Laney College Athletic Field & Field House Project
Upcoming SlideShare
Loading in...5
×
 

Laney College Athletic Field & Field House Project

on

  • 1,415 views

In November 2011, the Peralta Community College District celebrated the completion of the new Design-Build, state-of-the-art, LEED® Gold Certified Athletic Field & Field House Project on the Laney ...

In November 2011, the Peralta Community College District celebrated the completion of the new Design-Build, state-of-the-art, LEED® Gold Certified Athletic Field & Field House Project on the Laney College campus in Oakland, California. This assignment is particularly significant because it is the first design/build project of any kind undertaken by the District.

Statistics

Views

Total Views
1,415
Views on SlideShare
1,047
Embed Views
368

Actions

Likes
0
Downloads
2
Comments
0

3 Embeds 368

http://www.cordobacorp.com 339
http://offline.inverselogic.net 26
http://cordobacorp.com 3

Accessibility

Upload Details

Uploaded via as Microsoft PowerPoint

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

    Laney College Athletic Field & Field House Project Laney College Athletic Field & Field House Project Presentation Transcript

    • Project Scope of Work 1 (E) 10th Street (E) 5th Street (E) Football Field Increment #2“Baseball Field” Increment #3 “Field House” Increment #1 “Parking Lot”
    • Laney College 2 Athletic Field & Field House Project Presented by: Nawar Al Juburi LEED® Green AssociateAssistant Construction Manager/Field Engineer Cordoba Corporation Northern California Regional Office 500 12th Street, Suite 330 Oakland, CA 94607
    • Background & Priority 3 Lake Merritt BART Lake Merritt StationInterstate Highway 880 Eagles North(To Downtown Football Field San Francisco ) Laney College Laney College Campus Athletic Filed & Field House Interstate Highway Peralta Community880 South (To Oakland College District Office International Airport) STRATEGIC PROJECT LOCATION
    • Project Team / Cordoba’s Role 4 Owner (PERALTA COMMUNITY COLLEGE DISTRICT) Construction Management (CORDOBA CORPORATION ) Design-Build Entity Architect of Record(GILBANE BUILDING COMPANY ) (GOULD EVANS BAUM THORNLEY, INC.)
    • Project Scope of Work 5 (E) 10th Street (E) 5th Street (E) Football Field Increment #2“Baseball Field” Increment #3 “Field House” Increment #1 “Parking Lot”
    • Inc. # 1: New Solar-Powered Parking Lot Structure 6
    • Inc. # 2: New Baseball Field 7
    • Inc. #3 Athletic Field House 8
    • First Floor- 12,000 sq.ft. 9
    • Second Floor- 5,500 sq.ft. 10
    • Final Project Cost 11 $18 Million This cost included five (5) Approved Change Orders 1.50% Unforeseen Conditions 1% E&O 2%Owner Request
    • Project Highlights 12 Completed November 2011 Design-Build LEED® Gold Certified $1.9 million Photovoltaic Collection System Minimum of 340,000 kilowatt hours per year 100% of the peak energy demand of the Field House 75% of the annual power consumption This translates into $350k in savings within the first 5 years of the buildings use