IRRIGATION & FLOOD CONTROL DEPARTMENT (IFCD), MANIPUR Estd. in May, 1976 Assured Irrigation in the state with  Water  Reso...
ONGOING PROJECTS  UNDER MAJOR & MEDIUM IRRIGATION [email_address]
Ongoing Irrigation Projects of IFCD Sl. No. Name of the Projects District Source/ River 1 Khuga Multipurpose Project Chura...
1. Thoubal Multipurpose Project Starting Year :-  1980  Original Cost:- Rs. 47.25 crore( 1980) Revised Cost:-  Rs. 982  cr...
Present Status: A . Physical progress : 85% B.  Financial Progress: Expenditure up to March, 2011 is Rs.819.62 crore inclu...
Rehabilitation & Resettlement :- 6(six) villages namely (i) Louphong (T), (ii) Phayang (K), (iii) Lamlai Khullen (T), (iv)...
D/S View of Thoubal Dam under Construction
Thoubal Dam Spillway under Construction
THOUBAL BARRAGE IN OPERATION SINCE 1991
THOUBAL RIGHT MAIN CANAL IN OPERATION
2. Khuga Multipurpose project <ul><li>Dt. Of start : 1980 Cost:- Original-Rs. 15 crore( 1980) Revised-Rs.381.28 crore (200...
<ul><li>Physical progress  : 98% </li></ul><ul><li>Financial Progress : Expenditure up to March, 2011 is Rs.395.54 crore i...
Shortfall in the completion of the Khuga Multipurpose Project is due to non-completion of the canal portion resulting from...
VIEW OF KHUGA DAM AND SPILLWAY
Khuga Dam Right Side Main Canal in Operation
3. Dolaithabi Barrage Project Starting Year :-  1992   Original Cost:- Rs.  18.86  crore (1992) Revised Cost:- Rs.  213.52...
Ultimate Benefits :-   Irrign. Pot. of 7,545 Ha over CCA of 5,500 Ha  Physical progress  :43.50 % Financial Status :-  Exp...
Concreting at Bay 1, 2 & 3 of Dolaithabi Barrage in Progress
Concreting at Bay 4, 5 & 6 of Dolaithabi Barrage in Progress
Reasons for delay in completion  for ongoing projects: <ul><ul><li>Deteriorated Law and order in the project sites in gene...
Upcoming SlideShare
Loading in …5
×

IFCDongoing

763 views
613 views

Published on

Published in: Business, Technology
0 Comments
1 Like
Statistics
Notes
  • Be the first to comment

No Downloads
Views
Total views
763
On SlideShare
0
From Embeds
0
Number of Embeds
4
Actions
Shares
0
Downloads
6
Comments
0
Likes
1
Embeds 0
No embeds

No notes for slide

IFCDongoing

  1. 1. IRRIGATION & FLOOD CONTROL DEPARTMENT (IFCD), MANIPUR Estd. in May, 1976 Assured Irrigation in the state with Water Resource Projects Managing Flood Control Works Also creates Potential for: a. Raw Water for Water Supplies b . Hydel Power Committed for:
  2. 2. ONGOING PROJECTS UNDER MAJOR & MEDIUM IRRIGATION [email_address]
  3. 3. Ongoing Irrigation Projects of IFCD Sl. No. Name of the Projects District Source/ River 1 Khuga Multipurpose Project Churachandpur District Khuga River 2 Thoubal Multipurpose Project Senapati/Ukhrul & Imphal East District Thoubal River 3 Dolaithabi Barrage Project Imphal East District Iril River
  4. 4. 1. Thoubal Multipurpose Project Starting Year :- 1980 Original Cost:- Rs. 47.25 crore( 1980) Revised Cost:- Rs. 982 crore (2009) The project is planned to harness the perennial water of Thoubal River for creation of Irrigation facility, water supply facility and Hydro Power generation <ul><ul><li>Earthen Dam 1074m long, 66m high </li></ul></ul><ul><ul><li>Barrage of 9 Bays of 9m each </li></ul></ul><ul><ul><li>RMC:- 28Km </li></ul></ul><ul><ul><li>LMC:- 29.117Km </li></ul></ul>Components:- Ultimate Benefits:- a. Irrign. Pot. of 33,449 Ha over CCA of 21,862 Ha. b. Water Supply of 10MGD c. Hydro-Electric Power of 7.5 MW.
  5. 5. Present Status: A . Physical progress : 85% B. Financial Progress: Expenditure up to March, 2011 is Rs.819.62 crore inclusive of AIBP(CA) Rs. 435.50 crore Achievements: The Barrage component along with part of the canal was completed and in operation since 1991 with a partial irrigation potential of 14,861Ha upto the end of March,2011. in Thoubal and Imphal East District Targetted Dt. Of Completion : - March 2012
  6. 6. Rehabilitation & Resettlement :- 6(six) villages namely (i) Louphong (T), (ii) Phayang (K), (iii) Lamlai Khullen (T), (iv) Lamlai Mongbung, (v)Chadong and (vi) Lamlai Khunou(T) are to be submerged/displaced due to the construction of Thoubal Project. Out of the 6 villages 4(four) villages namely (i)Louphong (T), (ii) Phayang(K), (iii)Lamlai Khullen(T) and (iv) Lamlai Mongbung had been completed. The rehabilitation work of 2(two) villages namely Chadong and Lamlai Khunou arer being started.
  7. 7. D/S View of Thoubal Dam under Construction
  8. 8. Thoubal Dam Spillway under Construction
  9. 9. THOUBAL BARRAGE IN OPERATION SINCE 1991
  10. 10. THOUBAL RIGHT MAIN CANAL IN OPERATION
  11. 11. 2. Khuga Multipurpose project <ul><li>Dt. Of start : 1980 Cost:- Original-Rs. 15 crore( 1980) Revised-Rs.381.28 crore (2009) </li></ul><ul><li>Envisages construction of Earthen Dam across Khuga River at Mata Village in Churachandpur District to harness the perennial water of Khuga River for irrigation, Water Supply and Hydro-power Generation. </li></ul><ul><li>Components: a) Earthen Dam 230m. long </li></ul><ul><li>b) Canal : i) RSMC – 60km. </li></ul><ul><li>ii) LSMC – 6.50km </li></ul><ul><li>c) Power Component – 3x500 KW </li></ul><ul><li>Ultimate Benefits : </li></ul><ul><ul><li>Annual Irrigation – 15,000 ha. </li></ul></ul><ul><ul><li>Water Supply – 5 MGD </li></ul></ul><ul><ul><li>Power Generation – 1.50 MW </li></ul></ul>
  12. 12. <ul><li>Physical progress : 98% </li></ul><ul><li>Financial Progress : Expenditure up to March, 2011 is Rs.395.54 crore inclusive of AIBP(CA) Rs. 163.38 crore </li></ul><ul><li>Achievements: </li></ul><ul><ul><li>The Head Work along with a part of canal of the Khuga Multipurpose Project was completed and inaugurated on 12 th November, 2010 with a partial irrigation of 10,000 Ha in Churachandpur and Bishnupur District and potential of 5 MGD of raw water for PHED has been created. </li></ul></ul><ul><li>Targetted Dt. Of Completion : Dec. 2011 </li></ul>
  13. 13. Shortfall in the completion of the Khuga Multipurpose Project is due to non-completion of the canal portion resulting from requirerment of canal lining which was not in the provision of the revised estimate. To achieve the ultimate benefit revised estimate in consultation with Central water Commission is under preparation and also for the improvement of the canal.
  14. 14. VIEW OF KHUGA DAM AND SPILLWAY
  15. 15. Khuga Dam Right Side Main Canal in Operation
  16. 16. 3. Dolaithabi Barrage Project Starting Year :- 1992 Original Cost:- Rs. 18.86 crore (1992) Revised Cost:- Rs. 213.52 crore (2009) The Dolaithabi Barrage Project at Dolaithabi in the Imphal East District, Manipur envisages construction of Barrage 78.75m long across Iril River to harness the perennial water of Iril River for irrigation facilities. <ul><ul><li>Barrage 73.75m long of 6 Bays of 10m each </li></ul></ul><ul><ul><li>Main canal:- 2.58 Km (discharge- 3 cumecs) </li></ul></ul><ul><ul><li>RMC:- 17.30 Km (discharge- 1 cumecs) </li></ul></ul><ul><ul><li>LMC:- 17.30 Km (discharge- 2 cumecs) </li></ul></ul>Components:-
  17. 17. Ultimate Benefits :- Irrign. Pot. of 7,545 Ha over CCA of 5,500 Ha Physical progress :43.50 % Financial Status :- Expenditure up to March, 2011 is Rs. 179.58 crore inclusive of AIBP Rs. 93.62 crore Targetter Dt. Of Completion: - March 2012 .
  18. 18. Concreting at Bay 1, 2 & 3 of Dolaithabi Barrage in Progress
  19. 19. Concreting at Bay 4, 5 & 6 of Dolaithabi Barrage in Progress
  20. 20. Reasons for delay in completion for ongoing projects: <ul><ul><li>Deteriorated Law and order in the project sites in general and frequent economic blockades on both national highways/supply routes. </li></ul></ul><ul><ul><li>Problems relating to land acquisition, rehabilitation plan of the oustees for Thoubal and Khuga Projects. </li></ul></ul><ul><ul><li>Non-release of Central Assistance under AIBP during 2009-10. </li></ul></ul><ul><ul><li>Continued blockade of 61 days during 2010 on NH 39 and NH 53 resulting scarcity of construction materials which in turn slowed down the progress of the projects significantly. </li></ul></ul>

×