CorTek General Overview

Loading...

Flash Player 9 (or above) is needed to view presentations.
We have detected that you do not have it on your computer. To install it, go here.

0 comments

Post a comment

    Post a comment
    Embed Video
    Edit your comment Cancel

    Favorites, Groups & Events

    CorTek General Overview - Presentation Transcript

    1. Core Construction System Presented By: Aaron Rutledge CorTek, Inc. 999 Van Buren Ave. Loveland, CO 80537 Phone: 970-663-2222 Fax: 970-663-9969 [email_address] www.corteksystems.com
    2. Service Cores
      • 2+ hour fire rated egress shaft required for buildings over 2 stories
      • Concrete a cost effective material to create this fire separation and resulting vertical structure
      • Monolithic concrete structure naturally becomes integral part of buildings lateral system
    3. Problematic for Construction
      • Cores must be in place before surrounding framing can be installed
      • Slow to construct with highly unpredictable schedules
      • Quality issues frequently arise
      • Dangerous
      “ Like rolling the dice on every project”
    4. A better way…
      • Free up site schedule and resources by modularizing core off site in a specialized factory set up for quality and efficiency
    5. The CorTek Core Construction System
      • Stay-in-place modular form system for concrete core structures
      • Factory built modules stack like building blocks.
      • Custom-built to the specific requirements of each project.
    6.  
    7. Features:
      • High tolerance, all-steel construction.
      • Modules are load-bearing before concrete.
      • Pre-installed:
        • Horizontal Rebar
        • Stairs
        • Embed Plates and Shear Tabs
        • Ledger Angle
        • Elevator Divider Beams
        • Optional Finishing Connectors (hat channel, masonry ties)
    8. A Load Bearing Form
      • Vertical and horizontal structural elements support construction loads and allow form to be modularized.
      • Structural skeleton allows for support of stairs, landings, structural framing, scaffolding, personnel, and other construction loads
      • Form does not require stripping
      • Finished wall structurally equal to a conventional 8”-12” CIP concrete wall
    9. Optional wall thickness Effective thickness: 8” 10” 12” Actual thickness: 10” 12” 14” Because of the much higher tolerances of the CorTek System, the resulting finished wall assembly can be thinner than conventional methods for many applications.
    10. Pre-installed stairs
    11. Railings shipped ready to bolt on
    12. Optional Stair & Railing Designs Pan treads Checkered plate treads Grating treads Parallel tube rails Picket rails Wire mesh rails
    13. Beam Attachments and Ledger Angle Pre-installed
    14. Benefits:
      • Immediate presence of stairs allows trades early and safe access to structure
      • Elimination of many dangerous field operations
      • Can eliminate the need for scaffolding
      • Reduction of poor fit-up and coordination problems among trades
      • Cores generally part of the critical path—the CorTek system cannot be beat for speed--reducing overall schedule by weeks or months on most projects.
    15. Job Site Efficiency >Enabling Lean Construction
      • Drastic reduction of field labor.
      • Just In Time Delivery minimizes site congestion.
      • Core construction can be concurrent with frame construction.
      • Re-work from misplaced embeds, doors, bulging concrete and leaning or twisted towers eliminated
      • Several cores can be constructed simultaneously
    16. Safety—A Job Site’s Most Important Consideration Moving formwork to a controlled factory environment eliminates many dangerous field operations
    17.  
    18.  
    19. Where’s the rest of the structure?
    20. Concurrent Framing Framing does not wait for formwork—saving weeks to months on project schedule
    21. Quality
      • Parametric modeling essentially eliminates detailing mistakes.
      • Controlled manufacturing environment.
      • Multiple fail safing operations.
      • Rigid Quality Assurance Program
      • Jigs, Fixtures and Design provide extraordinarily tight tolerances
    22. Green Benefits
      • No wood forms and resulting site waste
      • No form oil
      • Greatly minimizes site labor installation
      • Recycled and recyclable steel used in construction.
      • Perfect delivery method for high volume fly ash concrete
    23. Target Projects
        • MULTI-STORY BUILDINGS OF ALL TYPES . . . . . .
        • Structural steel framed buildings.
        • Wood framed buildings.
        • Concrete framed buildings.
        • Industrial Structures.
        • Current production equipment tooled for 8” - 12” thick walls to target 3-12 story buildings.
    24. Attachment can be made to all floor framing materials
    25.  
    26.  
    27.  
    28.  
    29.  
    30.  
    31.  
    32. Design
      • Direct Replacement for Conventional Cast-In-Place—no extra work required for Architect or Structural Engineer.
      • Conventional concrete rebar configurations.
      • No proprietary design methods or material strengths.
      • No requirement for special code approvals.
    33. Complete Detailed Shop Drawings
      • Stair and Railing Layouts
      • Rebar details
      • Framing and Floor Connections
      • 3D Revit model available for each project.
    34. Competition
      • Price for a typical stair core story with 2 flights of stairs, 8 embeds and ledger angle at floor perimeter. Price includes placed concrete and all installation costs
      • Conventional Methods
        • Cast-In-Place: $38,574/Story*
        • Pre-Cast: $49,219/Story*
        • Masonry: $34,346/Story*
      • CorTek: $36,786
      • *Based on independent estimate provided by the Icon Group September 2008
    35. Installation Sequence and Details
    36. Foundation Embeds
    37. Base Module
    38. Core Leveling Detail
    39.  
    40. Install Vertical Reinforcement
    41. Vertical Reinforcement In Place
    42. Base Connection Weld
    43. Going Vertical
    44. Module Alignment Detail
    45. Non-contact Vertical Splice Bars
    46. Non-contact Vertical Rebar Splices
    47. Vertical steel attached to each module
    48. Vertical Bar Alignment Guides
    49. Contractor drops in steel beam and bolts it together.
    50. Concrete Placing Form designed for approximately 6 feet/hour of concrete Up to 18 foot lifts can be poured at a time. Removable weep hole plugs aid placing concrete to correct pour heights Web bar spacing allows for easy penetration of pumper tip hose and vibrator
    51. Interior and Exterior finishes
      • Exterior
      • Exposed Metal
      • Drywall
      • Masonry
      • Stucco
      • Thin set brick
      • Interior
      • Exposed Metal
      • Drywall
      • Hardboard Panel
      • Tile
    52. Optional pre-installed hat channel accommodates exceptionally thin finish face
    53. Hat-channel can be field shot directly on to walls and finished conventionally
    54. Optional pre-installed masonry tie backs accelerate masonry field work
    55. Exposed metal interior is an aesthetic alternate to concrete
    56. Difficult/slow/error-prone field work brought into a controlled factory environment set up for efficiency and quality. Computer aided parametric design used for rapid parametric structural and architectural design. Decreased site congestion increases project flow. Freeing site schedule from concrete core schedule increases “battle plan” options. An Advanced Building System
    57. Conclusion
      • Eliminates the need for scaffolding and forms
      • Reduces Critical Path construction time associated with building cores
      • Pre-installed stairs
      • Pre-installed floor and beam connections
      • Modules do not require stripping.
      • CorTek cores are individually designed for each job in a controlled environment
      • Simultaneous construction with floor framing
      • Structurally equivalent to 8”-12” CIP concrete shear wall.
      • Cost effective
    58. Questions & Comments
    59. www.corteksystems.com
    SlideShare Zeitgeist 2009

    + Aaron RutledgeAaron Rutledge Nominate

    custom

    143 views, 0 favs, 0 embeds more stats

    More info about this document

    © All Rights Reserved

    Go to text version

    • Total Views 143
      • 143 on SlideShare
      • 0 from embeds
    • Comments 0
    • Favorites 0
    • Downloads 0
    Most viewed embeds

    more

    All embeds

    less

    Flagged as inappropriate Flag as inappropriate
    Flag as inappropriate

    Select your reason for flagging this presentation as inappropriate. If needed, use the feedback form to let us know more details.

    Cancel
    File a copyright complaint
    Having problems? Go to our helpdesk?

    Categories