWall® @ the JLR
Technical Academy
• Introduction – John Vickers
• The Jaguar Land Rover “Mission Statement”
• The Sustainability Assessment process - Tony McGuire
• SolarWall® Installation and Operation – Peter Phillipson
• Summary – John Vickers
Introduction
• Plant Engineering - who we are / what we do
• Technical Academy project objectives
• Incorporate Sustainability Engineering techniques in the
Technical Academy building refurbishment design
• An efficient / effective way of communicating with the Jaguar
Land Rover Dealership Community
• To deliver relevant and practical guidance on Sustainability to
the Dealership community
Introduction continued
• Are there better ways to achieve the project objectives?
• Does the proposal provide value for money?
• Does the project deliver against key Sustainability objectives?
How do you measure / quantify these?
Sustainability
Assessment process
• The introduction of Sustainability Assessment
• Incorporate Sustainability Engineering in building refurbishment
• Adopt a Life Cycle Thinking approach
• Improve building: Air tightness / Insulation / Thermal capacity
• Material selection important - EPDs?
• Consider Life Cycle Operational Phase CO2
• Future Energy cost escalation challenging
• Each technique used to achieve at least two objectives
• Evaluation included > 30 sustainability techniques initially
• Techniques ranked on basis of £invested and tonnes of CO2 abated
• SolarWall® helps JLR meet its objectives
Operational Phase - CO2
abatement
• A rational basis for investment
decisions
• Techniques ranked by:
• Tonnes of CO2 saved
• £k Investment
• Eco – efficiency metric:
£k invested (£k/tCO2)
Tonnes of CO2 abated a ll®
W
l ar
So
SolarWall® installation
and operation
• Installation:
• Installed approx. 300m2 of SolarWall ® onto South elevation
• Building elevation has a 21° from vertical
• Connected via ductwork and damper to internal fan unit and
distribution ‘sock’
• Operational aspects:
• Controlled via site Building Management System (Trend)
• Blends outside air and stratified hot air
• Controls temperature within workshop
• Provides minimum fresh air requirements
SolarWall® installation
and operation
Solar Wall East AHU Input Temp (March 2009) SolarWall Input East
OAT
45
40
35
30
25
Degress C
20
15
10
5
0
18/03 20/03 22/03 24/03 26/03 28/03 30/03 01/04
‐5
‐10
;
Performance will be demonstrated on the site walk around when there
will be an opportunity for technical questions.
In closing
• Future Projects
• Holistic approach to the building refurbishment challenge
• The Sustainability Assessment process
• Life Cycle Thinking Approach
0 comments
Post a comment