SlideShare a Scribd company logo
1 of 55
Download to read offline
© 2014 HDR, Inc., all rights reserved.
Presented by: Dan Becker, CCM, PMP, ENV SP
2015
Managing Project Risk
Through Alternative Project
Delivery
 Understand how using APD can reduce some risks on developing capital projects
 Identify reasons Owners are turning to “alternative” ways to delivering their projects
 Understand the benefits of alternative project delivery (APD) over traditional
design/bid/build
 Identify the risks in utilizing alternative project delivery.
 Understand the engineer’s role in executing projects using alternative delivery
approaches
2
Learning Objectives
 Risk Management
 Project Delivery Option Considerations
 Project Delivery Options
o Design/Build
o CM@R
 Key Elements for Successful APD
 Engineers role in Executing APD
3
Agenda
 Risk Management
 Project Delivery Option Considerations
 Project Delivery Options
o Design/Build
o CM@R
 Key Elements for Successful APD
 Engineers role in Executing APD
4
Agenda
 Risk as defined by ISO 31000
o The effect of uncertainty on objectives, whether
positive or negative
 Risk management is the identification, assessment, and
prioritization of risks
After risks are identified…..
 Coordinated and economical application of resources to minimize,
monitor, and control the probability and/or impact of events
5
What is Risk Management
Typical Project Risks
• Differing Site Conditions
• Delays
• Revised Regulations
• Restricted site access
• Errors and Omissions
• Ambiguities in the Documents
• Miscommunication
• Work added by the Owner
• Cumulative Impact of Changes
• Delays in Owner Furnished Items
 Strikes
 Material shortages
 Labor shortages
 Interference by other trades or contractors
 Third party (utilities) interferences/delays
 Natural Disasters
 Assigning risk to the party that can best manage the risk
 Risk sharing when it makes sense
 Dealing with issues as they arise
 Know your (and organization’s) tolerance for various risk and risk
management approaches
 Monitor and track progress towards mitigating risks
7
Critical Elements for an Effective
Risk Management Program
 If risks are assigned to the “wrong” party, it can be costly
 Assess the resources available as you develop and
implement your plan.
8
Select the Appropriate Method to
Deliver the Project and Manage Risk
 Risk Management
 Project Delivery Option Considerations
 Project Delivery Options
o Design/Build
o CM@R
 Key Elements for Successful APD
 Engineers role in Executing APD
9
Agenda
Changing the Paradigm
Public Owners are frustrated with
Design/Bid/Build/Claim project delivery
model
However
Public Owners and Contractors are
most familiar with Design/Bid/Build
project delivery model
10
Owners are Looking for Ways to
Manage/Reduce Risks
 Design/Bid/Build
 Design/Build
 CM @ Risk (aka GC/CM and CM/GC)
11
Primary Methods Used for Delivering
Projects
 Job Order Contracting
o Pre-Pricing items for developing construction costs
 P3 – Public Private Initiative
o Publicly or privately funded
o Usually design/build , could be operated
 IPD – Integrated Project Delivery12
Alternative Delivery Methods
 Project Characteristics
 Reasons to consider APD
 Know your organization
 Know your own style
13
Assess the Appropriate Delivery
Approach for your Project
 New, Remodel, Upgrade, or Expansion Project
 Unique Project Characteristics
o Compatibility with existing equipment and/or systems
o New Technologies
o Site Constraints
o Resource Constraints
o Operational Constraints
14
Project Characteristics
 Project Schedule
o Consent Decrees
o Market Conditions – first to market
o Construction Phasing
 Project Budgets/Costs
o Funding Sources
o Funding Partners
o Cash flow
15
Project Characteristics
 Resources to develop plans and specifications
 Does your organization need to stay involved in every step of the
design and construction
 Is your organization willing to let the contractor loose on the
development of the project
 Trust within the organization/between departments; how are
departmental disagreements resolved
 Is your procurement department adaptable
16
Know Your Organization
o Handling change
o APD requires a paradigm shift
• New ways of approaching a project
• APD requires working closely with the design team and contractor;
collaboration
o Challenging the status quo
• Challenge your organization’s way of doing business
• APD requires collaboration and negotiating skills
17
Know your own Style
 Too many claims at the end of the project
 Too many change orders
 Contract documents were not well coordinated
 Poor scheduling
 Dissatisfaction with the project outcome
o Mechanical/electrical system incompatibility
o Settling for lowest bid items vs. desired items
o Lack of cohesion with the team
“the surgery was a success, but the patient died!!!”
18
Why Owners are Looking
for a Change
19
 Risk Management
 Project Delivery Option Considerations
 Project Delivery Options
o Design/Build
o CM@R
 Key Elements for Successful APD
 Engineers role in Executing APD
20
Agenda
 CM@Risk (GC/CM or CM/GC)
o Selection based on qualifications and some pricing information
o Contractor brought in during the design process (Usually
around 30%)
 Design/Build
o Selection based on qualifications and price
o Single entity responsible for delivering the project; design and
construction (and operations in some instances)21
Primary Alternative Delivery Methods
 Collaboration between the Owner, Engineer and Contractor
 Owner maintains control of the design process
 CMR provides constructability review comments and
recommendations during the design phase
 CMR provides value engineering/analysis
recommendations during the design phase
 CMR has input into the construction phasing plan; CMR will
be responsible for implementation of that plan
23
Benefits of CM@Risk (CMAR)
 Shortened construction schedule
o Early award of project elements (subcontracts and/or equipment) can
reduce the overall project duration.
o Expedited submittal review process
 Reduction of claims
o Better coordination
o CM@R will work with design team to develop subcontract packages
o Construction phasing issues will be resolved early on
 Cost incentives
o Split savings at the end of the job
Benefits of CMAR
 Selection Criteria should focus on your requirements
 Owners can get hung up on negotiating the GMP
o Develop parameters for negotiating GMP
o GMP may be higher than going out for low bid
 Change orders will not be completely eliminated
o Differing site conditions may impact the project
o Owners may request changes
o Permitting authority changes
25
Managing Expectations for CMAR
CMAR Selection Criteria
Evaluation Criteria Points
Attendance at the Pre-Proposal Meeting and Site Tour 10
Firm’s Experience 100
Project Personnel 200
Approach to Executing the Project 100
Reference Checks 100
Project Financial Questionnaire 90
Interview 200
Price Proposals* 200
Total Points 1,000
* Price proposal usually includes overhead and profit. Some proposals have included
pre-construction phase services if they are well defined.
CMAR Bid Form
Description of Bid Item: % Fee Estimated GMP Amount
Percent Fee Amount
(% Fee x Estimated GMP) % $ 17,000,000 $ ________________
(Percent Fee Amount)
Specified General
Conditions Work $ ________________
Total Bid: $ ________________
CMAR Bid Form
28
Description of Bid Item: % Fee Estimated GMP Amount
Percent Fee Amount
(% Fee x Estimated GMP) % $ 17,000,000 $ ________________
(Percent Fee Amount)
Specified General
Conditions Work $ ________________
Total Bid: $ ________________
CMAR Bid Form
29
Description of Bid Item: % Fee Estimated GMP Amount
Percent Fee Amount
(% Fee x Estimated GMP) 7 % $ 17,000,000 $ 1,190,000.00
(Percent Fee Amount)
Specified General
Conditions Work $ 1,700,000.00
Total Bid: $ 2,890,000.00
 Quality management
o Owners need to monitor quality during construction (QA)
 Claims can still occur
o While a collaborative process, failing to comply with the
contract requirements can still lead to claims
30
Managing Expectations for CMAR
 Single source of accountability
o Contractor responsible for delivering an operating facility
o Contractor responsible for the design and construction
 Budget management
o Contractor develops a project within established budget
 Enhanced communication
o Direct communication/collaboration between the Engineer and
Contractor
o Contractor and engineer collaborate to use their creativity to reduce
costs and delivery time.
31
Benefits of Design/Build (D/B)
 Faster project delivery
o Construction can begin before completing the design
o Design documents may not need to be developed the same level
of detail as in the DBB method
 Quality Control
o Removes ambiguity that may arise in material and construction
specifications
o Engineer working for the builder
 Reduced design document related change orders
o Changes attributed to conflicts in the design documents
Benefits of D/B
 Change orders will not be completely eliminated
o Owners may request changes
o Differing site conditions may impact the project
o Permitting authority changes
 Quality management
o Owner needs to define quality standards in the RFP
o Owner needs to review design for compliance with the standards
defined in the contract documents
o Owners need to monitor quality during construction (QA)
33
Managing Expectations for D/B
Projects
 Selection Criteria should focus on your
requirements
 Claims can still occur
o While a collaborative process, failing to comply with
the contract requirements can still lead to claims
34
Managing Expectations for D/B
Projects
Selecting D/B
35
Evaluation Criteria Points
Attendance at the Pre-Proposal Meeting and Site Tour 10
Firm’s Experience 100
Project Personnel 200
Approach to Executing the Project 100
Reference Checks 100
Project Financial Questionnaire 90
Interview 200
Price Proposals* 200
Total Points 1,000
* Price proposal can include a lump sum cost for design and construction or variation
 Lump Sum D/B
o Many D/B projects have been awarded on both qualifications and price
with 30% design
o If the Owner wants changes during the design phase, it will need to
negotiate a change order.
 Progressive D/B
o D/B selected on qualifications and some pricing data; design effort,
overhead and profit
o After design 90% to 100% Owner and DB negotiate the construction costs
as either lump sum or GMP
36
Progressive D/B
Selecting D/B (Progressive)
37
Evaluation Criteria Points
Attendance at the Pre-Proposal Meeting and Site Tour 10
Firm’s Experience 100
Project Personnel 250
Approach to Executing the Project 150
Reference Checks 100
Project Financial Questionnaire 90
Interview 200
Price Proposals* 100
Total Points 1,000
* Price proposal usually includes overhead and profit. Some proposals have included
design services.
Selecting D/B (Progressive)
38
Evaluation Criteria Points
Attendance at the Pre-Proposal Meeting and Site Tour 10
Firm’s Experience 100
Project Personnel 250
Approach to Executing the Project 150
Reference Checks 100
Project Financial Questionnaire 90
Interview 200
Price Proposals* 100
Total Points 1,000
* Price proposal usually includes overhead and profit. Some proposals have included
design services.
 Risk Management
 Project Delivery Option Considerations
 Project Delivery Options
• Design/Build
• CM@R
 Key Elements for Successful APD
 Engineers role in Executing APD
39
Agenda
 Select the best delivery method for
your organization and project
 Confirm market conditions
o Are there firms that can successfully
deliver the project with the selected
method
 Is your team ready to meet the
challenge 40
Key Elements for a Successful APD
 Solicitation Document
o Spell out your expectations
o Define the rolls of the parties
o Define the selection criteria (including protest
procedures)
o Develop to the appropriate level of detail for the delivery
approach and project needs;
• Quality standards
• Collaboration and coordination expectations
41
Key Elements for a Successful APD
 The Owner needs to line up an experienced team to
manage the project
o Owner is responsible for the management of the contracts
o Owner needs to monitor the quality of the project
 Selection Process
o Well defined selection process
o Find the team that best meets your project needs
o Find the team that you feel most comfortable working with
Key Elements for a Successful APD
Selection of the Management Team is critical to
the success of a project
o Check the history of the team
• Check references
• Interview the team; how do they interact with each other and the
Owner during the interview?
• Has the team worked together?
• Has this team managed a CMR or design/build project before?
• Does the Contractor have a reputation of changing out team
members during the project?
Key Elements for a Successful APD
 Does the team understand your project issues
 How will the team resolve issues
o How has the Design/Build team resolved issues on past projects?
o Ask for specifics
 Has the team provided pre-construction
services on other projects
44
Key Elements for a Successful APD
 Risk Management
 Project Delivery Option Considerations
 Project Delivery Options
• Design/Build
• CM@R
 Key Elements for Successful APD
 Engineers role in Executing APD
45
Agenda
Engineers have a role as owner’s PM, design engineer on the
DB team, owner’s representative during execution of the work
 Project management
 Procurement
 Design
 Design Reviews
 Value Engineering
 Construction Administration
 Construction Inspection
46
Engineer’s Role in APD
 Provide project definition
 Provide the project budget and schedule
 Make recommendations of the appropriate
procurement process for the project
 Define the quality standards
 Chief Collaborator
47
Engineer’s Project Management
Role in APD
 Provide project definition
 Recommendation of the appropriate procurement process
for the project
 Identify the key elements for selecting the APD Contractor
 Review proposals
 Make recommendations on
selection of the team.
48
Engineer’s Role During Procurement
 Liaison between the DB and Owner’s organization
 Coordinate review of the design documents – 30%, 60%,
and 90%
o Document reviews within the organization
o Develop list and prioritize comments to be reviewed with DB
o Review comments to the DB
 Review submittals
 Review changes
49
Role of Owner’s Engineer in D/B
 Develop design documents – 30%, 60%, and 90%
o Review documents with DB team
o Review documents with the Owner
o Incorporate Owner’s comments into design documents
o Develop technical packages for subcontracts
 Respond to technical/design issues during construction
 Review submittals prior to installation
 Incorporate changes as they arise into the work.
50
Role of D/B’s Engineer
 Develop design documents – 30%, 60%, and 90%
o Review documents with the Contractor
o Incorporate Contractor comments/ recommendations into design
documents
o Develop technical packages for subcontracts
 Develop cost estimates
o Develop estimates at 30%, 60% and 90%
o Reconcile with the Contractor
51
Role of Engineer in CMAR
 Respond to technical/design/quality issues during
construction
 Review submittals prior to installation
 Develop changes to the work
 Periodic inspections including reviewing the work
for substantial and final completion
52
Role of Engineer in CMAR
 APD can aid you in managing risks associated with
project delivery
 Successful APD occurs when;
o You and your organization buy into the selected approach
o Assign risks to the party that can best manage those risks
o You take the time to develop a complete solicitation document to
select the right contractor
o You assemble the right team, (management team and contractor) to
deliver the APD
53
Conclusion
For follow-up questions,
please contact me at
425.468.1514 or
dan.becker@hdrinc.com
Thank you
for joining us today!
QUESTIONS?

More Related Content

What's hot

Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Constructionshillier38
 
DESIGN & BUILD
DESIGN & BUILDDESIGN & BUILD
DESIGN & BUILDWill Bennett
 
EPC Business Model
EPC Business ModelEPC Business Model
EPC Business Modelavnishnarula86
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxLisa Cooley, LEED AP
 
Construction Documents
Construction DocumentsConstruction Documents
Construction DocumentsAllan Berry
 
Guide to Construction Procurement Strategies
Guide to Construction Procurement StrategiesGuide to Construction Procurement Strategies
Guide to Construction Procurement StrategiesSarah Fox
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksPankaj K Sinha
 
Questions in notes
Questions in notesQuestions in notes
Questions in notesCKMCforstudents
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentationTimun Loh
 
Epc issues and recommendations
Epc issues and recommendationsEpc issues and recommendations
Epc issues and recommendationsubk1411
 
Capital Project Risk Survey
Capital Project Risk SurveyCapital Project Risk Survey
Capital Project Risk SurveyEric Ho
 
20080704 innovative approach in contracts and tender procurement management
20080704 innovative approach in contracts and tender procurement management20080704 innovative approach in contracts and tender procurement management
20080704 innovative approach in contracts and tender procurement managementraymond_wan2005
 
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...EMLI Indonesia
 
Construction process
Construction processConstruction process
Construction processMazen Al-Qadi
 
Bridging Gt Apr09
Bridging Gt Apr09Bridging Gt Apr09
Bridging Gt Apr09Jeff Hendrick
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryPMI Chennai Chapter
 
Procurement system
Procurement systemProcurement system
Procurement systemSyed Kashif Ali
 
Akinjiyan_Olufemi_DRP14-15 Submitted
Akinjiyan_Olufemi_DRP14-15 SubmittedAkinjiyan_Olufemi_DRP14-15 Submitted
Akinjiyan_Olufemi_DRP14-15 SubmittedOlufemi Isaac Akinjiyan
 

What's hot (20)

Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Construction
 
DESIGN & BUILD
DESIGN & BUILDDESIGN & BUILD
DESIGN & BUILD
 
ACH 121 Lecture 02 (Arch. Basic Services )
ACH 121 Lecture 02 (Arch. Basic Services )ACH 121 Lecture 02 (Arch. Basic Services )
ACH 121 Lecture 02 (Arch. Basic Services )
 
EPC Business Model
EPC Business ModelEPC Business Model
EPC Business Model
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptx
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
 
Guide to Construction Procurement Strategies
Guide to Construction Procurement StrategiesGuide to Construction Procurement Strategies
Guide to Construction Procurement Strategies
 
Procurement Methods
Procurement MethodsProcurement Methods
Procurement Methods
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract Risks
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
Epc issues and recommendations
Epc issues and recommendationsEpc issues and recommendations
Epc issues and recommendations
 
Capital Project Risk Survey
Capital Project Risk SurveyCapital Project Risk Survey
Capital Project Risk Survey
 
20080704 innovative approach in contracts and tender procurement management
20080704 innovative approach in contracts and tender procurement management20080704 innovative approach in contracts and tender procurement management
20080704 innovative approach in contracts and tender procurement management
 
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
 
Construction process
Construction processConstruction process
Construction process
 
Bridging Gt Apr09
Bridging Gt Apr09Bridging Gt Apr09
Bridging Gt Apr09
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
 
Procurement system
Procurement systemProcurement system
Procurement system
 
Akinjiyan_Olufemi_DRP14-15 Submitted
Akinjiyan_Olufemi_DRP14-15 SubmittedAkinjiyan_Olufemi_DRP14-15 Submitted
Akinjiyan_Olufemi_DRP14-15 Submitted
 

Similar to Alternative Delivery

Handout_Delivery Methods.pdf
Handout_Delivery Methods.pdfHandout_Delivery Methods.pdf
Handout_Delivery Methods.pdfsarmedwahab
 
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy pptCON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt2cd
 
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdfCCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdfChassyTesoro1
 
CompTIA Project+ Objectives
CompTIA Project+ ObjectivesCompTIA Project+ Objectives
CompTIA Project+ Objectivessombat nirund
 
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1Charles S. Maggio
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryMECandPMV
 
Nuclear Supply Chain Symposium - Canadian Contracting Models
Nuclear Supply Chain Symposium - Canadian Contracting ModelsNuclear Supply Chain Symposium - Canadian Contracting Models
Nuclear Supply Chain Symposium - Canadian Contracting ModelsThis account is closed
 
Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...Browne Jacobson LLP
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfMoncefMakni1
 
1._pmc_2019_day_1_project_initiation_and_planning_final.pptx
1._pmc_2019_day_1_project_initiation_and_planning_final.pptx1._pmc_2019_day_1_project_initiation_and_planning_final.pptx
1._pmc_2019_day_1_project_initiation_and_planning_final.pptxsheryl90
 
Changes in construction
Changes in constructionChanges in construction
Changes in constructionMohamed Abdalla
 
Changes in construction projects
Changes in construction projectsChanges in construction projects
Changes in construction projectsMohamed Abdalla
 
10 me667 chap2 project management
10 me667 chap2 project management10 me667 chap2 project management
10 me667 chap2 project managementPavan Kumar
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Lee Pei Gie
 

Similar to Alternative Delivery (20)

Handout_Delivery Methods.pdf
Handout_Delivery Methods.pdfHandout_Delivery Methods.pdf
Handout_Delivery Methods.pdf
 
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy pptCON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
 
Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]
 
Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]
 
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdfCCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
 
CompTIA Project+ Objectives
CompTIA Project+ ObjectivesCompTIA Project+ Objectives
CompTIA Project+ Objectives
 
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
 
Chapter 3- Contract Management
Chapter 3- Contract ManagementChapter 3- Contract Management
Chapter 3- Contract Management
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project delivery
 
Nuclear Supply Chain Symposium - Canadian Contracting Models
Nuclear Supply Chain Symposium - Canadian Contracting ModelsNuclear Supply Chain Symposium - Canadian Contracting Models
Nuclear Supply Chain Symposium - Canadian Contracting Models
 
ACH 231 Lecture 06 (Project Delivery)
ACH 231 Lecture 06 (Project Delivery)ACH 231 Lecture 06 (Project Delivery)
ACH 231 Lecture 06 (Project Delivery)
 
Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdf
 
1._pmc_2019_day_1_project_initiation_and_planning_final.pptx
1._pmc_2019_day_1_project_initiation_and_planning_final.pptx1._pmc_2019_day_1_project_initiation_and_planning_final.pptx
1._pmc_2019_day_1_project_initiation_and_planning_final.pptx
 
PASBA 2010 presentation
PASBA 2010 presentationPASBA 2010 presentation
PASBA 2010 presentation
 
Changes in construction
Changes in constructionChanges in construction
Changes in construction
 
Changes in construction projects
Changes in construction projectsChanges in construction projects
Changes in construction projects
 
10 me667 chap2 project management
10 me667 chap2 project management10 me667 chap2 project management
10 me667 chap2 project management
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 

More from American Society of Civil Engineers, Orange County Branch

More from American Society of Civil Engineers, Orange County Branch (20)

ASCE OC Luncheon - Sustainability in Transportation Part 2
ASCE OC Luncheon - Sustainability in Transportation Part 2ASCE OC Luncheon - Sustainability in Transportation Part 2
ASCE OC Luncheon - Sustainability in Transportation Part 2
 
ASCE OC Sustainability in Transportation Presentation Part 1
ASCE OC Sustainability in Transportation Presentation Part 1ASCE OC Sustainability in Transportation Presentation Part 1
ASCE OC Sustainability in Transportation Presentation Part 1
 
ASCE OC - EWRI: OCWD Mid-Basin Injection: Centennial Park Project
ASCE OC - EWRI: OCWD Mid-Basin Injection: Centennial Park ProjectASCE OC - EWRI: OCWD Mid-Basin Injection: Centennial Park Project
ASCE OC - EWRI: OCWD Mid-Basin Injection: Centennial Park Project
 
ASCE OC Branch - T&DI Luncheon - Delivering the State's First Diverging Diamo...
ASCE OC Branch - T&DI Luncheon - Delivering the State's First Diverging Diamo...ASCE OC Branch - T&DI Luncheon - Delivering the State's First Diverging Diamo...
ASCE OC Branch - T&DI Luncheon - Delivering the State's First Diverging Diamo...
 
ASCE OC Branch - Geo-Institute Dinner Presentation: Fundamentals of Torque Do...
ASCE OC Branch - Geo-Institute Dinner Presentation: Fundamentals of Torque Do...ASCE OC Branch - Geo-Institute Dinner Presentation: Fundamentals of Torque Do...
ASCE OC Branch - Geo-Institute Dinner Presentation: Fundamentals of Torque Do...
 
ASCE OC Geo Institute - Dinner Presentation - 08-15-2017
ASCE OC Geo Institute - Dinner Presentation - 08-15-2017ASCE OC Geo Institute - Dinner Presentation - 08-15-2017
ASCE OC Geo Institute - Dinner Presentation - 08-15-2017
 
Interaction of MSE Abutments with Superstructures under Seismic Loading
Interaction of MSE Abutments with Superstructures under Seismic LoadingInteraction of MSE Abutments with Superstructures under Seismic Loading
Interaction of MSE Abutments with Superstructures under Seismic Loading
 
Wilshire Grand Redevelopment Project
Wilshire Grand Redevelopment ProjectWilshire Grand Redevelopment Project
Wilshire Grand Redevelopment Project
 
Jessica Cassman on ENVISION 10/20/16
Jessica Cassman on ENVISION 10/20/16Jessica Cassman on ENVISION 10/20/16
Jessica Cassman on ENVISION 10/20/16
 
Beth Breitenbach on ENVISION 10/20/16
Beth Breitenbach on ENVISION 10/20/16Beth Breitenbach on ENVISION 10/20/16
Beth Breitenbach on ENVISION 10/20/16
 
Doug Sereno on ENVISION 10/20/16
Doug Sereno on ENVISION 10/20/16Doug Sereno on ENVISION 10/20/16
Doug Sereno on ENVISION 10/20/16
 
The State of Orange County's Infrastructure - 2016 Report Card
The State of Orange County's Infrastructure - 2016 Report CardThe State of Orange County's Infrastructure - 2016 Report Card
The State of Orange County's Infrastructure - 2016 Report Card
 
ASCE OC Geo-Institute Luncheon - ARTIC: Anaheim Regional Transportation Inter...
ASCE OC Geo-Institute Luncheon - ARTIC: Anaheim Regional Transportation Inter...ASCE OC Geo-Institute Luncheon - ARTIC: Anaheim Regional Transportation Inter...
ASCE OC Geo-Institute Luncheon - ARTIC: Anaheim Regional Transportation Inter...
 
Autonomous Vehicles and Reducing GHG
Autonomous Vehicles and Reducing GHGAutonomous Vehicles and Reducing GHG
Autonomous Vehicles and Reducing GHG
 
Hyperxite sponsor packet_v2.4 (4)
Hyperxite sponsor packet_v2.4 (4)Hyperxite sponsor packet_v2.4 (4)
Hyperxite sponsor packet_v2.4 (4)
 
Transforming Transportation at the Speed of Sound
Transforming Transportation at the Speed of SoundTransforming Transportation at the Speed of Sound
Transforming Transportation at the Speed of Sound
 
ASCE Seawater Desalination Project at Huntington Beach - Poseidon Water
ASCE Seawater Desalination Project at Huntington Beach - Poseidon WaterASCE Seawater Desalination Project at Huntington Beach - Poseidon Water
ASCE Seawater Desalination Project at Huntington Beach - Poseidon Water
 
Hyperxite sponsor packet_v2.4
Hyperxite sponsor packet_v2.4Hyperxite sponsor packet_v2.4
Hyperxite sponsor packet_v2.4
 
TTG Luncheon 4.6.2016 - OC Streetcar
TTG Luncheon 4.6.2016 - OC StreetcarTTG Luncheon 4.6.2016 - OC Streetcar
TTG Luncheon 4.6.2016 - OC Streetcar
 
Can a GSA be formed within a Partially Adjudicated Basin? | Brian Powell, EMWD
Can a GSA be formed within a Partially Adjudicated Basin? | Brian Powell, EMWDCan a GSA be formed within a Partially Adjudicated Basin? | Brian Powell, EMWD
Can a GSA be formed within a Partially Adjudicated Basin? | Brian Powell, EMWD
 

Recently uploaded

Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxVelmuruganTECE
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
The SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsThe SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsDILIPKUMARMONDAL6
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the weldingMuhammadUzairLiaqat
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsSachinPawar510423
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdfCaalaaAbdulkerim
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Steel Structures - Building technology.pptx
Steel Structures - Building technology.pptxSteel Structures - Building technology.pptx
Steel Structures - Building technology.pptxNikhil Raut
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 

Recently uploaded (20)

Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptx
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
The SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsThe SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teams
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the welding
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documents
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdf
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Steel Structures - Building technology.pptx
Steel Structures - Building technology.pptxSteel Structures - Building technology.pptx
Steel Structures - Building technology.pptx
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 

Alternative Delivery

  • 1. © 2014 HDR, Inc., all rights reserved. Presented by: Dan Becker, CCM, PMP, ENV SP 2015 Managing Project Risk Through Alternative Project Delivery
  • 2.  Understand how using APD can reduce some risks on developing capital projects  Identify reasons Owners are turning to “alternative” ways to delivering their projects  Understand the benefits of alternative project delivery (APD) over traditional design/bid/build  Identify the risks in utilizing alternative project delivery.  Understand the engineer’s role in executing projects using alternative delivery approaches 2 Learning Objectives
  • 3.  Risk Management  Project Delivery Option Considerations  Project Delivery Options o Design/Build o CM@R  Key Elements for Successful APD  Engineers role in Executing APD 3 Agenda
  • 4.  Risk Management  Project Delivery Option Considerations  Project Delivery Options o Design/Build o CM@R  Key Elements for Successful APD  Engineers role in Executing APD 4 Agenda
  • 5.  Risk as defined by ISO 31000 o The effect of uncertainty on objectives, whether positive or negative  Risk management is the identification, assessment, and prioritization of risks After risks are identified…..  Coordinated and economical application of resources to minimize, monitor, and control the probability and/or impact of events 5 What is Risk Management
  • 6. Typical Project Risks • Differing Site Conditions • Delays • Revised Regulations • Restricted site access • Errors and Omissions • Ambiguities in the Documents • Miscommunication • Work added by the Owner • Cumulative Impact of Changes • Delays in Owner Furnished Items  Strikes  Material shortages  Labor shortages  Interference by other trades or contractors  Third party (utilities) interferences/delays  Natural Disasters
  • 7.  Assigning risk to the party that can best manage the risk  Risk sharing when it makes sense  Dealing with issues as they arise  Know your (and organization’s) tolerance for various risk and risk management approaches  Monitor and track progress towards mitigating risks 7 Critical Elements for an Effective Risk Management Program
  • 8.  If risks are assigned to the “wrong” party, it can be costly  Assess the resources available as you develop and implement your plan. 8 Select the Appropriate Method to Deliver the Project and Manage Risk
  • 9.  Risk Management  Project Delivery Option Considerations  Project Delivery Options o Design/Build o CM@R  Key Elements for Successful APD  Engineers role in Executing APD 9 Agenda
  • 10. Changing the Paradigm Public Owners are frustrated with Design/Bid/Build/Claim project delivery model However Public Owners and Contractors are most familiar with Design/Bid/Build project delivery model 10 Owners are Looking for Ways to Manage/Reduce Risks
  • 11.  Design/Bid/Build  Design/Build  CM @ Risk (aka GC/CM and CM/GC) 11 Primary Methods Used for Delivering Projects
  • 12.  Job Order Contracting o Pre-Pricing items for developing construction costs  P3 – Public Private Initiative o Publicly or privately funded o Usually design/build , could be operated  IPD – Integrated Project Delivery12 Alternative Delivery Methods
  • 13.  Project Characteristics  Reasons to consider APD  Know your organization  Know your own style 13 Assess the Appropriate Delivery Approach for your Project
  • 14.  New, Remodel, Upgrade, or Expansion Project  Unique Project Characteristics o Compatibility with existing equipment and/or systems o New Technologies o Site Constraints o Resource Constraints o Operational Constraints 14 Project Characteristics
  • 15.  Project Schedule o Consent Decrees o Market Conditions – first to market o Construction Phasing  Project Budgets/Costs o Funding Sources o Funding Partners o Cash flow 15 Project Characteristics
  • 16.  Resources to develop plans and specifications  Does your organization need to stay involved in every step of the design and construction  Is your organization willing to let the contractor loose on the development of the project  Trust within the organization/between departments; how are departmental disagreements resolved  Is your procurement department adaptable 16 Know Your Organization
  • 17. o Handling change o APD requires a paradigm shift • New ways of approaching a project • APD requires working closely with the design team and contractor; collaboration o Challenging the status quo • Challenge your organization’s way of doing business • APD requires collaboration and negotiating skills 17 Know your own Style
  • 18.  Too many claims at the end of the project  Too many change orders  Contract documents were not well coordinated  Poor scheduling  Dissatisfaction with the project outcome o Mechanical/electrical system incompatibility o Settling for lowest bid items vs. desired items o Lack of cohesion with the team “the surgery was a success, but the patient died!!!” 18 Why Owners are Looking for a Change
  • 19. 19
  • 20.  Risk Management  Project Delivery Option Considerations  Project Delivery Options o Design/Build o CM@R  Key Elements for Successful APD  Engineers role in Executing APD 20 Agenda
  • 21.  CM@Risk (GC/CM or CM/GC) o Selection based on qualifications and some pricing information o Contractor brought in during the design process (Usually around 30%)  Design/Build o Selection based on qualifications and price o Single entity responsible for delivering the project; design and construction (and operations in some instances)21 Primary Alternative Delivery Methods
  • 22.
  • 23.  Collaboration between the Owner, Engineer and Contractor  Owner maintains control of the design process  CMR provides constructability review comments and recommendations during the design phase  CMR provides value engineering/analysis recommendations during the design phase  CMR has input into the construction phasing plan; CMR will be responsible for implementation of that plan 23 Benefits of CM@Risk (CMAR)
  • 24.  Shortened construction schedule o Early award of project elements (subcontracts and/or equipment) can reduce the overall project duration. o Expedited submittal review process  Reduction of claims o Better coordination o CM@R will work with design team to develop subcontract packages o Construction phasing issues will be resolved early on  Cost incentives o Split savings at the end of the job Benefits of CMAR
  • 25.  Selection Criteria should focus on your requirements  Owners can get hung up on negotiating the GMP o Develop parameters for negotiating GMP o GMP may be higher than going out for low bid  Change orders will not be completely eliminated o Differing site conditions may impact the project o Owners may request changes o Permitting authority changes 25 Managing Expectations for CMAR
  • 26. CMAR Selection Criteria Evaluation Criteria Points Attendance at the Pre-Proposal Meeting and Site Tour 10 Firm’s Experience 100 Project Personnel 200 Approach to Executing the Project 100 Reference Checks 100 Project Financial Questionnaire 90 Interview 200 Price Proposals* 200 Total Points 1,000 * Price proposal usually includes overhead and profit. Some proposals have included pre-construction phase services if they are well defined.
  • 27. CMAR Bid Form Description of Bid Item: % Fee Estimated GMP Amount Percent Fee Amount (% Fee x Estimated GMP) % $ 17,000,000 $ ________________ (Percent Fee Amount) Specified General Conditions Work $ ________________ Total Bid: $ ________________
  • 28. CMAR Bid Form 28 Description of Bid Item: % Fee Estimated GMP Amount Percent Fee Amount (% Fee x Estimated GMP) % $ 17,000,000 $ ________________ (Percent Fee Amount) Specified General Conditions Work $ ________________ Total Bid: $ ________________
  • 29. CMAR Bid Form 29 Description of Bid Item: % Fee Estimated GMP Amount Percent Fee Amount (% Fee x Estimated GMP) 7 % $ 17,000,000 $ 1,190,000.00 (Percent Fee Amount) Specified General Conditions Work $ 1,700,000.00 Total Bid: $ 2,890,000.00
  • 30.  Quality management o Owners need to monitor quality during construction (QA)  Claims can still occur o While a collaborative process, failing to comply with the contract requirements can still lead to claims 30 Managing Expectations for CMAR
  • 31.  Single source of accountability o Contractor responsible for delivering an operating facility o Contractor responsible for the design and construction  Budget management o Contractor develops a project within established budget  Enhanced communication o Direct communication/collaboration between the Engineer and Contractor o Contractor and engineer collaborate to use their creativity to reduce costs and delivery time. 31 Benefits of Design/Build (D/B)
  • 32.  Faster project delivery o Construction can begin before completing the design o Design documents may not need to be developed the same level of detail as in the DBB method  Quality Control o Removes ambiguity that may arise in material and construction specifications o Engineer working for the builder  Reduced design document related change orders o Changes attributed to conflicts in the design documents Benefits of D/B
  • 33.  Change orders will not be completely eliminated o Owners may request changes o Differing site conditions may impact the project o Permitting authority changes  Quality management o Owner needs to define quality standards in the RFP o Owner needs to review design for compliance with the standards defined in the contract documents o Owners need to monitor quality during construction (QA) 33 Managing Expectations for D/B Projects
  • 34.  Selection Criteria should focus on your requirements  Claims can still occur o While a collaborative process, failing to comply with the contract requirements can still lead to claims 34 Managing Expectations for D/B Projects
  • 35. Selecting D/B 35 Evaluation Criteria Points Attendance at the Pre-Proposal Meeting and Site Tour 10 Firm’s Experience 100 Project Personnel 200 Approach to Executing the Project 100 Reference Checks 100 Project Financial Questionnaire 90 Interview 200 Price Proposals* 200 Total Points 1,000 * Price proposal can include a lump sum cost for design and construction or variation
  • 36.  Lump Sum D/B o Many D/B projects have been awarded on both qualifications and price with 30% design o If the Owner wants changes during the design phase, it will need to negotiate a change order.  Progressive D/B o D/B selected on qualifications and some pricing data; design effort, overhead and profit o After design 90% to 100% Owner and DB negotiate the construction costs as either lump sum or GMP 36 Progressive D/B
  • 37. Selecting D/B (Progressive) 37 Evaluation Criteria Points Attendance at the Pre-Proposal Meeting and Site Tour 10 Firm’s Experience 100 Project Personnel 250 Approach to Executing the Project 150 Reference Checks 100 Project Financial Questionnaire 90 Interview 200 Price Proposals* 100 Total Points 1,000 * Price proposal usually includes overhead and profit. Some proposals have included design services.
  • 38. Selecting D/B (Progressive) 38 Evaluation Criteria Points Attendance at the Pre-Proposal Meeting and Site Tour 10 Firm’s Experience 100 Project Personnel 250 Approach to Executing the Project 150 Reference Checks 100 Project Financial Questionnaire 90 Interview 200 Price Proposals* 100 Total Points 1,000 * Price proposal usually includes overhead and profit. Some proposals have included design services.
  • 39.  Risk Management  Project Delivery Option Considerations  Project Delivery Options • Design/Build • CM@R  Key Elements for Successful APD  Engineers role in Executing APD 39 Agenda
  • 40.  Select the best delivery method for your organization and project  Confirm market conditions o Are there firms that can successfully deliver the project with the selected method  Is your team ready to meet the challenge 40 Key Elements for a Successful APD
  • 41.  Solicitation Document o Spell out your expectations o Define the rolls of the parties o Define the selection criteria (including protest procedures) o Develop to the appropriate level of detail for the delivery approach and project needs; • Quality standards • Collaboration and coordination expectations 41 Key Elements for a Successful APD
  • 42.  The Owner needs to line up an experienced team to manage the project o Owner is responsible for the management of the contracts o Owner needs to monitor the quality of the project  Selection Process o Well defined selection process o Find the team that best meets your project needs o Find the team that you feel most comfortable working with Key Elements for a Successful APD
  • 43. Selection of the Management Team is critical to the success of a project o Check the history of the team • Check references • Interview the team; how do they interact with each other and the Owner during the interview? • Has the team worked together? • Has this team managed a CMR or design/build project before? • Does the Contractor have a reputation of changing out team members during the project? Key Elements for a Successful APD
  • 44.  Does the team understand your project issues  How will the team resolve issues o How has the Design/Build team resolved issues on past projects? o Ask for specifics  Has the team provided pre-construction services on other projects 44 Key Elements for a Successful APD
  • 45.  Risk Management  Project Delivery Option Considerations  Project Delivery Options • Design/Build • CM@R  Key Elements for Successful APD  Engineers role in Executing APD 45 Agenda
  • 46. Engineers have a role as owner’s PM, design engineer on the DB team, owner’s representative during execution of the work  Project management  Procurement  Design  Design Reviews  Value Engineering  Construction Administration  Construction Inspection 46 Engineer’s Role in APD
  • 47.  Provide project definition  Provide the project budget and schedule  Make recommendations of the appropriate procurement process for the project  Define the quality standards  Chief Collaborator 47 Engineer’s Project Management Role in APD
  • 48.  Provide project definition  Recommendation of the appropriate procurement process for the project  Identify the key elements for selecting the APD Contractor  Review proposals  Make recommendations on selection of the team. 48 Engineer’s Role During Procurement
  • 49.  Liaison between the DB and Owner’s organization  Coordinate review of the design documents – 30%, 60%, and 90% o Document reviews within the organization o Develop list and prioritize comments to be reviewed with DB o Review comments to the DB  Review submittals  Review changes 49 Role of Owner’s Engineer in D/B
  • 50.  Develop design documents – 30%, 60%, and 90% o Review documents with DB team o Review documents with the Owner o Incorporate Owner’s comments into design documents o Develop technical packages for subcontracts  Respond to technical/design issues during construction  Review submittals prior to installation  Incorporate changes as they arise into the work. 50 Role of D/B’s Engineer
  • 51.  Develop design documents – 30%, 60%, and 90% o Review documents with the Contractor o Incorporate Contractor comments/ recommendations into design documents o Develop technical packages for subcontracts  Develop cost estimates o Develop estimates at 30%, 60% and 90% o Reconcile with the Contractor 51 Role of Engineer in CMAR
  • 52.  Respond to technical/design/quality issues during construction  Review submittals prior to installation  Develop changes to the work  Periodic inspections including reviewing the work for substantial and final completion 52 Role of Engineer in CMAR
  • 53.  APD can aid you in managing risks associated with project delivery  Successful APD occurs when; o You and your organization buy into the selected approach o Assign risks to the party that can best manage those risks o You take the time to develop a complete solicitation document to select the right contractor o You assemble the right team, (management team and contractor) to deliver the APD 53 Conclusion
  • 54. For follow-up questions, please contact me at 425.468.1514 or dan.becker@hdrinc.com Thank you for joining us today!