1 | P a g e
Confirmation of the last date for formal
response to the British Government
change to solar financial regime for
5+MW plants under Consultation. “I’m
developing a 5+MW plant but did not pre-
accredit the related asset-SPV’s
prospective facility for ROCs before
13.5.14 (the publication date of URD
14D/114) – how does the Grace Period (in
URD 14D/114) operate in relation to my
PV asset?”
General disclaimer: the following constitutes the written view of the author and in no way constitutes actual legal advice
or a legal opinion and so no reliance may be placed upon the content hereinaftercontained by any reader of this document
in any way whatsoever. In the event that legal advice or opinion is sought, please contact the author of this opinion at
the contact details below. The view below is expressly confined to matters as they stand at 22 May 2014, under the laws
of England and Wales and in accordance with current publications from Her Majesty’s Department for the Energy and
Climate Change as published at https://www.gov.uk on 13 May, 2014.
LAST DATE FOR RESPONSES TO URD 14D/114
The last date for responses to the Consultation can be by 7 July 2014. Any
assistance upon construction of a response may be requested using the contact
information below. See FN1 below.
GRACE PERIOD FOR 5+MW GROUNDMOUNTED PV INSTALLATIONS
Evidence to allow the grace period to install a >5MW plant by April 2016 will
not be invoked unless:
(a) preliminary ROCs accreditation for each development asset was obtained
2 | P a g e
on or before 13.5.14, or,
(b) evidence at paragraph 32 in URD 14D/114 can be provided, namely,
(a) an accepted DNO connection offer; and,
(b) planning consent (conditional/unconditional) or confirmation that there
is no planning consent; and,
(c) a Director’s Certificate that the developer or the SPV-yieldco that will be
the tenant-co during the O&M phase under a lease has an agreement to
lease with the Landowner, or, has bought the freehold title before
13.5.14; and,
(d) evidence in the form of receipted invoices that £100,000 per expected
installed megawatt of expected consented capacity has been expended
on/before 13.5.14, or material equipment contracts (for the photovoltaic
panels, inverters, switch gear and mounting structures) have been
entered into on or before 13.5.14 (probably with evidence of the board
meetings/written resolution passed by the board to approve entry into
such contracts to prove evidence of capacity).
See FN2 below.
London, 22 May 2014.
To find out more on how My Business Counsel can assist you, please contact our
Solar Team today on info@mybusinesscounsel.com or by calling +44 (0) 203 507
0152.
FN1 - Responses
 Issue date of URD 14D/114: 13 May 2014
 Responses to URD 14D/114 by: 7 July 2014
- See at:
https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/31052
4/Consultation_on_changes_to_financial_support_for_solar_PV_.pdf (p.2/24)
FN2 - Grace period
“…
3 | P a g e
Proposed Policy
21. The Government therefore considers it necessary to take action to control the costs
of large-scale solar PV to ensure it is affordable in the context of the RO and EMR. We
propose to achieve this by closing the RO across Great Britain to new solar PV
generating stations, both ground- and building-mounted, above 5MW from 1 April
2015. The closure would also apply to any additional capacity added to an accredited
solar PV station from 1 April 2015 where the station is, or would become, above 5MW.
This would mean, for example, that a station which is already above 5MW in size could
not add additional capacity under the RO after 31 March 2015 unless it qualified for a
grace period in respect of the additional capacity. Similarly, a station currently of 3MW,
for example, could add up to an additional 2MW of capacity after 31 March 2015 without
requiring a grace period. However, such a station could not add an amount of capacity
after 31 March 2015 that would take the total installed capacity above 5MW unless the
additional capacity that took it above the 5MW threshold qualified for a grace period. The
5MW limit would be based on the total installed capacity of a station.
22. Regardless of the changes proposed in this consultation document, solar PV
installations above 5MW in size will be eligible to apply for support under the new CfD
auctions. The first allocation round is expected to open in October 2014. In addition,
projects of 5MW and below would continue to be eligible for the RO (see below), and
support for small-scale solar PV projects will continue to be available from the FIT
scheme.
23. In order to seek to protect developers that have already made a significant financial
commitment to projects, we propose the following grace period arrangements. New solar
PV stations above 5MW would continue to be eligible to enter the RO after 31 March
2015 if one of the following conditions is met:
a) preliminary accreditation under the RO has been obtained for the station on or before
13 May 2014 (i.e. the date of publication of this consultation); or
b) evidence as described in paragraphs 32-33 is provided to Ofgem demonstrating that
significant commitments have been made on or before 13 May 2014 in respect of the
project. The evidence must be provided to Ofgem by 31 March 2015.
24. We propose that the above grace period would also be available for additional
capacity added to stations accredited on or before 13 May 2014.
25. In addition, in order to benefit from the grace period, the station must be
commissioned and accredited by 31 March 2016 and all of the other usual RO eligibility
requirements must be met. In the case of additional capacity, it must be added to the
station by 31 March 2016. The grace period lasts for 1 year following closure of the RO
to larger solar PV projects because the relatively fast deployment times for solar PV
leads us to expect that those projects which have already incurred significant financial
commitments should be able to commission and accredit by 31 March 2016.
26. Projects benefitting from a grace period would receive the ROC level in force on the
date of accreditation, i.e. the grace period would not protect the project from the
scheduled reductions in the level of ROC support.
4 | P a g e
27. Before the 1 April 2015 closure date, new solar PV stations above 5MW can
continue to be accredited under the RO if they have commissioned and submitted an
accreditation application before 1 April 2015 and meet all the other usual RO eligibility
requirements. This also applies to additional capacity added to existing accredited
stations before 1 April 2015. Solar PV projects above 5MW in scale which for any reason
are not eligible for the grace period and do not accredit by 31 March 2015, will not be
eligible to enter the RO after that date. They will, however, be eligible to apply for
support under the CfD once that process opens for applications, subject to the rules of
that scheme.
28. As from 1 April 2015, solar PV installations supported under the FIT will no longer be
allowed to enter the RO when they exceed the maximum 5MW threshold under the FIT.
29. The RO is already closed to solar PV microgenerators. The RO would remain open
to new solar PV stations up to 5MW (other than microgenerators) until 31 March 2017.
The grid connection delay grace period set out in the Government Response to the
consultations on Renewable Obligation Transition and on Grace Periods13 would remain
available to solar PV stations up to 5MW. The 1 April 2017 closure date and grid delay
grace period would continue to apply to additional capacity added to RO accredited solar
PV stations, as long as the entire station remains at 5MW or less total installed capacity.
Evidence requirements for the grace period
32. Due to the speed at which solar PV projects can deploy and the need for cost
control, the evidence requirements need to be rigorous to ensure that only those
projects that have already made significant financial commitments are able to qualify for
the grace period. In drawing up the evidence requirements, we wish to ensure that they
enable Ofgem to
assess the evidence quickly and objectively, and with confidence that their decisions are
unlikely to be subject to subsequent legal challenge; and that they minimise the risk of
gaming. This implies that the evidence needs to be defined in detail and involve minimal
subjective judgement or evaluation.
33. We propose that four categories of evidence will be required, and that developers
will need to present all four types of evidence in combination to Ofgem in order to
demonstrate eligibility to enter the RO after 31 March 2015. The categories below draw
on our experience of, and responses from, the consultations on RO grace periods
associated with closure of the RO in April 201714 and DECC engagement with
stakeholders on the evidence to demonstrate progress against delivery milestones set
out in contracts for difference. The proposed forms of evidence are:
a) A grid connection offer and acceptance of that offer, both dated no later than 13 May
2014, and a letter from the network operator estimating or setting a date for the grid
connection which is on or before 31 March 2016; or confirmation that no grid connection
is required;
b) Relevant planning consents dated no later than 13 May 2014, evidenced by either
planning permission under the Town and Country Planning Act 1990 or the Town and
Country Planning (Scotland) Act 1997, consent under section 36 of the Electricity Act, or
development consent under the Planning Act 2008; or confirmation that planning
approval is not required. We consider it unlikely that operators will necessarily be able to
comply with all outstanding conditions precedent in advance of construction. We
5 | P a g e
therefore propose not to require that conditions precedent set upon the planning consent
are fulfilled in advance of construction;
c) A Director’s Certificate confirming that as at 13 May 2014 the developer or proposed
operator of the station owns the land on which the station is to be situated or has an
agreement to lease the land. We do not consider that an option to purchase or lease
land is a sufficient indication that a project has made a significant financial decision and
is as committed to proceeding as a project which has actually purchased or leased the
land;
d) Evidence in the form of invoices and payment receipts from the developer or
proposed operator of the station that demonstrate that a minimum of £100,000 per MW
of expected consented capacity in project pre-commissioning costs (PPC) has been
incurred on the project by 13 May 2014, OR proof that all material equipment contracts
have been entered into for the project by 13 May 2014. For the purposes of this
consultation, PPC refers to the costs of the initial development of a plant including
planning, pre-development costs, and equipment and construction costs. With regard to
solar PV developments >5MW, £100,000 per MW of capacity represents 10% of the
total project pre-commissioning costs quoted in the CfD agreement15. For example, a
6MW project would have to provide invoices and payment receipts for expenditure of at
least £600,000
incurred by 13 May 2014. For solar PV developments >5MW, we propose that ‘material
equipment contracts' means contracts for the key electricity generation plant and
apparatus used at a solar PV station, and includes photovoltaic panels, inverters, switch
gear and mounting structures.
..”.
- See at:
https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/31052
4/Consultation_on_changes_to_financial_support_for_solar_PV_.pdf (p.9-12/24)

More Related Content

Viewers also liked

Kangen richness business plan proper
Kangen richness business plan properKangen richness business plan proper
Kangen richness business plan proper
Vox Populi
 
Pmp application form.ashx
Pmp application form.ashxPmp application form.ashx
Pmp application form.ashx
Shelly Fizer
 
Cap baltimore-realpropertymgt
Cap baltimore-realpropertymgtCap baltimore-realpropertymgt
Cap baltimore-realpropertymgt
sulemancapital
 

Viewers also liked (9)

Easy health premium chart apollo munich insurance
Easy health premium chart apollo munich insuranceEasy health premium chart apollo munich insurance
Easy health premium chart apollo munich insurance
 
Market Analysis - Current US Energy Storage Market
Market Analysis - Current US Energy Storage MarketMarket Analysis - Current US Energy Storage Market
Market Analysis - Current US Energy Storage Market
 
Kangen richness business plan proper
Kangen richness business plan properKangen richness business plan proper
Kangen richness business plan proper
 
Pmp application form.ashx
Pmp application form.ashxPmp application form.ashx
Pmp application form.ashx
 
Cap baltimore-realpropertymgt
Cap baltimore-realpropertymgtCap baltimore-realpropertymgt
Cap baltimore-realpropertymgt
 
IT Strategy in Airlines Industry
IT Strategy in Airlines IndustryIT Strategy in Airlines Industry
IT Strategy in Airlines Industry
 
Dubai International Dance Competition - Nrityanjali (jan29-feb05)
Dubai International Dance Competition - Nrityanjali (jan29-feb05)Dubai International Dance Competition - Nrityanjali (jan29-feb05)
Dubai International Dance Competition - Nrityanjali (jan29-feb05)
 
CSCW networked privacy workshop - keynote
CSCW networked privacy workshop - keynoteCSCW networked privacy workshop - keynote
CSCW networked privacy workshop - keynote
 
The Danish Market for Telemedicine Solutions 2015
The Danish Market for Telemedicine Solutions 2015 The Danish Market for Telemedicine Solutions 2015
The Danish Market for Telemedicine Solutions 2015
 

More from Bhalindra Bath - projects & M&A law

Impact of CfDs for 5+MW solar installations in the UK post 1.4.15 - URN 14D/114
Impact of CfDs for 5+MW solar installations in the UK post 1.4.15 - URN 14D/114Impact of CfDs for 5+MW solar installations in the UK post 1.4.15 - URN 14D/114
Impact of CfDs for 5+MW solar installations in the UK post 1.4.15 - URN 14D/114
Bhalindra Bath - projects & M&A law
 

More from Bhalindra Bath - projects & M&A law (13)

The Contracts for Difference – Strike Back (with a cameo appearance by...Ener...
The Contracts for Difference – Strike Back (with a cameo appearance by...Ener...The Contracts for Difference – Strike Back (with a cameo appearance by...Ener...
The Contracts for Difference – Strike Back (with a cameo appearance by...Ener...
 
Summary
SummarySummary
Summary
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...
 
MBC ENGINEERING, INFRASTRUCTURE & PROCUREMENT - 03.2015
MBC ENGINEERING, INFRASTRUCTURE & PROCUREMENT -  03.2015MBC ENGINEERING, INFRASTRUCTURE & PROCUREMENT -  03.2015
MBC ENGINEERING, INFRASTRUCTURE & PROCUREMENT - 03.2015
 
MBC W2F W2E BIOFUEL BIOMASS AD - 03.2015
MBC W2F W2E BIOFUEL BIOMASS AD -  03.2015MBC W2F W2E BIOFUEL BIOMASS AD -  03.2015
MBC W2F W2E BIOFUEL BIOMASS AD - 03.2015
 
MBC SOLAR
MBC SOLAR MBC SOLAR
MBC SOLAR
 
Exploiting deep geothermal energy and oil in the UK, building CO2 reduction c...
Exploiting deep geothermal energy and oil in the UK, building CO2 reduction c...Exploiting deep geothermal energy and oil in the UK, building CO2 reduction c...
Exploiting deep geothermal energy and oil in the UK, building CO2 reduction c...
 
DECC decision on ROCs CfDs Grace Periods Grandfathering of ROCs and degressio...
DECC decision on ROCs CfDs Grace Periods Grandfathering of ROCs and degressio...DECC decision on ROCs CfDs Grace Periods Grandfathering of ROCs and degressio...
DECC decision on ROCs CfDs Grace Periods Grandfathering of ROCs and degressio...
 
URN 14D 328 - applying for a Contract for Difference this October 2014 under ...
URN 14D 328 - applying for a Contract for Difference this October 2014 under ...URN 14D 328 - applying for a Contract for Difference this October 2014 under ...
URN 14D 328 - applying for a Contract for Difference this October 2014 under ...
 
De-risking and enabling uk shale gas and deep heat geothermal projects; &, ri...
De-risking and enabling uk shale gas and deep heat geothermal projects; &, ri...De-risking and enabling uk shale gas and deep heat geothermal projects; &, ri...
De-risking and enabling uk shale gas and deep heat geothermal projects; &, ri...
 
5.6.14 UK Infrastructure Bill - potential impact on private sector businesses...
5.6.14 UK Infrastructure Bill - potential impact on private sector businesses...5.6.14 UK Infrastructure Bill - potential impact on private sector businesses...
5.6.14 UK Infrastructure Bill - potential impact on private sector businesses...
 
Potential next steps for developers if URD 14D/114 is passed
Potential next steps for developers if URD 14D/114 is passedPotential next steps for developers if URD 14D/114 is passed
Potential next steps for developers if URD 14D/114 is passed
 
Impact of CfDs for 5+MW solar installations in the UK post 1.4.15 - URN 14D/114
Impact of CfDs for 5+MW solar installations in the UK post 1.4.15 - URN 14D/114Impact of CfDs for 5+MW solar installations in the UK post 1.4.15 - URN 14D/114
Impact of CfDs for 5+MW solar installations in the UK post 1.4.15 - URN 14D/114
 

Recently uploaded

一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理
一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理
一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理
bd2c5966a56d
 
一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理
一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理
一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理
F La
 
一比一原版(Waterloo毕业证书)加拿大滑铁卢大学毕业证如何办理
一比一原版(Waterloo毕业证书)加拿大滑铁卢大学毕业证如何办理一比一原版(Waterloo毕业证书)加拿大滑铁卢大学毕业证如何办理
一比一原版(Waterloo毕业证书)加拿大滑铁卢大学毕业证如何办理
e9733fc35af6
 
一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理
一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理
一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理
ss
 
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
bd2c5966a56d
 
一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理
Airst S
 
一比一原版(KPU毕业证书)加拿大昆特兰理工大学毕业证如何办理
一比一原版(KPU毕业证书)加拿大昆特兰理工大学毕业证如何办理一比一原版(KPU毕业证书)加拿大昆特兰理工大学毕业证如何办理
一比一原版(KPU毕业证书)加拿大昆特兰理工大学毕业证如何办理
e9733fc35af6
 
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
Airst S
 

Recently uploaded (20)

Performance of contract-1 law presentation
Performance of contract-1 law presentationPerformance of contract-1 law presentation
Performance of contract-1 law presentation
 
ARTICLE 370 PDF about the indian constitution.
ARTICLE 370 PDF about the  indian constitution.ARTICLE 370 PDF about the  indian constitution.
ARTICLE 370 PDF about the indian constitution.
 
一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理
一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理
一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理
 
一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理
一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理
一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理
 
一比一原版(Waterloo毕业证书)加拿大滑铁卢大学毕业证如何办理
一比一原版(Waterloo毕业证书)加拿大滑铁卢大学毕业证如何办理一比一原版(Waterloo毕业证书)加拿大滑铁卢大学毕业证如何办理
一比一原版(Waterloo毕业证书)加拿大滑铁卢大学毕业证如何办理
 
3 Formation of Company.www.seribangash.com.ppt
3 Formation of Company.www.seribangash.com.ppt3 Formation of Company.www.seribangash.com.ppt
3 Formation of Company.www.seribangash.com.ppt
 
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURYA SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
 
一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理
一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理
一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理
 
Hely-Hutchinson v. Brayhead Ltd .pdf
Hely-Hutchinson v. Brayhead Ltd         .pdfHely-Hutchinson v. Brayhead Ltd         .pdf
Hely-Hutchinson v. Brayhead Ltd .pdf
 
Understanding the Role of Labor Unions and Collective Bargaining
Understanding the Role of Labor Unions and Collective BargainingUnderstanding the Role of Labor Unions and Collective Bargaining
Understanding the Role of Labor Unions and Collective Bargaining
 
Relationship Between International Law and Municipal Law MIR.pdf
Relationship Between International Law and Municipal Law MIR.pdfRelationship Between International Law and Municipal Law MIR.pdf
Relationship Between International Law and Municipal Law MIR.pdf
 
Reason Behind the Success of Law Firms in India
Reason Behind the Success of Law Firms in IndiaReason Behind the Success of Law Firms in India
Reason Behind the Success of Law Firms in India
 
Chambers Global Practice Guide - Canada M&A
Chambers Global Practice Guide - Canada M&AChambers Global Practice Guide - Canada M&A
Chambers Global Practice Guide - Canada M&A
 
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
 
一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理
 
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
 
Human Rights_FilippoLuciani diritti umani.pptx
Human Rights_FilippoLuciani diritti umani.pptxHuman Rights_FilippoLuciani diritti umani.pptx
Human Rights_FilippoLuciani diritti umani.pptx
 
Shubh_Burden of proof_Indian Evidence Act.pptx
Shubh_Burden of proof_Indian Evidence Act.pptxShubh_Burden of proof_Indian Evidence Act.pptx
Shubh_Burden of proof_Indian Evidence Act.pptx
 
一比一原版(KPU毕业证书)加拿大昆特兰理工大学毕业证如何办理
一比一原版(KPU毕业证书)加拿大昆特兰理工大学毕业证如何办理一比一原版(KPU毕业证书)加拿大昆特兰理工大学毕业证如何办理
一比一原版(KPU毕业证书)加拿大昆特兰理工大学毕业证如何办理
 
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
 

Final response date for URD 14D/114. If I am developing a 5+MW asset now, will I qualify for the proposed grace period according to URD 14D/114?

  • 1. 1 | P a g e Confirmation of the last date for formal response to the British Government change to solar financial regime for 5+MW plants under Consultation. “I’m developing a 5+MW plant but did not pre- accredit the related asset-SPV’s prospective facility for ROCs before 13.5.14 (the publication date of URD 14D/114) – how does the Grace Period (in URD 14D/114) operate in relation to my PV asset?” General disclaimer: the following constitutes the written view of the author and in no way constitutes actual legal advice or a legal opinion and so no reliance may be placed upon the content hereinaftercontained by any reader of this document in any way whatsoever. In the event that legal advice or opinion is sought, please contact the author of this opinion at the contact details below. The view below is expressly confined to matters as they stand at 22 May 2014, under the laws of England and Wales and in accordance with current publications from Her Majesty’s Department for the Energy and Climate Change as published at https://www.gov.uk on 13 May, 2014. LAST DATE FOR RESPONSES TO URD 14D/114 The last date for responses to the Consultation can be by 7 July 2014. Any assistance upon construction of a response may be requested using the contact information below. See FN1 below. GRACE PERIOD FOR 5+MW GROUNDMOUNTED PV INSTALLATIONS Evidence to allow the grace period to install a >5MW plant by April 2016 will not be invoked unless: (a) preliminary ROCs accreditation for each development asset was obtained
  • 2. 2 | P a g e on or before 13.5.14, or, (b) evidence at paragraph 32 in URD 14D/114 can be provided, namely, (a) an accepted DNO connection offer; and, (b) planning consent (conditional/unconditional) or confirmation that there is no planning consent; and, (c) a Director’s Certificate that the developer or the SPV-yieldco that will be the tenant-co during the O&M phase under a lease has an agreement to lease with the Landowner, or, has bought the freehold title before 13.5.14; and, (d) evidence in the form of receipted invoices that £100,000 per expected installed megawatt of expected consented capacity has been expended on/before 13.5.14, or material equipment contracts (for the photovoltaic panels, inverters, switch gear and mounting structures) have been entered into on or before 13.5.14 (probably with evidence of the board meetings/written resolution passed by the board to approve entry into such contracts to prove evidence of capacity). See FN2 below. London, 22 May 2014. To find out more on how My Business Counsel can assist you, please contact our Solar Team today on info@mybusinesscounsel.com or by calling +44 (0) 203 507 0152. FN1 - Responses  Issue date of URD 14D/114: 13 May 2014  Responses to URD 14D/114 by: 7 July 2014 - See at: https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/31052 4/Consultation_on_changes_to_financial_support_for_solar_PV_.pdf (p.2/24) FN2 - Grace period “…
  • 3. 3 | P a g e Proposed Policy 21. The Government therefore considers it necessary to take action to control the costs of large-scale solar PV to ensure it is affordable in the context of the RO and EMR. We propose to achieve this by closing the RO across Great Britain to new solar PV generating stations, both ground- and building-mounted, above 5MW from 1 April 2015. The closure would also apply to any additional capacity added to an accredited solar PV station from 1 April 2015 where the station is, or would become, above 5MW. This would mean, for example, that a station which is already above 5MW in size could not add additional capacity under the RO after 31 March 2015 unless it qualified for a grace period in respect of the additional capacity. Similarly, a station currently of 3MW, for example, could add up to an additional 2MW of capacity after 31 March 2015 without requiring a grace period. However, such a station could not add an amount of capacity after 31 March 2015 that would take the total installed capacity above 5MW unless the additional capacity that took it above the 5MW threshold qualified for a grace period. The 5MW limit would be based on the total installed capacity of a station. 22. Regardless of the changes proposed in this consultation document, solar PV installations above 5MW in size will be eligible to apply for support under the new CfD auctions. The first allocation round is expected to open in October 2014. In addition, projects of 5MW and below would continue to be eligible for the RO (see below), and support for small-scale solar PV projects will continue to be available from the FIT scheme. 23. In order to seek to protect developers that have already made a significant financial commitment to projects, we propose the following grace period arrangements. New solar PV stations above 5MW would continue to be eligible to enter the RO after 31 March 2015 if one of the following conditions is met: a) preliminary accreditation under the RO has been obtained for the station on or before 13 May 2014 (i.e. the date of publication of this consultation); or b) evidence as described in paragraphs 32-33 is provided to Ofgem demonstrating that significant commitments have been made on or before 13 May 2014 in respect of the project. The evidence must be provided to Ofgem by 31 March 2015. 24. We propose that the above grace period would also be available for additional capacity added to stations accredited on or before 13 May 2014. 25. In addition, in order to benefit from the grace period, the station must be commissioned and accredited by 31 March 2016 and all of the other usual RO eligibility requirements must be met. In the case of additional capacity, it must be added to the station by 31 March 2016. The grace period lasts for 1 year following closure of the RO to larger solar PV projects because the relatively fast deployment times for solar PV leads us to expect that those projects which have already incurred significant financial commitments should be able to commission and accredit by 31 March 2016. 26. Projects benefitting from a grace period would receive the ROC level in force on the date of accreditation, i.e. the grace period would not protect the project from the scheduled reductions in the level of ROC support.
  • 4. 4 | P a g e 27. Before the 1 April 2015 closure date, new solar PV stations above 5MW can continue to be accredited under the RO if they have commissioned and submitted an accreditation application before 1 April 2015 and meet all the other usual RO eligibility requirements. This also applies to additional capacity added to existing accredited stations before 1 April 2015. Solar PV projects above 5MW in scale which for any reason are not eligible for the grace period and do not accredit by 31 March 2015, will not be eligible to enter the RO after that date. They will, however, be eligible to apply for support under the CfD once that process opens for applications, subject to the rules of that scheme. 28. As from 1 April 2015, solar PV installations supported under the FIT will no longer be allowed to enter the RO when they exceed the maximum 5MW threshold under the FIT. 29. The RO is already closed to solar PV microgenerators. The RO would remain open to new solar PV stations up to 5MW (other than microgenerators) until 31 March 2017. The grid connection delay grace period set out in the Government Response to the consultations on Renewable Obligation Transition and on Grace Periods13 would remain available to solar PV stations up to 5MW. The 1 April 2017 closure date and grid delay grace period would continue to apply to additional capacity added to RO accredited solar PV stations, as long as the entire station remains at 5MW or less total installed capacity. Evidence requirements for the grace period 32. Due to the speed at which solar PV projects can deploy and the need for cost control, the evidence requirements need to be rigorous to ensure that only those projects that have already made significant financial commitments are able to qualify for the grace period. In drawing up the evidence requirements, we wish to ensure that they enable Ofgem to assess the evidence quickly and objectively, and with confidence that their decisions are unlikely to be subject to subsequent legal challenge; and that they minimise the risk of gaming. This implies that the evidence needs to be defined in detail and involve minimal subjective judgement or evaluation. 33. We propose that four categories of evidence will be required, and that developers will need to present all four types of evidence in combination to Ofgem in order to demonstrate eligibility to enter the RO after 31 March 2015. The categories below draw on our experience of, and responses from, the consultations on RO grace periods associated with closure of the RO in April 201714 and DECC engagement with stakeholders on the evidence to demonstrate progress against delivery milestones set out in contracts for difference. The proposed forms of evidence are: a) A grid connection offer and acceptance of that offer, both dated no later than 13 May 2014, and a letter from the network operator estimating or setting a date for the grid connection which is on or before 31 March 2016; or confirmation that no grid connection is required; b) Relevant planning consents dated no later than 13 May 2014, evidenced by either planning permission under the Town and Country Planning Act 1990 or the Town and Country Planning (Scotland) Act 1997, consent under section 36 of the Electricity Act, or development consent under the Planning Act 2008; or confirmation that planning approval is not required. We consider it unlikely that operators will necessarily be able to comply with all outstanding conditions precedent in advance of construction. We
  • 5. 5 | P a g e therefore propose not to require that conditions precedent set upon the planning consent are fulfilled in advance of construction; c) A Director’s Certificate confirming that as at 13 May 2014 the developer or proposed operator of the station owns the land on which the station is to be situated or has an agreement to lease the land. We do not consider that an option to purchase or lease land is a sufficient indication that a project has made a significant financial decision and is as committed to proceeding as a project which has actually purchased or leased the land; d) Evidence in the form of invoices and payment receipts from the developer or proposed operator of the station that demonstrate that a minimum of £100,000 per MW of expected consented capacity in project pre-commissioning costs (PPC) has been incurred on the project by 13 May 2014, OR proof that all material equipment contracts have been entered into for the project by 13 May 2014. For the purposes of this consultation, PPC refers to the costs of the initial development of a plant including planning, pre-development costs, and equipment and construction costs. With regard to solar PV developments >5MW, £100,000 per MW of capacity represents 10% of the total project pre-commissioning costs quoted in the CfD agreement15. For example, a 6MW project would have to provide invoices and payment receipts for expenditure of at least £600,000 incurred by 13 May 2014. For solar PV developments >5MW, we propose that ‘material equipment contracts' means contracts for the key electricity generation plant and apparatus used at a solar PV station, and includes photovoltaic panels, inverters, switch gear and mounting structures. ..”. - See at: https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/31052 4/Consultation_on_changes_to_financial_support_for_solar_PV_.pdf (p.9-12/24)