Barry Moose with North Carolina Department of Transportation (NCDOT) Division 10 reports at the Charlotte Chamber 2011 Transportation Summit

Barry Moose with North Carolina Department of Transportation (NCDOT) Division 10 reports at the Charlotte Chamber 2011 Transportation Summit

  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Be the first to comment
    Be the first to like this
No Downloads

Views

Total Views
924
On Slideshare
871
From Embeds
53
Number of Embeds
2

Actions

Shares
Downloads
1
Comments
0
Likes
0

Embeds 53

http://charlottechamber.com 51
http://www.linkedin.com 2

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
    No notes for slide

Transcript

  • 1. 2011 Charlotte Regional Transportation Summit
    April 8, 2011
  • 2. Division 10 Project Updates
  • 3. MUMPO Orientation
    State Transportation Improvement Program (STIP)
    Schedule:
    Draft STIP will cover the 12-18 Fiscal Years
    Anticipated Draft TIP should be adopted in July 2011
  • 4. State Transportation Improvement Program
    Facts:
    Statewide Equity Budget is Projected to be $9.21 Billion.
    Does not include Loop Program Dollars
    Does not include Public Transportation Dollars
    Or Congestion Mitigation/Air Quality Dollars
  • 5. State Transportation Improvement Program
    Division 10:
    Our 10 Year Work Plan Proposes to Bring $2,659,500,960 into our Region.
  • 6. Also we are currently working on a new Loop Prioritization process as well as the Mobility Fund Prioritization.
    This could bring additional dollars to the region.
  • 7. Up Coming Projects
  • 8. R-2248E
    The last roadway section of I-485 and in conjunction with R-2123CE will complete the 485 loop.
    Contract to be let to bid May 28, 2010.
    $185 Million
    Let To Contract
  • 9. R-2123CE
    Interchange of I-485 and I-85. The other project to complete the loop. High speed design interchanging freeway to freeway.
    Contract to be let to bid September 2, 2010.
    $155 Million
    LetToContract
  • 10. I-3803B
    Widening of I-85 from interchange with I-485 to the interchange with NC 73. Project is 5.5 miles long and will widen to an 8 lane section.
    Contract to be let to bid August 5, 2010.
    $200 Million
    LetToContract
  • 11. R-2248H
    Complete interchange at Garrison Rd and will serve both CLT Airport and Norfolk Southern Inter-modal facility current under construction. Good example to partnership with both the Airport and Railroad. Will be completed before Inter-modal facility opens.
    Contract to be let to bid July 2010.
    $1.5 Million
    LetToContract
  • 12. U-0209B
    Converting Independence Blvd. to Expressway from Albemarle Rd. to Conference Drive. Will provide for center lanes for future transit and/or managed lanes.
    Contract to be let to bid July 2012 with R/W beginning May of this year.
    $170 Million
    R/WUnderway
  • 13. R-4902
    Widen I-485 from existing 4 lanes to 6 lanes with auxiliary lanes between Johnston Road and NC 51. 6.6 Miles
    Current Let Date is scheduled for FY 2014. With an Anticipated Cost of $70 Million.
    LetDateMovedtoFebruary2012
  • 14. I-4733
    Reconstruction of Catawba Ave. interchange with I-77. Originally proposed as new interchange at a cost of $35 million. Has a federal earmark of $5 million.
    Looking at the use of a Diverging Diamond design which will reduce cost to $6 million and will use the existing bridge.
  • 15. Monroe Bypass
    The Monroe Bypass; this will be a Design Build contract administered by the Turnpike Authority.
    RFQ Advertisement April 15, 2010
    Bid Opening October 22, 2010
    Approx. Cost $750 million
  • 16. Rail Projects
    Two rail projects will be let to contract within next two years as part of the $545 million NC received through competitive ARRA grants.
    12 Double track as part of high speed rail.
    Norfolk Southern/CSX grade separation
    $250 million
  • 17. I-5405
    I-277 (BROOKSHIRE FREEWAY) TO WEST
    CATAWBA AVENUE (EXIT 28).
    CONSTRUCT HIGH OCCUPANCY TOLL
    (HOT) LANES AND CONVERT EXISTING
    HIGH OCCUPANCY VEHICLE (HOV) LANES
    TO HIGH OCCUPANCY TOLL (HOT)
    Estimated Cost $64 Million
  • 18. I-3802A
    Widening of I-85 for the existing 4 lanes to 8 lanes from NC 73 to Rowan County Line.
    New Let Date January 2013 from last TIP of 2017.
    Estimated Cost $120 Million.