Loading…

Flash Player 9 (or above) is needed to view presentations.
We have detected that you do not have it on your computer. To install it, go here.

Like this presentation? Why not share!

CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED

on

  • 3,795 views

 

Statistics

Views

Total Views
3,795
Views on SlideShare
3,795
Embed Views
0

Actions

Likes
0
Downloads
69
Comments
0

0 Embeds 0

No embeds

Accessibility

Upload Details

Uploaded via as Microsoft PowerPoint

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

CIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITED CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED Presentation Transcript

  • CIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITED
    AA
    GTE (Civil)
  • CONTENTS:
    Project Overview
    Civil Construction and Fatima Fertilizer
    My Working Areas
    Roads and its Structures
    Weigh Bridge
    Nitro Phosphate (NP) Plant
  • Project Overview:
    Salient Features:
    Start of Land Acquiring in Year 2005.
    Total Land Acquired 800 acres.
    Estimated Cost in Rs. = 8,000 million
    Start of project phase in April 2007 (NA plant).
    Total no of plants/supporting areas are 50+.
    Four Types of Fertilizer Products/Plants having design capacity.
    1. Urea 1500 MTPD
    2. CAN 1400 MTPD
    3. NP 1200 MTPD
    4. NPK 1000 MTPD
  • Project Overview:
    Salient Features:
    Other Supporting Plants having design capacity
    1. Ammonia 1500 MTPD
    2. Nitric Acid 1500 MTPD
    3. Offsite & Utilities 50 MW
    Gas consumption of 75 MMCFD
    Civil Contractors
    1. CNCEC China
    2. IPL Pakistan
    Civil Designers
    1. NESPAK Pakistan
    2. A & A Pakistan
  • Civil Construction and Fatima Fertilizer:
    Civil Engineering role in the establishment of any kind of project is not ignorable.
    The project like Fatima Fertilizer, its importance is more.
    Fatima Fertilizer have structures
    From simple pumps foundations to complex pile foundation under Prilling towers and Ammonia Tank.
    From steel structures of Urea, CAN, Bulk Storage & Ware houses to concrete structures of Cooling Tower, Raw water Reservoir, Bagging, NA and NP plants.
    From Technical building, CCR I & II, Substations to Strom water drains, water pits, area development and network of roads.
  • Civil Construction and Fatima Fertilizer:
    In Fatima Fertilizer, basic form of structure is frame structure .
    Frame Structure is a combination of beams and columns and load is transfer through this system to design foundation.
    Two types of frame structures are used.
    1. Steel Structures
    2. Concrete Structures
  • Steel Structures:
    • Steel structures are basically composite structures having substructure of concrete and superstructure of steel e.g.
    • Ammonia & Urea Plants
    • CAN & NPK Plants
    • Bulk Storage (Phase-I)
    • Ware houses, Pipe Racks etc.
  • Concrete Structures:
    • Concrete structures comprise of both substructure and superstructure of concrete e.g.
    • Raw Water Reservoir and Treatment Plant
    • Cooling Tower & Urea Prilling Tower
    • Bagging (Phase I & II)
    • Bulk storage (Phase II)
    • NP Plant
    • Substations CCR I & II and Equalization Basin
    • Workshop, Technical Building, Laboratory, etc
  • Pictorial View of Civil Construction in FFCL:
    Construction View of
    Urea Prilling Tower and Plant
  • Nitric Acid Plant
    Foundation of
    Ammonia Storage Tank
  • Construction View of
    Cooling Tower
    Raw Water Reservoir and
    Water Treatment Plant
  • Construction of CAN Plant
    Construction of Ammonia Plant
  • Construction of
    Bagging (Phase – I)
    Construction of
    Bulk Storage (Phase – I)
  • Bagging (Phase – II)
    under construction
    NP Plant
    under construction
  • My Working Areas:
    In Fatima Fertilizer during my Trainee period of 1 year, I worked on Roads and its Structures, Construction of Weigh Bridge and also play a vital role in the construction of NP plant.
  • Job Responsibilities:
    Study of Drawings
    Design Reviews
    Survey of roads
    Quality Control at site ( Formwork, Steel & Concrete)
    Inspections before concrete
    Checking of Bar Bending Schedule
    Checking of Bills
  • Roads and its Structures:
    Salient Features
    Total length of Roads = 17.484 km
    Completed Length of roads = 8.301 km
    Remaining Length of roads = 9.183 km
    Roads have Strom water drain and walkway on one side, and shoulders on both sides.
    Designer = Akbar & Associates
    Contractors = IPL, Farhan Munir & Company, AHCC
    Type of Pavement = Rigid Pavement
    Design Capacity = 90 Tons
  • What is Rigid Pavement?
    Rigid pavements are generally constructed of a reinforced concrete slab or more recently a continuously reinforced concrete road base.
    The pavement structure deflects very little under loading due to the high modulus of elasticity of their surface course.
    A rigid pavement structure is typically composed of a PCC or RCC surface course built on top of either
    the sub-grade or
    an underlying base course. 
  • Rigid Pavement:
    Typical Cross-section of a Rigid pavement
  • Why we (FFCL) preferred Rigid Pavement instead of Flexible Pavement (Carpet Road)?
    Rigid Pavement lasts much, much longer i.e. 30+ years compared to 5-10 years of flexible pavements.
    In the long run it is about half the cost to install and maintain. But the initial costs are somewhat high.
    Rigid pavement has the ability to bridge small imperfections in the sub grade.
    Less Maintenance cost and Continuous Traffic and Flow.
    Low thermal variation as compared to Flexible Pavement.
    Rigid Pavement has one draw back in terms of its repair i.e. we have to remove 2-3 panels instead of damaged portion as in case of Flexible pavements.
  • Pictorial View of Roads in FFCL
    KLP Road under construction
  • Roads in the Plant Area
  • Weigh Bridge:
    Salient Features:
    Total No of Weigh Bridges = 4
    Weigh Bridges constructed = 2
    Located near Gate # 1 or KLP Gate.
    No of Load Cells = 8
    Design Load measurement capacity = 120 Tons
    Designer
    Mechanical = Mettler Toledo
    Civil = Akbar & Associates
    Contractor = IPL
  • View of Weigh Bridge in FFCL
  • Nitro Phosphate (NP) Plant
  • Nitro Phosphate (NP) Plant:
    NP plant started from Prilling Tower in 2009.
    Estimated Civil Cost in Rs. = 279.1 million
    Civil Designer = NESPAK
    Civil Contractor = IPL
    80% of Civil work completed.
    Remaining 20% include Refrigeration area and Lime Drying unit, paints, brick masonry, and finishing works.
  • Nitro Phosphate (NP) Plant:
    NP Plant is divided into four parts
    Prilling Tower & Lift Well
    Main Building
    Substation
    CN & AN Section, Refrigeration Area, and Lime Drying Unit
  • Salient Features:
    Prilling Tower supported on 72 piles of length 27m.
    Prilling Tower has height of 67.9m and diameter of 19m.
    Lift Well has height of 70.1m, supported on 900mm thick raft foundation.
    Main Building has dimensions of 67.5m x 27.5m x 37.3m supported on raft foundation.
    Main Building comprise of 10 floors max on line 1-2.
    Substation comprise of 2 floors supported on isolated foundation.
  • Special Techniques adopted at NP Plant:
    Prilling Tower and Lift Well concrete done by using Slip Form Method.
    Strengthening of Columns has to be decided.
  • Slip Form Method:
    The most common method adopted for the construction of an RCC outer shell/prilling tower is by using the ‘slip form method’.
    In this method the form work for the concrete literally slips up cm by cm to produce an integrated concrete column in the form of wall.
    Continuous pouring of concrete ensures a joint free construction.
    At a rate of 0.3 meters per hour, this is consider as fast construction method.
  • Components of Slip Form Method:
    Slip form method is comprise of a complicated system of jacks and radial screws.
    Radial steel yokes, which have an inverted “U” at both ends, support the slip form shuttering all around the shell/prilling tower.
    Walers strengthen and keep the shuttering in place.
    The working deck and scaffolding is supported from the walers and yokes.
    The yokes are supported on hydraulic jacks, which move on jack rods embedded in the concrete.
    As the concrete pouring progresses the jacks lifts up the yokes, together with the decks and slip form.
    Screwed on pieces extend the jack rod as the work progresses.
    The entire system of decks and shuttering appear as if floating on top of the tower.
  • NP Prilling Tower
  • Top View of NP Prilling Tower
  • Strengthening of Columns:
    To increase the capacity of NP Main Building columns from 3500 Tons to 5500 Tons, the procedure that is used called Strengthening of columns.
    Why Strengthening of columns needed?
    Continuous changing of mechanical design of Cfit of NP main building, load on columns increased from 3500 Tons to 5500 Tons.
    To counter this problem, columns has to be strengthened by using concrete and steel jacketing.
  • View after Completion of Lift Well and Prilling Tower
    Main Building and CN Section under construction
    Lift Well
    Prilling Tower
    Main Building
    Sub Station
    CN, AN Section and LD Unit
  • Any Questions????