City Council
October 15, 2013
Project Budget
• Budget Breakdown
• $4M project
• $3.2M – Statewide Transportation Enhancement
Program grant, administered...
Red Arroyo Shared Use Path Project
•

Project limits
•

•

Sherwood Way to Knickerbocker Road

Project Elements
•
•
•
•
•
...
Red Arroyo Shared Use Path Project
•

COSA
•
•
•
•
•
•
•
•

trail design
trail heads
bathroom
stormwater ponds
parking lot...
Red Arroyo Shared Use Path Project

Trailhead

Neighborhood
Trailhead
Red Arroyo Shared Use Path Project

Parking(66)
POND

POND

Parking(63)
UNIDAD PARK

Trailhead

Neighborhood
Trailhead

Re...
Red Arroyo Shared Use Path Project

Parking(25)

POND

Trailhead

Neighborhood
Trailhead
Red Arroyo Shared Use Path Project
Red Arroyo Shared Use Path Project

Typical Bridge Section
Red Arroyo Shared Use Path Project
Trail Heads
Provide quick access point to trail
system from neighborhood or
parking are...
Red Arroyo Shared Use Path Project
• Stormwater Quality
Ponds
• Interception and
collection of
sediment, debris,
nutrients...
Red Arroyo Shared Use Path Project
• Project Timeline
•
•
•
•
•

Project currently in final design
Continual plan review b...
Upcoming SlideShare
Loading in …5
×

San Angelo City Council 10-15-13 red arroyo project update

827 views

Published on

Published in: Technology, Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
827
On SlideShare
0
From Embeds
0
Number of Embeds
13
Actions
Shares
0
Downloads
4
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

San Angelo City Council 10-15-13 red arroyo project update

  1. 1. City Council October 15, 2013
  2. 2. Project Budget • Budget Breakdown • $4M project • $3.2M – Statewide Transportation Enhancement Program grant, administered by TxDOT • $800K – CoSA • $325K – stormwater quality improvements • $325K – ½-cent sales tax for general park improvements • $150K – private donation (anonymous)
  3. 3. Red Arroyo Shared Use Path Project • Project limits • • Sherwood Way to Knickerbocker Road Project Elements • • • • • • • 4.7 miles of 14-foot-wide improved surface, multi-use path 4 major / 6 neighborhood trailheads Parking Lots: Millbrook (66), Unidad Park (63), Sul Ross (25) 2-3 stormwater quality ponds 6 bridge crossings 1 restroom facility (near Unidad Park) Park benches/rest areas
  4. 4. Red Arroyo Shared Use Path Project • COSA • • • • • • • • trail design trail heads bathroom stormwater ponds parking lots USACE permit partial bridge design partial inspection • TxDOT • • • • • • • grant administration plan review FEMA flood study partial bridge design letting partial inspection lighting
  5. 5. Red Arroyo Shared Use Path Project Trailhead Neighborhood Trailhead
  6. 6. Red Arroyo Shared Use Path Project Parking(66) POND POND Parking(63) UNIDAD PARK Trailhead Neighborhood Trailhead Restroom
  7. 7. Red Arroyo Shared Use Path Project Parking(25) POND Trailhead Neighborhood Trailhead
  8. 8. Red Arroyo Shared Use Path Project
  9. 9. Red Arroyo Shared Use Path Project Typical Bridge Section
  10. 10. Red Arroyo Shared Use Path Project Trail Heads Provide quick access point to trail system from neighborhood or parking area. Provide a map to identify where you are and the distances for each section of trail. . Show geographical proximity to commercial areas, neighborhoods, library, park, etc. Working with ASU Students to produce Logo and Trail Maps
  11. 11. Red Arroyo Shared Use Path Project • Stormwater Quality Ponds • Interception and collection of sediment, debris, nutrients, and pollutants
  12. 12. Red Arroyo Shared Use Path Project • Project Timeline • • • • • Project currently in final design Continual plan review by TxDOT Final plans: January 2014 Letting: July 2014 Project Time: 9 months (tentative)

×