    Work Package 10 - DIssemination - Presentation Transcript

    1. WP 10 Dissemination
      CONVERGE KICK OFF MEETING BUDAPEST 2009
    2. Covered in this session:
      WP 10 Description and Work Plan (20 minutes):
      Objectives
      Deliverables
      Work Plan
      Questions from TSC to the team
      Information needed to move forwards
      Selection of a logo
      Discussion (40 Minutes)
      Discussion
      Conclusions
    3. WP 10 - Objectives
      Establish fast and efficient communication networks
      Use new communication technologies andminimize travel
      Ensure structured knowledge and communication management.
      Disseminate scientific and technological expertise
      Generation of a website
      Create a database of stakeholders and experts
      Establish information pathways
    4. WP10 - Deliverables
      D44 Project website with internal (partner) and external (public) interfaces (Month 3)
      D45 Dissemination plan (month 6)
      D46 Scientific publications (ongoing)
      D47 Best practice tool-kit (Month 48)
      D48 Regular press releases through the public relations office of Partner 2 (Ongoing)
      D49 A film to market the project and to convey information (48)
      D50 EC Periodic report (Month 12, 24, 36, 48)
    5. Collaborative Learning Network
      Participatory stakeholders
      Our case communities (WP5 & 6, 3 & 7)
      Participatory advisors (not on the board)
      New participants, coming with their own resources
      Advisory Board
      Main communication with these:
      Email
      Workshops
      Website
      Face to face
    6. Collaborative Interest Network
      Interested stakeholders
      Community Actors
      Decision Makers
      Policy Makers
      Those wanting to explore C&C in its expanded form
      Schools
      Main communication with these – one-way
      Website
      Social Media
      Journals,
      Local Media
      Radio etc
    7. Work Plan: Internal Communication
      Communication Channels & Expectations
      Email
      Monthly team newsletter from TSC to include a reminder of forthcoming Deliverables & Milestones, linking to the latest items published on the website and informing the team of progress made in individual WP’s.
      Urgent Communication
      Subteam communication - internal to Workpackage– team emails coordinated by WP Leader.
      Phone / Skype
      Communication within sub teams,
      1:1 communication
      Video Conference
      Team meetings: hosted by TSC unless otherwise organised
      Subteam meetings: hosted by WP Lead participant.
      Face to Face:
      Quarterly team meetings to be attended by at least 1 representative of each participating organisation (participation can be by web if necessary)
      Website:
      Reports, publication of findings, and a running record of all communications will be hosted on the website for the team to access, which acts as frontpage for:
      Database- to host reports and information
      Wiki– team members to share expertise & experiences through wiki
    8. Work Plan: External Communication
      Communication Channels & Expectations
      Email
      Quarterly newsletter to key stakeholders including progress update
      Video Conference
      Open meetings – the public can attend open meetings via weblink
      Publications in the relevant journals of each sector and region
      For the purpose of local media, translation into local language of reports, press releases and the overall media relationship organised by local participants
      Local & National Newspapers, Radio & Television etc
      Participants to translate and forward press releases generated by coordinator to their local media outlets
      Face to Face:
      At workshops and meetings
      Website:
      Reports, publication of findings, and a running record of all communications will be hosted via the website for the public to access, which acts as frontpage for:
      Database- hosting reports and information
      Wiki– with which certain stakeholders can interact
      Film on the CONVERGE project
      Translation to be organised by local participants in liaison with TSC where necessary – (India)
    9. Work Plan: Communication Strategy
      On this slide draw up the communication hierarchy and get partners to name their main link for communication
    10. Fostering CONVERGE’s Identity
      Consistency in Branding
      Selection of a logo
    11. Questions to the team
      Which Video Conferencing Software do you currently use?
      What are your concerns regarding internal communication?
      Should subteam email communication be restricted?
      What content do you imagine will come from your WP’s to be disseminated via WP10?
      Which are the typical means of dissemination for this kind of research in your country and field?
    SlideShare Zeitgeist 2009

    + convergeadminconvergeadmin Nominate

    custom

    97 views, 0 favs, 0 embeds more stats

    WOrk Package 10 as presented at the CONVERGE Projec more

    More info about this document

    © All Rights Reserved

    Go to text version

    • Total Views 97
      • 97 on SlideShare
      • 0 from embeds
    • Comments 0
    • Favorites 0
    • Downloads 0
    Most viewed embeds

    more

    All embeds

    less

    Flagged as inappropriate Flag as inappropriate
    Flag as inappropriate

    Select your reason for flagging this presentation as inappropriate. If needed, use the feedback form to let us know more details.

    Cancel
    File a copyright complaint
    Having problems? Go to our helpdesk?

    Categories