3. Well Field Piping
Completed design: June 28, 2011
Bids Received: August 12, 2011
Contractor: Price Construction, LTD
NTP: October 4, 2011
Current Status: Construction is 95% complete
3
4. Transmission Main
Completed design: August 12, 2011
Bids Received: September 23, 2012
Contractor: Oscar Renda Contracting
Delay in approval and release of funds by TWDB
NTP: January 23, 2012
Current status: Construction activities are
underway
4
5. Booster Pump Station & Well Field
Completed design: February 29, 2012
Design approved by TCEQ & TWDB: April 2012
Bids Received: May 1, 2012
Contractor: Archer Western Construction LLC
Status: COSA Approval
NTP: June 11, 2012 pending final approval and
release of funds by TWDB
5
6. Groundwater Treatment
Ion Exchange (IX) pilot testing 100% complete
Reverse Osmosis (RO) pilot testing 95%
complete
Surface Water Treatment Plant Assessment
completed for incorporation of new facilities
Final design will commence upon selection of
treatment/disposal alternative
6
7. Groundwater Treatment Background
Single-use Ion Exchange (IX)
• Previous pilot testing for groundwater indicated that
single use ion exchange is a viable technology for
removing radium
• Pilot tests showed that O&M costs were higher than
what was suggested by the manufacturers
• Results suggested evaluating other treatment
technologies like RO
Reverse Osmosis
• Pilot Plant investigations started in January 2012
7
8. Treatment Alternative 1: Single-Use
Ion Exchange (IX)
Pretreatment Ion Exchange (IX)
Phosphate
Finished Water
(99% Recovery)
Well Granular Spent Disposal to
Media Resin Licensed Facility
Filter
8
9. Treatment Alternative 2: Reverse
Osmosis (RO)
Pretreatment 3-Stage RO Post Treatment
Acid Antiscalant
Finished Water
(90% Recovery)
CO2
Cartridge Excellent
Filters Water Quality
Well
Granular Brine to
Media Air Calcite
Treatment/
Filter Stripper Contactor
Disposal
9
10. Preliminary RO Results Summary
Excellent membrane performance
All three (3) RO membranes tested produced
good results which allows good competition
All membranes tested maintained radium
below 1 pCi/L in the treated water
10
11. Comparison of Radium at the Point
of Entry Using RO and Single-Use IX
IX Effluent
RO Effluent
Combined TCEQ Limit
Ra 5
(pCi/L)
0
Time
11
12. GW Treatment/Disposal Alternatives
1. Single-Use Ion Exchange (IX) with spent media
to an approved landfill
2. Reverse Osmosis (RO) with Brine to:
a. Deep well injection
b. Land application (mixing with WWTP Effluent)
c. Single-Use Ion Exchange (IX)
12
13. 2a. Brine Disposal/ Deep Well Injection
Inject RO brine into deep underground aquifer
Location of injection wells needs to be identified
Test well needs to be constructed and piloted at anticipated
full scale capacity prior to approval (approx 18 months)
14. 2b. Brine Disposal / Land Application
Brine is pumped to storage pond at wastewater
treatment plant (WWTP)
Brine blended with WWTP effluent
Mixture is land applied
15. 2c. Brine Disposal/ IX Brine Treatment
Single-use IX used to treat RO brine
Treated concentrate sent to sewer
Resin disposed of at a low-level radioactive waste site
16. Incorporation of Hickory GW into
Existing SWTP
Investigated incorporation of Groundwater Treatment
Facilities to expedite design once a treatment alternative
is selected
Evaluated existing plant conditions with respect to
regulations, reliability, performance & hydraulics
Conducted a blending study to investigate compatibility of
the Surface Water & Ground Water
16
17. Estimated Construction Costs Comparison for
a Treatment Capacity of 6 mgd
2a. RO / Deep 2b. RO / Land
1. IX 2c. RO/IX
Well Inj. Application
Alternative
Capital Cost
(millions)
$23.4 $61.0 $65.0 $39.8
Annual O&M
(millions)
$3.3 $2.4 $1.8 $2.2
NPV O&M Costs
(millions)
$92.3 $68.5 $51.1 $62.2
Total NPV Cost
(millions) $115.7 $129.5 $116.1 $102.0
Note: Costs in millions and are for 2012 dollars, assuming a discount rate of 3% and a project life o
30 years starting in 2014, with a capacity of 6 mgd and no expansions.
18. Anticipated Schedule
RO/ Deep RO / Land
IX RO / IX
Well Application
Anticipated Start June 2012
Deep Well Full Scale Pilot
Design & Operation (Approval
needed by TCEQ, TWDB)
--- 18 --- ---
Design (Expedited) 8 11 11 9
TCEQ / TWDB Review 2 2 2 2
Bid/Award/NTP 2 2 2 2
Construction 12 – 15 15 - 18 15 - 18 15 - 18
24 - 28 48 - 51 30 - 33 28 - 31
Total time
months months months months
18
19. Treatment Alternative Evaluation Summary
Reverse
Ion Exchange Osmosis with
(IX) Brine (IX)
Treatment
Capital costs ✓
Annual O&M ✓
Net present value ✓ ✓
Schedule ✓ ✓
Treated water quality ✓
Water recovery ✓
Price fluctuations/competition ✓
22. Capital Cost to Add 3 MGD Capacity in 2014
Reverse Osmosis with
Ion Exchange
IX of Brine
Additional Wells, piping,
civil, electrical etc
$14.5 $14.5
Booster Pump Station
Upgrade
$0.4 $0.4
Treatment $6.0 $11.1
Total Cost $20.9 $26.0
Note: Estimates are given in millions for 2012 dollars.
Additional engineering & management is estimated at 12% and is included in the estimate
23. Recommended SWTP Improvements
Chemical storage and feed facilities for joint use
between GW and SW facilities
New clearwell as the existing clearwell is reaching
its service life
Facilities to recycle filter backwash washwater to
the head of the surface WTP will conserve an
average of 0.3 MGD (100 MG/year)
Raw water blending and flow split structure to
handle the different source waters
23
24. Costs for Major Recommended SWTP
Improvement
Estimated Costs
Alternative
Clearwell $3.9
Backwash handling
facilities
$3.4
Flow blending split
structure
$2.9
New control/lab building $2.4
Note: Estimates are given in millions for 2012 dollars. Additional engineering &
management is estimated at 15% and is included in the estimate