ADTEC REPORT 16 MAY 2009

573
views

Published on

Published in: Technology, Business

0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
573
On Slideshare
0
From Embeds
0
Number of Embeds
2
Actions
Shares
0
Downloads
5
Comments
0
Likes
0
Embeds 0
No embeds

Report content
Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
No notes for slide

Transcript

  • 1. LAPORAN KEMAJUAN PROJEK NO.21 ‘MEI 2009’ PROJEK ADTEC TAIPING KEMENTERIAN SUMBER MANUSIA JABATAN KERJA RAYA MALAYSIA KAMALBINA SDN. BHD PEMILIK PEGARAH PROJEK KONTRAKTOR R&B
  • 2. ADTEC TAIPING LOKASI PROJEK
  • 3. BANGUNAN PENTADBIRAN BENGKEL TEK. MAKLUMAT & JAMIN KUALITI DEWAN BESAR PUSAT SUMBER DEWAN KULIAH LOBI UTAMA KAFETERIA MIKRO ELEKTRONIK KOMPOSIT PLASTIK M&E PLANT ROOM 1 TNB SUB STATION SERAMIK M&E PLANT ROOM 2 GARAJ KENDERAAN ASRAMA LELAKI ASRAMA PEREMPUAN DEWAN MAKAN SURAU KELAS F KELAS G KUARTERS B, C, C&D PELAN TAPAK ADTEC TAIPING
  • 4. KEMAJUAN KERJA FIZIKAL JADUAL : 79.69 % SEBENAR : 80.28 % KESELURUHAN : 0.60 % TARIKH LAPORAN : 16 MEI 2009
  • 5. KEMAJUAN KERJA KEWANGAN JADUAL : 79.06 % SEBENAR : 79.61 % KESELURUHAN : 0.55 % TARIKH LAPORAN : 16 MEI 2009
  • 6.  
  • 7. KEMAJUAN KERJA FIZIKAL - DEWAN BESAR BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 100% 85.77% - 14.23% MEI 09’ 88.35% 92.38% 4.03% MECHANICAL PLANNED ACTUAL AIR COND 89.36% 85.00% FIRE FIGHTING 63.03% 86.28% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 98.05% 87.50% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 90.00% MAIN S/BOARD 100.00% 90.00% LPS NA NA PA 40.54% 51.35% SMATV 28.33% 35.18% CCTV NA NA ICT 0.00% 0.76%
  • 8. DEWAN BESAR
  • 9. DEWAN BESAR
  • 10. KEMAJUAN KERJA FIZIKAL – LOBI BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 100.00% 94.30% -5.70% MEI 09’ 98.92% 94.90% -4.02% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 93.11% 100.00% SUBMAIN CABLE 90.77% 100.00% DB 75.00% 100.00% LUMINAIRE 81.78% 100.00% MAIN S/BOARD NA NA LPS NA NA PA NA NA SMATV NA NA CCTV 73.63% 32.69% ICT NA NA
  • 11. LOBI UTAMA
  • 12. KEMAJUAN KERJA FIZIKAL – DEWAN KULIAH UTAMA BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 99.45% 81.81% -17.64% MEI 09’ 92.24% 91.71% -0.52% MECHANICAL PLANNED ACTUAL AIR COND 89.71% 90.00% FIRE FIGHTING 72.55% 75.06% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 97.65% 100.00% SUBMAIN CABLE 90.60% 100.00% DB 75.00% 100.00% LUMINAIRE 83.76% 95.00% MAIN S/BOARD 75.00% 90.00% LPS 85.82% 92.01% PA 36.40% 48.82% SMATV NA NA CCTV NA NA ICT 0.00% 29.98%
  • 13. DEWAN KULIAH UTAMA
  • 14. KEMAJUAN KERJA FIZIKAL – PUSAT SUMBER/PERPUSTAKAAN BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 100.00% 91.94% -8.06% MEI 09’ 95.30% 95.38% 0.09% MECHANICAL PLANNED ACTUAL AIR COND 88.44% 85.00% FIRE FIGHTING 38.38% 78.47% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 96.33% 95.00% SUBMAIN CABLE 90.32% 95.00% DB 85.00% 100.00% LUMINAIRE 84.09% 98.00% MAIN S/BOARD 85.00% 90.00% LPS 88.34% 96.92% PA 43.31% 54.45% SMATV 76.21% 73.61% CCTV NA NA ICT 13.59% 17.42%
  • 15. PUSAT SUMBER / PERPUSTAKAAN
  • 16. KEMAJUAN KERJA FIZIKAL – PENTADBIRAN & PENGURUSAN SUMBER BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 100.00% 88.93% -11.07% MEI 09’ 92.72% 92.73% 0.01% MECHANICAL PLANNED ACTUAL AIR COND 86.99% 89.96% FIRE FIGHTING 45.23% 40.30% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 97.36% 95.00% SUBMAIN CABLE 91.48% 92.00% DB 85.00% 100.00% LUMINAIRE 69.62% 95.00% MAIN S/BOARD 75.00% 90.00% LPS 86.00% 90.85% PA 20.34% 37.23% SMATV 69.40% 68.28% CCTV 2.36% 1.06% ICT 9.65% 12.59%
  • 17. BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER
  • 18. KEMAJUAN KERJA FIZIKAL - KAFETARIA BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 100.00% 96.14% -03.86% MEI 09’ 98.36% 98.71% 0.08% MECHANICAL PLANNED ACTUAL AIR COND 75.55% 100.00% FIRE FIGHTING 54.69% 70.73% KITCHEN EQUIP. 27.61% 34.00% LPG INSTALL. 0.00% 0.00% COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 90.94% 100.00% LUMINAIRE 94.07% 100.00% MAIN S/BOARD NA NA LPS 75.13% 88.81% PA 30.39% 43.51% SMATV 67.06% 66.02% CCTV NA NA ICT 0.00% 0.00%
  • 19. KAFETERIA
  • 20. KEMAJUAN KERJA FIZIKAL – BENGKEL TEKNOLOGI MAKLUMAT BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 99.67% 89.84% -9.82% MEI 09’ 93.95% 95.49% 1.54% MECHANICAL PLANNED ACTUAL AIR COND 79.15% 89.24% FIRE FIGHTING 29.88% 15.93% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 97.22% 95.00% SUBMAIN CABLE 94.32% 100.00% DB 93.83% 100.00% LUMINAIRE 84.21% 100.00% MAIN S/BOARD 75.00% 90.00% LPS 89.76% 96.80% PA 54.28% 61.18% SMATV 78.82% 73.97% CCTV 37.46% 20.60% ICT 4.29% 9.58%
  • 21. BENGKEL TEKNOLOGI MAKLUMAT
  • 22. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (PLASTIK) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 99.20% 94.41% -4.79% MEI 09’ 96.82% 95.67% -1.14% MECHANICAL PLANNED ACTUAL AIR COND 88.70% 88.41% FIRE FIGHTING 45.37% 45.37% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 81.45% 85.00% DUST CONTROL NA NA PROCESS COOLING 0.00% 0.00% ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 75.00% 100.00% LUMINAIRE 94.28% 100.00% MAIN S/BOARD 75.00% 90.00% LPS 92.90% 96.80% PA 62.47% 64.97% SMATV 75.18% 74.39% CCTV 55.21% 30.36% ICT 9.90% 14.40%
  • 23. BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)
  • 24. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 99.13% 94.65% -4.48% MEI 09’ 97.05% 95.65% -1.40% MECHANICAL PLANNED ACTUAL AIR COND 61.02% 78.34% FIRE FIGHTING 43.93% 32.95% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 81.45% 85.00% DUST CONTROL 31.69% 77.29% PROCESS COOLING 0.00% 0.00% ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 94.29% 100.00% MAIN S/BOARD 61.95% 90.00% LPS 84.99% 93.25% PA 53.85% 59.26% SMATV 75.26% 75.20% CCTV 56.15% 30.88% ICT 16.58% 11.59%
  • 25. BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)
  • 26. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (SERAMIK) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 98.21% 92.30% -5.91% MEI 09’ 95.12% 94.67% -0.46% MECHANICAL PLANNED ACTUAL AIR COND 86.19% 85.00% FIRE FIGHTING 41.34% 33.30% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 81.45% 85.00% DUST CONTROL 10.44% 72.95% PROCESS COOLING 0.00% 0.00% ELECTRICAL PLANNED ACTUAL WIRING 98.53% 100.00% SUBMAIN CABLE 94.89% 95.00% DB 78.00% 100.00% LUMINAIRE 90.95% 100.00% MAIN S/BOARD 85.00% 90.00% LPS 90.99% 96.49% PA 53.24% 60.41% SMATV 73.29% 74.70% CCTV 63.51% 34.93% ICT 16.96% 22.29%
  • 27. BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)
  • 28. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. JAMINAN KUALITI BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 99.71% 91.02% -8.70% MEI 09’ 94.30% 95.17% -0.87% MECHANICAL PLANNED ACTUAL AIR COND 58.17% 59.54% FIRE FIGHTING 23.90% 21.39% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 81.45% 85.00% DUST CONTROL 38.25% 60.33% PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 96.41% 95.00% SUBMAIN CABLE 92.64% 95.00% DB 92.64% 90.00% LUMINAIRE 67.10% 85.00% MAIN S/BOARD 30.09% 90.00% LPS 84.35% 96.20% PA 41.16% 53.00% SMATV 45.52% 54.97% CCTV 44.98% 24.74% ICT 3.77% 0.00%
  • 29. BENGKEL KEJ. JAMINAN KUALITI
  • 30. KEMAJUAN KERJA FIZIKAL – BENGKEL MIKRO ELEKTRONIK BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 98.51% 90.05% -8.47% MEI 09’ 92.86% 94.80% 1.94% MECHANICAL PLANNED ACTUAL AIR COND 89.48% 87.17% FIRE FIGHTING 22.33% 11.16% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 81.45% 85.00% DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 97.65% 95.00% SUBMAIN CABLE 90.51% 90.00% DB 50.09% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 90.00% LPS 88.47% 96.70% PA 52.12% 58.72% SMATV 61.66% 64.98% CCTV 58.47% 32.16% ICT 0.00% 0.00%
  • 31. BENGKEL MIKRO ELEKTRONIK
  • 32. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘B’ BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 100.00% 96.79% -3.21% MEI 09’ 100.00% 100.00% 0.00% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 100.00% FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 100.00% LPS 100.00% 95.68% PA NA NA SMATV 35.86% 48.48% CCTV 37.80% 20.79% ICT 100.00% 90.00%
  • 33. KUARTERS KELAS ‘B’
  • 34. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C’ BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 100.00% 96.94% -3.06% MEI 09’ 100.00% 100.00% 0.00% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 100.00% FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 90.00% LPS 100.00% 95.78% PA NA NA SMATV 27.51% 42.76% CCTV NA NA ICT 98.03% 62.02%
  • 35. KUARTERS KELAS ‘C’
  • 36. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C+D’ BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 100.00% 96.38% -3.62% MEI 09’ 100.00% 100.00% 0.00% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 100.00% FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 90.00% LPS 100.00% 96.33% PA NA NA SMATV 35.86% 48.48% CCTV NA NA ICT 100.00% 90.00%
  • 37. KUARTERS KELAS ‘C’ + ‘D’
  • 38. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS F ( 1 BLOK 4 TINGKAT & I BLOK 5 TINGKAT) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 99.68% 94.20% -5.48% MEI 09’ 97.14% 98.49% 1.36% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 90.00% LPS 92.69% 96.98% PA NA NA SMATV 81.76% 80.03% CCTV NA NA ICT 96.04% 90.36%
  • 39. KUARTERS KELAS ‘F’ ( 4 TINGKAT )
  • 40. KUARTERS KELAS ‘F’ ( 5 TINGKAT )
  • 41. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS G (1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 99.33% 93.98% -5.35% MEI 09’ 97.58% 98.48% 0.90% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 86.52% 90.00% LPS 100.00% 96.98% PA NA NA SMATV 81.76% 80.03% CCTV NA NA ICT 98.74% 96.73%
  • 42. KUARTERS KELAS ‘G’ ( 5 TINGKAT )
  • 43. KUARTERS KELAS ‘G’ ( 4 TINGKAT )
  • 44. KEMAJUAN KERJA FIZIKAL – DEWAN MAKAN BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 100.00% 97.34% -2.66% MEI 09’ 99.42% 99.60% 0.18% MECHANICAL PLANNED ACTUAL AIR COND 83.40% 95.00% FIRE FIGHTING 36.66% 70.31% KITCHEN EQUIP. 27.61% 34.00% LPG INSTALL. 0.00% 0.00% COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 98.00% SUBMAIN CABLE 98.49% 98.00% DB 93.59% 90.00% LUMINAIRE 100.00% 80.00% MAIN S/BOARD 100.00% 90.00% LPS 98.91% 97.32% PA 56.87% 61.20% SMATV 67.06% 71.44% CCTV NA NA ICT 100.00% 1.40%
  • 45. DEWAN MAKAN
  • 46. KEMAJUAN KERJA FIZIKAL – ASRAMA LELAKI A & B BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 100.00% 97.10% -2.90% MEI 09’ 98.70% 99.43% 0.73% MECHANICAL PLANNED ACTUAL AIR COND 51.93% 75.00% FIRE FIGHTING 39.40% 38.83% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 98.47% 99.50% SUBMAIN CABLE 92.53% 95.00% DB 76.93% 75.00% LUMINAIRE 100.00% 90.00% MAIN S/BOARD 100.00% 90.00% LPS 94.22% 97.48% PA 64.19% 66.13% SMATV 60.98% 67.30% CCTV 37.44% 20.59% ICT 79.41% 79.22%
  • 47. ASRAMA LELAKI A & B
  • 48. KEMAJUAN KERJA FIZIKAL – ASRAMA PEREMPUAN C & D BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 99.99% 97.67% -2.32% MEI 09’ 98.95% 99.37% 0.52% MECHANICAL PLANNED ACTUAL AIR COND 44.80% 75.00% FIRE FIGHTING 67.44% 46.61% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 98.41`% 99.50% SUBMAIN CABLE 94.66% 95.00% DB 75.95% 75.00% LUMINAIRE 92.74% 90.00% MAIN S/BOARD 100.00% 90.00% LPS 98.08% 97.64% PA 59.38% 63.54% SMATV 60.98% 67.30% CCTV 35.21% 19.36% ICT 85.90% 82.44%
  • 49. ASRAMA PEREMPUAN C & D
  • 50. KEMAJUAN KERJA FIZIKAL - SURAU BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 98.65% 92.10% -6.55% MEI 09’ 95.20% 92.10% 0.69% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING 89.00% 0.00% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 95.52% 100.00% SUBMAIN CABLE 93.11% 100.00% DB 100.00% 100.00% LUMINAIRE 52.31% 100.00% MAIN S/BOARD 85.00% 90.00% LPS 88.76% 96.24% PA 29.36% 44.39% SMATV NA NA CCTV NA NA ICT NA NA
  • 51. SURAU
  • 52. KEMAJUAN KERJA FIZIKAL - ASTAKA BANGUNAN SOKONGAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 100.00% 98.86% -1.14% MEI 09’ 99.80% 99.83% 0.04% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING 82.47% 0.00% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 98.67% 100.00% MAIN S/BOARD 100.00% 100.00% LPS 85.72% 93.89% PA 38.16% 49.36% SMATV NA NA CCTV NA NA ICT NA NA
  • 53. BANGUNAN SOKONGAN ASTAKA
  • 54. KEMAJUAN KERJA FIZIKAL – M&E PLANT ROOM BANGUNAN SOKONGAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 100.00% 100.00% 0.00% MECHANICAL PLANNED ACTUAL AIR COND 96.91% 88.04% FIRE FIGHTING 32.54% 29.75% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 95.00% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 0.00% LUMINAIRE 89.07% 85.00% MAIN S/BOARD 28.42% 100.00% LPS NA NA PA NA NA SMATV NA NA CCTV NA NA ICT NA NA
  • 55. BANGUNAN SOKONGAN M&E PLANT ROOM – PUSAT SUMBER
  • 56. BANGUNAN SOKONGAN M&E PLANT ROOM - BENGKEL
  • 57. DECORATIVE FENCE
  • 58. BANGUNAN SOKONGAN GARAJ KENDERAAN
  • 59. ELEVATED WATER TANK, PUMP HOUSE & SUCTION TANK
  • 60. WAKAF
  • 61. LALUAN BERBUMBUNG
  • 62. OPEN PLAZA
  • 63. KERJA INFRA – JALAN UTAMA
  • 64. GELANGGANG PERMAINAN
  • 65. GELANGGANG PERMAINAN - TENIS
  • 66. VINYL FLOORING : CLEANROON
  • 67. VINYL FLOORING : BENGKEL
  • 68. ACOUSTIC WALL : DEWAN BESAR
  • 69. ACOUSTIC WALL & CEILING : DEWAN KULIAH
  • 70. KITCHEN HOOD : CAFETERIA
  • 71. KABINET DAPUR : KUATERS KELAS G
  • 72. PERABUT ASRAMA PELAJAR
  • 73.