CloudValley is a not for profit project intended to construct a WDM based fiber network around Cork.

CloudValley is a not for profit project intended to construct a WDM based fiber network around Cork.

Published in: Business, Technology

0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
1,140
On Slideshare
0
From Embeds
0
Number of Embeds
0
Actions
Shares
0
Downloads
6
Comments
0
Likes
0
Embeds 0
No embeds

Report content
Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
No notes for slide

Transcript

  • 1. Cloud Valley 16 x 10Gbps Layer II Logical Mesh Cork Neutral Internet eXchange Association Limited www.cnix.ie
  • 2. Not for Profit CoOp
    • Strategy Elements
    • Owner Operated via Board of Mgmt
    • Technology work subcontracted
    • Company Limited by Shares
    • Cork Neutral Internet eXchange Association Limited
    • Peering location and member of INEX
  • 3. Existing Infrastructure
    • Duct Providers
    • Government Owned (eNet Operated)
    • BT / Eircom
    • Cork County City Council
  • 4. Existing Infrastructure
  • 5. Providers & Consumers
    • 16 Key Sites (10Gbps Trans.)
    • NSC / Rubicon / CIX / Strencom / ABP / Westgate etc
    • 16 Local Providers (1Gbps Distrib.)
    • ISP and WISPs
    • Park & Building Operators
  • 6. Benefits Service Now 10Mbps / 100Mbps New 40G / 10G / 1G Now 3 weeks New 3 hours Cost Now 100Mbps = € 7,200 p.a. New 100Mbps = € 120 p.a. New 10,000Mbps = €12,000 p.a.
  • 7. Benefits
    • Support Local Businesses (Jobs)
    • ISP and WISPs
      • Business Parks & Last Mile
    • Park & Building Operators
      • Rubicon, NSC, Tyndall
    • Software Companies
      • Big Data
      • Gaming
    • Target new FDI
  • 8. Technology
  • 9. The Future ?
  • 10. Budget
    • Capex €9,000 /node
    • € 1,000 per fiber tap + €8,000 CPE
    • Opex €12,000 /annum /node
    • Duct Fiber Rental €4.00/m/annum
      • 30km for 12 nodes = €120K
    • NOC / Install / Support
      • € 24K for 12 nodes
  • 11. Benefits Service Now 10Mbps / 100Mbps New 40G / 10G / 1G Now 3 weeks New 3 hours Cost Now 100Mbps = € 7,200 p.a. New 100Mbps = € 120 p.a. New 10,000Mbps = €12,000 p.a.