TITLE :  URBAN TRANSPORTATION            ASSIGNMENT 1NAME        : MUHAMMAD BIN RAMLANMATRIX NO   : P 57600SUBJECT     : K...
QUESTION ASSIGNMENT 1   A proposed development will be constructed near the Putrajaya-Kajang highway as   shown in Figure ...
SOLUTION ASSIGNMENT 1a) Compute production and attraction      Land Use          Residential Unit        Production rate  ...
c) Compute the number of each transport mode entering and exiting the development inthe morning       Number of each vehic...
Upcoming SlideShare
Loading in...5
×

KA6564 Assignment 1

247

Published on

0 Comments
1 Like
Statistics
Notes
  • Be the first to comment

No Downloads
Views
Total Views
247
On Slideshare
0
From Embeds
0
Number of Embeds
1
Actions
Shares
0
Downloads
8
Comments
0
Likes
1
Embeds 0
No embeds

No notes for slide

Transcript of "KA6564 Assignment 1"

  1. 1. TITLE : URBAN TRANSPORTATION ASSIGNMENT 1NAME : MUHAMMAD BIN RAMLANMATRIX NO : P 57600SUBJECT : KKKA 6564YEAR : 2011/2012LECTURER : PROF IR DR RIZA ATIQ O.K. RAHMAT
  2. 2. QUESTION ASSIGNMENT 1 A proposed development will be constructed near the Putrajaya-Kajang highway as shown in Figure 1. Proposed Development To Putrajaya To Kajang Figure 1 The development consists of an office building with 102,000 square meter floor area and a 295 units condominium tower. It is expected will attract 3.3 person-trips per 100 square meter floor area per hour in the morning, whereas the condominium will produce 1.45 person-trips per unit per hour. It is estimated that only 16% of the generated trip by the condominium destine to the office building in the development area. Mode Split Average Capacity Car 55% 1.9 Motorcycle 9% 1.15 Bus 36% 50 You are required to:a) Compute production and attraction.b) Compute the number of persons entering and exiting the development area per hour in the morning.c) Compute the number of each transport mode entering and exiting the development in the morning.d) If 80% of the attraction is from Kajang, determine the minimum width of the bridge.
  3. 3. SOLUTION ASSIGNMENT 1a) Compute production and attraction Land Use Residential Unit Production rate Morning production (person-trip / unit / (person-trip / hr) hr)Condominium 295 1.45 428 Land Use Residential Unit (m2) Attraction rate Morning Attraction (person-trip / m2 / (person-trip / hr) hr)Office building (102000/100) = 1020 3.3 3366b) Compute the number of persons entering and exiting the development area per hour inthe morning Land Use Number of person Number of persons Number of persons from the entering the exiting the condominium development area development area (person-trip / hr) (person-trip / hr) destine to the office building in the development area (person-trip / hr) Development area (16/100) x 428 = 68 3366 – 68 = 3298 428 – 68 = 360
  4. 4. c) Compute the number of each transport mode entering and exiting the development inthe morning Number of each vehicle entering development: Land Use Entering Modal Split Person Trip Number of vehicles car motorcycle bus car motorcycle bus car motorcycle busDevelopment 3298 55% 9% 36% 1814 297 1187 955 258 24 area TOTAL 955 258 24 Number of each vehicle exiting development: Land Use Exiting Modal Split Person Trip Number of vehicles car motorcycle bus car motorcycle bus car motorcycle bus Development 360 55% 9% 36% 198 32 130 104 28 3 area TOTAL 955 258 24D) If 80% of the attraction is from Kajang, determine the minimum width of the bridge. Land Use Attraction from kajang (person-trip / hr) Development area (80/100) x 3298 = 2638 Numbers Quantity Cars 2638/1.9 = 1388 Lane *For Malaysian Standard: 1800 Cars Per Link 1388/1800 = 0.77 ≈ 1 Items Description Bridge Width *assume 1 lane is 3.5m, road shoulder is 1m, marginal strip is 0.5m. Therefore, bridge width for two lane is: = (3.5m + 1m + 0.5m) x 2 = 10m

×