• Share
  • Email
  • Embed
  • Like
  • Save
  • Private Content
Part 3.Ul Fs Power Point Pdf
 

Part 3.Ul Fs Power Point Pdf

on

  • 2,096 views

 

Statistics

Views

Total Views
2,096
Views on SlideShare
2,096
Embed Views
0

Actions

Likes
1
Downloads
146
Comments
0

0 Embeds 0

No embeds

Accessibility

Categories

Upload Details

Uploaded via as Adobe PDF

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

    Part 3.Ul Fs Power Point Pdf Part 3.Ul Fs Power Point Pdf Presentation Transcript

    • GREEN ROOF INSTALLATION Ulf Waldmann Mission Valley Roofing, Inc.
    • The German Experience 1960s West Germany was 60% the size of California with a population of 60 million Due to rapid population growth, economic expansion and industrialized agricultural production open natural space was dwindling and green roofs were installed to replace these spaces. Green roofs were not necessarily looked at as usable space. Extensive sedum covered green roof installed in 1962
    • The German Experience cont. 1974 The large Green Roof on the Karlsruhe Hospital was used in a scientific study about climatological consequences of vegetated roofs. Stormwater retention and filtering was the largest benefit. 1979 Established Green Roof Supply Companies were present and very extensive systems developed. W & M Roofing Office Bremen Germany Installed 1984 over SBS Torch applied membrane
    • The German Experience cont. 1982 The FLL (German Landscaping Research Association) published their first guidelines for green roofs which were adopted as industry and test standards and are still the leading source of info today. In the 80s local governments started to mandate green roofs and grant incentives. One incentive were reduced waste- and storm water fees.
    • The German Experience cont. 1990 The FBB (German association for all professions related vegetation on buildings) was founded. To date an estimated 160 million sq. ft. of roofs are vegetated, 95% of which is “Extensive” The most extensive lighweight systems in Germany are 1 ½” thin
    • Extensive Green Roof Example: Haseco-Zoger Bremen Germany
    • General Types of Roofs SLOPED and LOW SLOPE ROOFS We do not call them flat and steep roofs because all roofs should have slope! Sloped Roof  A sloped roof is any roof with a slope of 3” per 12” or more or 14 degrees. Sometimes 2” in 12” is still considered sloped.  Roofing is installed under the assumption that water sheds off the roof quickly.  Common roofing materials are: Shingles, Tile, Slate, Metal Low Slope Roof  A slope of less than 3” in 12” but no less than ¼” in 12”  Roofing or Waterproofing is installed assuming that water may “stand” on the roof for a while  Roofing Materials are installed in a manner that results in a “Membrane” and associated flashings that should be able to tolerate standing water for a limited time. (48 hours)
    • Sloped Roof Example of S-Tile, Flat Tile and Solar Tile
    • Low Slope Roof Example Membrane Roof
    • Typical Green Roof Layers
    • Roof Membrane Types In the roofing industry we speak of roof systems. The waterproofing component of the system is the roof membrane. There are three basic types of membranes currently used for Green Roofs: 1. Bituminous (or Asphalt) 2. Thermoplastic Single Ply 3. Cold applied liquid
    • Bituminous Membranes  Bitumen is the correct name for asphalt, a byproduct of Oil refinement. It succeeded coal based “TAR” as the most widely used roofing product in the 1950s.  Conventional Asphalt (non-modified) Built-Up Roofs are not suitable for Green Roofs due to insufficient density, flexibility and their support of organic growth.  Single Ply installation of modified bitumen membrane (one layer of APP or SBS) is not recommended.  Need root barrier and/or root growth inhibitors. E.G. copper reinforcement or chemical fillers  SEBS Hot applied rubberized asphalt is the most widely used and proven bitumen based system for green roofs (American Hydrotech, Monsey Bakor)
    • Not Suitable BUR Gravel
    • Not Suitable Standard Non Modified Mineral Surface BUR
    • San Diego City College Installed membrane
    • Possibly suitable Modified Bitumen roof if more than one layer and with root inhibitors
    • Cold Applied Liquid Membranes Solvent based waterproofing coatings usually with a reinforcement of fabric. Most common are polyurethanes. Well proven in below grade waterproofing applications. VOC emissions and environmental conditions during installation can be problematic.
    • Thermoplastic Single Ply Membranes Thermoplastic Single-Ply membranes are usually PVC or TPO (Thermoplastic Olefin) rolled goods with the ability to be fused together by heat welding. These membranes have first been used in the 1960s in Europe and are currently the fastest growing and largest roofing segment on Earth.  TPO and PVC membranes are root proof, no inhibitors needed. Root barriers may be specified but are not required.  Hot air welded seams will prohibit root penetration.  Can be applied as ballasted systems i.e. loose laid with little fastening.  Are the more economical choice for green roofs.  60 mils minimum thickness recommended or more for “intensive” roofs.  Flashing techniques and details require little to no maintenance and are less prone to root penetration.  They are light weight and safe to install.
    • Hot Air Welding
    • General Roof Installation Safety & Fall Protection  Cal OSHA requires fall protection equipment for any construction work performed over 15 feet.  Federal OSHA guidelines are more stringent but only apply for work on Federal Government property  Fall protection measures can be: 1. Guard Rails 2. Personal Fall Arrest Equipment (Harness, Line and Anchor) 3. Warning Line or Safety Monitor.  All ladders have to be securely tied off at the top and have to extend 36” over the landing.  Fall protection and safety orders should also be followed during maintenance operations.
    • General Roof Installation Considerations  Positive drainage is a “must”. Plants don’t tolerate standing water. Small ponding can be allowed if the drainage layer is thick enough.  Flashing heights for penetrations and walls should be increased to allow for thickness of planting substrate and plants.  Standard galvanized metal flashings for pipe penetrations are not recommended for bituminous roofing in green roof application.  Water tests are recommended because repairs to defects are more costly after green roof layers were installed.
    • Pipe Flashing Detail
    • Membrane Pipe Boot
    • Installation Recommendations continued  If loose laid membrane is used and the ballast is applied later fastening of membrane should be sufficient to not allow roof to be damaged by wind uplift. Perimeter fastening is a “must”.  Important! Install gravel or pavers around penetrations that require maintenance. E.G. drains, pipes, walls and roof edges. Gravel separation at up–going walls is also a fire barrier.  Mechanical equipment of the roof requires the same separation. Equipment that needs frequent service such as HVAC should have a walkway provision for each it without harming vegetation.
    • Gravel at Edging
    • Typical Roof Details > Drain
    • Note the gravel around the drain
    • Manufacturer’s Specifications  The safest way to specify and install a green roof is to follow the manufacturer’s specifications. Most manufacturers have published green roof specs available.  Currently the specifications in the US are very material intensive. E.g. fully adhered insulation and membrane plus root barrier on TPO roofs. Manufacturer’s will allow less costly alternatives while still guaranteeing their system if asked.  Manufacturer’s Labor and Material warranties of up to 20 years are available.  Manufacturers offer their own filter and drainage products but those may not be desirable for supplier of growth media and plants.
    • Penguin Enclosure Berlin Zoo
    • Building Codes  Fire and wind uplift standards for green roofs are still in development.  The roof system in itself should comply with local fire resistance requirements.  It is recommended to comply with wind uplift requirements for non-ballasted roof systems, in case the vegetation and growth media will be removed at a later time.  Drainage should be designed and implemented for a non-vegetated system for the same reason.  Since codes are still in development the insulation “R-value” should currently be the same as for a non-vegetated system. R-values for the vegetation are a benefit but can no be relied on for thermal efficiency due to variability caused by moisture content, plant coverage, etc.  Fire Ratings are classified as U.L. classes A through C. The City of San Diego requires Class A on all buildings.  Wind uplift ratings are usually defined by Factory Mutual (FM) San Diego is an area that requires FM I-60 (60 lbs per sq. ft.) wind uplift for FM insured buildings.
    • Pavers and green roof Brucker Offices Bremen Germany
    • Filter and Drainage layers  Manufacturers specify different systems  Filter layer is usual spunbond polyester or polypropylene fleece and keeps silt from building up on roof membrane.  Drainage layer could be aggregate (blown clay, rock, etc.) or a manufactured good. It allows excess water to run to drains.  There are products that combine drainage and filter layer. San Diego City College Filter Sheet Installation
    • Installation of filter and drainage layers Mori Residence San Diego
    • San Diego City College Drainage medium installed at drain boxes only
    • Plants and growth Media Use a Specialist Growth media is the “soil” the plants grow in and needs to be specifically formulated for use on roofs, especially in Extensive systems. Here are different installation options:  Conventional application of drainage layers, growth media in bulk and bags and planting plugs is currently the most widely used in the US.  Hydro seeding extensive green roof system is the most economical but needs a lot of initial irrigation and does not allow for immediate wind uplift resistance.  Pre-grown mats, rolls or grid could be installed by Roofing Contractor and allow for immediate wind uplift resistance.  Intensive Green Roof Systems are planted like a regular garden.
    • Separation of Trades  Roof Installation and possibly Filter and drainage layers should be performed by a qualified roofing contractor  In many cases the roofing contractor roof loads and install the growth media.  A landscape professional will plant or seed and establish growth. In Germany the “Roof Gardener” was established as a separate specialty trade. Irrigation if needed should also be installed and monitored by them.
    • Vegetation on Steep Roofs  Steep roofs for vegetated covering are waterproofed in the same manner as low slope roofs. Traditional steep roof materials like shingles are not appropriate.  Provisions need to be taken to keep the growth media form sliding. There are many prefabricated grids, blocks, etc. available.  Irrigation is more complicated because water will move down the slope quickly.  Wind uplift potential is increased  The amount of sunlight may differ greatly on the roof.
    • Steep Roof
    • Steep Roof with blocking to keep vegetation and media from sliding
    • Maintenance  All roofs require periodic (yearly) maintenance.  Visual inspection of roof details, drainage, sealants, etc. should be followed by correction of all unsatisfactory conditions.  Single-ply and liquid applied roofs do not require any maintenance at seams. The replacement of sealants at tops of penetrations and at walls can be done without disturbing the vegetation.  Maintenance of vegetation should be performed by a landscape professional.  It is desirable to have inspections performed by landscaper and roofer together to address any overlapping issues such as plant growth into roof details.
    • Failure of the Waterproofing System  Today’s roof systems are very reliable. Total failures are rare if installed and designed correctly. Root penetration can be avoided by specifying the right materials.  Do not install vegetation over a roof system that is in any way compromised or not suitable for vegetation. Most existing roofs are not and replacement costs for a vegetated roof are much higher.  Membranes under green roofs will last longer than exposed membranes.  95% of roof leaks occur at detail areas. Repair involves removing the gravel around the detail or penetrations and then repairing with conventional methods.
    • Solar Photovoltaic on Green Roof  Can be installed on the same roof.  The cooling effects of the green improve solar performance.  Possible less dust accumulation on solar panels. Photo Courtesy of OPTIGRÜN, Germany
    • Roof Garden Bremen Germany