City CouncilJanuary 3, 2012
Hickory Water Supply       Update     January 3, 2012
Project Contracts• Well Field Piping• Transmission Main• Pump Station and Well Field Development• Treatment Plant
Well Field Pipelines• 50,700 feet of 20”, 16”, 12” and 8” pipe.• Notice to Proceed:                    October 4, 2011• Co...
Transmission Main• 62 miles of 30” pipe• Contract Awarded:               October 4, 2011• Notice to Proceed:              ...
Pump Station & Well Field Development• 6 million gallon per day booster pump station• Nine (9) 150 to 200 Hp well pumps• P...
Treatment Plant• Purpose:   Remove Radium 226-228 to EPA standard of 5 pCi/L• Pilot testing of treatment methods:   • Ion ...
R.O. Pilot Plant• Test performance of 3 different R.O. membranes• Pilot test period:              90 days• Startup:       ...
City CouncilJanuary 3, 2012
Upcoming SlideShare
Loading in …5
×

City Council January 3, 2012 Hickory update

497 views
473 views

Published on

0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
497
On SlideShare
0
From Embeds
0
Number of Embeds
1
Actions
Shares
0
Downloads
3
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

City Council January 3, 2012 Hickory update

  1. 1. City CouncilJanuary 3, 2012
  2. 2. Hickory Water Supply Update January 3, 2012
  3. 3. Project Contracts• Well Field Piping• Transmission Main• Pump Station and Well Field Development• Treatment Plant
  4. 4. Well Field Pipelines• 50,700 feet of 20”, 16”, 12” and 8” pipe.• Notice to Proceed: October 4, 2011• Completion Date: November 1, 2012• Work Progress • Right of Way Clearing: Complete • Fence Relocations: Complete • Pipe & material delivery: Jan 4, 2012 • Trenching & pipe installation: Jan 2012
  5. 5. Transmission Main• 62 miles of 30” pipe• Contract Awarded: October 4, 2011• Notice to Proceed: January 2012• Completion: June 2013• Work Schedule • R.O.W. preparation begins: Jan. 2012 • Pipe deliveries begin: Jan. 2012 • Pipe installation begins: Feb. 2012
  6. 6. Pump Station & Well Field Development• 6 million gallon per day booster pump station• Nine (9) 150 to 200 Hp well pumps• Project Design: 90% Complete• Advertise for Bids: March 2012• Award By Council: May 2012• Notice to Proceed: June 2012• Completion: June 2013
  7. 7. Treatment Plant• Purpose: Remove Radium 226-228 to EPA standard of 5 pCi/L• Pilot testing of treatment methods: • Ion Exchange: Completed 2011 • Reverse Osmosis
  8. 8. R.O. Pilot Plant• Test performance of 3 different R.O. membranes• Pilot test period: 90 days• Startup: January 2012• Report to TCEQ on results: May 2012• Treatment Plant Construction: • Begin Construction: 2013 • Completion: June 2014
  9. 9. City CouncilJanuary 3, 2012

×