Permitting Solar, Wind And Geothermal Projects On Public And Tribal Lands - Presentation Transcript
Permitting Solar, Wind and Geothermal Projects on Public and Tribal Lands Presented by: Alan Waltner, Law Offices of Alan Waltner www.waltnerlaw.com
Overview
Goal - Making Sense of a Complex Regulatory System
Alternative Energy Developments and Their Typical Impacts
Key Recent Developments (EO, MOUs and Program EISs)
Preferential Treatment and Programmatic Documents – Benefits and Limitations
Overview of Federal, State, and Local Regulatory Programs that may Apply to Alternative Energy Developments
Special Considerations on Federal, State and Tribal Lands
Ways to Increase the Likelihood of Success
Discussion/Closing Remarks
Components of an Alternative Energy Project
Wind turbines
Photovoltaic panels or thermal collectors
Geothermal drilling rigs, production facilities, pipelines and generation facilities
Transmission lines
Roads
Buildings
Direct use facilities
Geothermal projects are generally relatively small in scale and impact compared to other renewable energy projects such as wind and solar
All components need to be considered
Stages of the Development Process
Area-wide Planning
Leasing
Exploration
Development
Production
Abandonment/closure/restoration
Each can be a trigger for regulatory requirements
Proposed Ivanpah Solar Power Project
Proposed Ivanpah Solar Power Project
The Geysers
Salton Sea Power Project (Proposed Unit 6)
Typical Environmental Impacts of an Alternative Energy Development
Visual impacts
Habitat disturbance (animals, plants, wetlands, old growth forests)
Cultural/historical resources impacts
Air emissions (construction equipment emissions, fugitive dust, hydrogen sulfide and carbon dioxide from geothermal development)
Water use (mirror washing, cooling towers)
Wastewater discharges
Hazardous materials and waste
Noise (wind and geothermal)
Land use compatibility (i.e. recreational uses)
Avoiding or reducing impacts will reduce the regulatory hurdles
Key Recent Developments
California Executive Order S-14-08
CEC/DFG Memorandum of Understanding (MOU)
State/Federal Memorandum of Understanding
BLM Programmatic EISs
Wind PEIS Completed June 2005
Geothermal PEIS Completed October 2008
Transmission Corridor PEIS Completed November 2008
Solar EIS Initiated May 2008 – Currently Underway
California Executive Order S-14-08
Issued November 17, 2008
Establishes a 33% Renewable Portfolio Standard (RPS) by 2020
SB 107 established a 20% RPS by 2010
Directs state agencies to “take all appropriate actions” to implement this target
Expedites permitting for all renewable energy projects
Adopts various actions, goals and targets of the CEC/DFG MOU
“ Scoping” sessions of the participating agencies held in March 2009
CEC/DFG Memorandum of Understanding
Also adopted on November 17, 2008
Does not waive or modify any environmental laws
Formalizes the Renewable Energy Action Team (REAT)
Directs creation of a “one-stop” process for permitting renewable energy projects
Requires the identification of priority areas for development by February 1, 2009, where permitting times will be reduced by 50%
Directs the initiation of a Natural Community Conservation Plan (NCCP), to be known as the Desert Renewable Energy Conservation Plan (DRECP)
Specifies the establishment of long term California Endangered Species Act assurances by June 1, 2012
State/Federal Memorandum of Understanding
Also adopted on November 17, 2008
Does not waive or modify any environmental laws
Includes the CEC, DFG, Bureau of Land Management (BLM) and US Fish and Wildlife Service (USFWS)
Establishes a Renewable Energy Permit Team (REPT) to coordinate and expedite project permitting
Commits the federal agencies to developing a joint desert energy conservation plan (DECP)
Directs establishment of Best Management Practices (BMPs) and other interim guidelines
Benefits and Limitations of Preferential Treatment
Preferential treatment can get your project to the top of the “to do” pile
Access to agency staff is enhanced
Access to agency management is increased if problems arise
State MOU principally addresses state endangered species, which generally are not a key hurdle
Neither MOU waives or modifies substantive environmental laws
Team building with agency staff is essential
BLM Programmatic PEISs
Address priority development areas in 11 western states, including California and Nevada
Includes more detailed analysis of certain near-term projects
Will streamline future NEPA analysis
Provides a template for the analysis of impacts
Includes generic best management practices that provide a menu of future mitigation options
Addresses cumulative impacts
Benefits of Programmatic Documents
Provide a template for project-level environmental reviews, including analytical methods, mitigation measures, and impact conclusions
May be adequate for project-level cumulative impact analyses
May reduce the scope of issues in subsequent legal challenges
Provides for public participation at an early stage
May be required by NEPA in any event
Limitations of Programmatic Documents
Judicial challenges generally can be brought any time within 6 years of adoption (federal documents only, such as EA, EIS, or BO)
Reliance on a subsequently invalidated document may undermine project-level environmental analyses
Given the typical lack of project-specific details, the analysis in the programmatic document may be too general to support project-level approvals
FEDERAL, STATE AND LOCAL REGULATIONS
The Importance of Location
Surface owner (USFWS, BLM, DOD, state, or tribe) must approve development
Applicable regulations will depend on whether land is federally, state or tribally owned
Complex issues of sovereignty and waiver need to be evaluated
Some lands are off-limits to any development
All aspects of the project (including offsite components such as transmission) need to be evaluated
Key Federal Regulatory Programs
BLM Regulations
National Environmental Policy Act (NEPA)
Endangered Species Act (ESA)
Clean Water Act – Section 404 (CWA/404)
Clean Water Act – Section 402 (CWA/402)
National Historic Preservation Act (Section 106)
BLM’s FLPMA Right of Way Grant Regulations (Wind and Solar)
Apply to wind and solar projects
Includes any terms, conditions, and stipulations that BLM determines to be in the public interest, which may include modifying the proposed use or changing the route or location of the facilities
Project must not unnecessarily damage the environment or result in unnecessary or undue degradation
Grantee must, to the extent practicable, comply with all existing and subsequently enacted, issued, or amended Federal laws and regulations and state laws and regulations applicable to the authorized use
Implementing policies adopted in April 2007 (solar) and December 2008 (wind)
BLM Geothermal Regulations
Geothermal-specific regulations apply
Include general requirements to –
Protect the quality of waters, air, and other natural resources, including wildlife, and natural history
Prevent “unnecessary or undue degradation” of land
Protect cultural, scenic, and recreational resources
Accommodate other land uses
Minimize noise
BLM Geothermal Regulations (continued)
Prohibit leasing in –
National Parks, National Recreation Areas, and Indian trust lands outside of Indian Reservations
Wilderness areas or wilderness study areas, except those study areas established by Congress where leasing is expressly allowed
May require collection of environmental data for up to 1 year before operations
Failure to comply with environmental requirements can be a basis for lease revocation
National Environmental Policy Act (NEPA)
Requires preparation of appropriate environmental documents in connection with “major federal actions”
Administered by federal lead agency
Generally requires preparation of an Environmental Impact Statement (EIS) or Environmental Assessment (EA)
Project NEPA documents may now be streamlined as a result of BLM’s 2008 Programmatic EIS
Federal Endangered Species Act (ESA)
ESA program is oriented around the listing of species and the designation of critical habitat
Administered by USFWS for most terrestrial species
Prohibits the unpermitted “take” of listed species, defined to include the destruction or modification of habitat where it directly leads to death or injury of listed wildlife
Significant penalties for illegal take and potential citizen suits
Take can be authorized either through Section 10 permits, or Section 7 consultation
Sage Grouse Habitat
Alternate ESA Permit Pathways
The ESA offers two pathways for addressing the prohibition against “take” of a species under Section 9
Section 7 -- Consultation with USFWS
Section 10 -- Incidental take permit (ITP) and habitat conservation plan (HCP)
Consultation triggered by action authorized , funded , or carried out by the federal agency
Applies to any non-federal project which has a “federal nexus” – e.g., federal approval (BLM lease, or Corps 404 permit) or federal funding
Can be “formal” or “informal” depending upon the degree of impact
Can be done on a programmatic basis
Section 7 Consultation
Standards Under ESA Section 7
USFWS evaluates whether the action, together with cumulative effects, is likely to “jeopardize” the continued existence of the species
If USFWS finds potential “jeopardy” it must identify reasonable and prudent alternatives
If USFWS finds no jeopardy, must identify measures to minimize impacts
Federal agencies also must ensure that their actions are “not likely to result in the destruction, or adverse modification” of any formally designated “critical habitat”
Only applies if no federal “nexus”
“ Taking” may be allowed by permit if it is “incidental to, and not the purpose of” an otherwise lawful activity
Requires a Habitat Conservation Plan (HCP) that:
Identifies impact minimization measures
Proposes species conservation measures
Guarantees funding
More complex than Section 7 consultation
Section 10 Permits and Habitat Conservation Plans
Clean Water Act Section 404
Prohibits the filling of wetlands and other waters without a permit
Administered by the US Army Corps of Engineers
Proponents should avoid wetlands and other “waters” where practicable
Section 404 Permits
Nationwide Permits (NWP)
Issued in the form of regulations, covering particular categories of activities (e.g., surveys, utility lines) with minor impacts
Individual Permits
Site specific and project specific
Must demonstrate that project represents the “least environmentally damaging practicable alternative” (LEDPA) by analyzing alternative sites and configurations for the project
Clean Water Act Section 402
Triggered by “point source” discharge to “navigable” waters or tributaries
Generally administered by the states
NPDES permit required
Also applies to storm water discharges from construction and industrial activities
State has issued general permits for most activities
Simple notice of intent process
Stormwater pollution prevention plan and best management practices required
Other Potentially Applicable Federal Programs
Migratory Bird Treaty Act
Fish and Wildlife Coordination Act
National Wilderness Preservation Act
Wild and Scenic Rivers Act
Safe Drinking Water Act
Resource Conservation and Recovery Act
Occupational Safety and Health Act
Location-specific statutes
Budget riders, etc.
Potentially Applicable State Regulatory Programs
Programs Generally Applicable to Federal Lands
Water quality certifications under CWA Section 401
Historic resource reviews (Section 106)
CEC review of projects over 50MW
CEQA functional equivalence approach
Air permits (NSR, PSD and Title V)
Wastewater discharge permits Under CWA Section 402, including storm water construction permits
Section 401 Water Quality Certification
Part of the Federal permitting process
Applies to “any applicant for a Federal license or permit . . . to conduct any activity . . . which may result in any discharge into the navigable waters
Requires Regional Water Quality Control Board certification as a precondition to federal permit issuance
Nominally limited to water quality issues
Regional Boards are expanding the range of issues that they are addressing
Creates incentive to avoid water quality impacts
National Historic Preservation Act (NHPA) Section 106
Section 106 requires consultation with State Historic Preservation Officer for projects affecting historic resources
BLM has development a National Protocol Agreement (PA) that governs how BLM meets these responsibilities in California and portions of Nevada
Streamlines the 106 process by eliminating case-by-case consultation on undertakings that culminate in “no historic properties affected” and “no adverse effect” findings
Other State Processes Applicable on Federal Lands
California Energy Commission (CEC) review
Only applies to projects 50 mw or greater
Process is CEQA functional equivalent
Can help support the federal process
Air permits
Regulatory hurdles vary considerably by location
Generic state equipment standards apply
Wastewater discharge and storm water permits
State Regulatory Programs Generally Applicable Only to State and Private Lands
California Environmental Quality Act (CEQA)
California Endangered Species Act (CESA)
Streambed Alteration Agreements (1602)
Need to look at all components of the project, both on-site and off-site
Potentially Applicable Local Regulatory Programs
General Plan
Zoning
Conditional use permit
Grading permit
Encroachment permit
Generally not applicable to projects on federal/tribal lands
Generally not applicable to state projects on state lands
Apply to projects on private lands (including offsite components such as transmission lines)
Special Considerations on BLM Lands
Most resources are located on BLM lands
BLM applies standards of Federal Land Policy Management Act (FLPMA)
Multiple use, sustained yield
Applicable management plans need to be considered
California Desert Conservation Area Plan
BLM has also established detailed leasing regulations
Special Considerations on Forest Service Lands
Authorization from both Forest Service and BLM required
Forest Service is responsible for pre-leasing environmental review
Project must be consistent with applicable forest management plan
BLM is responsible for operations approvals
Forest Service continues to be responsible for regulating roads and transmission lines
Special Considerations on Tribal Lands
Extremely complicated jurisdictional issues, particularly regarding the application of state and local requirements
Some tribes have a sophisticated regulatory program, others have little or none
Bureau of Indian Affairs generally approves leases and is the federal lead agency under NEPA
Would be “inventing the wheel” since there has been minimal activity on Tribal lands thus far
Tribes can obtain “treatment as a state” status under certain federal laws, including the CWA
Tribal Considerations not Limited to Reservations
Impacts on:
Sacred sites
Traditional cultural properties or landscapes
Past or present hunting, fishing, or gathering areas
Changes in hydrology or ecological conditions of springs, seeps, wetlands and streams that could be considered sacred or have historic use associations
Special Considerations on State Lands (in California)
State Lands Commission (SLC) is responsible for issuing leases on behalf of the State as owner of the resource
Division of Oil, Gas and Geothermal Resources (DOGGR) regulates geothermal wells
Generally DOGGR is the lead agency for CEQA purposes at the exploration stage (on both state and private lands)
Review includes evaluation of a drilling plan
State agency approvals must comply with CEQA
KEY RECOMMENDATIONS FOR MAKING THE PROCESS WORK
Key Strategies for Structuring the Permit Process
EIS/EIR prepared first as a core environmental document
Provides a definitive project description
Establishes a mitigation template
Provides comprehensive information on biological resources, including wetlands
Involves the agencies and the public
CEC staff evaluation of projects over 50MW is a “functional equivalent” that can serve the same role (example, solar MOU)
Key Strategies for Structuring the Permit Process (continued)
Integrate environmental planning into the initial stages of project planning
Prepare a detailed regulatory analysis
Consider environmental constraints and avoid them where possible
Permitting Solar, Wind and Geothermal Projects on P more
Permitting Solar, Wind and Geothermal Projects on Public and Tribal Lands
Evaluates the Bureau of Land Management, Endangered Species Act, National Environmental Policy Act and other regulatory programs that apply to alternative energy developments less
0 comments
Post a comment